Reference no: EM132510440
The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all materials are added at the beginning of the process.
Work in process, January 1, 9,200 units, 70% completed $110,308*
*Direct materials (9,200 × $9.40)$86,480 Conversion (9,200 × 70% × $3.70)23,828 $110,308
Materials added during January from Weaving Department, 141,600 units $1,345,200
Direct labor for January 227,092
Factory overhead for January 277,556
Goods finished during January (includes goods in process, January 1), 143,200 units -Work in process, January 31, 7,600 units, 45% completed.
Question a. Find cost of production report for the Cutting Department.