The Cutting Department of Karachi Carpet Company provides the following data for January. Assume that all materials are added at the beginning of the process.

Work in process, January 1, 9,200 units, 70% completed $110,308*

*Direct materials (9,200 × $9.40)$86,480 Conversion (9,200 × 70% × $3.70)23,828 $110,308

Materials added during January from Weaving Department, 141,600 units $1,345,200

Direct labor for January 227,092

Factory overhead for January 277,556

Goods finished during January (includes goods in process, January 1), 143,200 units -Work in process, January 31, 7,600 units, 45% completed.

Question a. Find cost of production report for the Cutting Department.

Reference no: EM132510440

Questions Cloud

How is there still albinism : There are many plants that still cross and make albino offspring. If albinism is always fatal, how is there still albinism?
Compute the accounting rate of return : Compute the accounting rate of return using the initial required investment. Compute the net present value of the investment. Compute the payback period.
Make a connection between genetic drift and bottleneck : Make a connection between genetic drift and bottleneck by using an example that is either real or hypothetical.
Describe the phases of the cell cycle : The cell cycle is fundamental to the reproduction of eukaryotic cells. (a) Describe the phases of the cell cycle.
Find cost of production report for the cutting department : Find cost of production report for the Cutting Department. The Cutting Department of Karachi Carpet Company provides the data
Digital technology and social networks : How does digital technology and social networks affect our social and interpersonal skills? Is social media actually making us less social?
Explain the negative feedback mechanism : Draw a flow chart diagram to explain the negative feedback mechanism of temperature regulation when body temp drops below normal.
Determine the direct materials cost per equivalent unit : Assuming that the direct materials cost is the same for November and December, did the conversion cost per equivalent unit increase, decrease
Find the volume of the solid enclosed by the cylinder : Use a triple integral to find the volume of the solid enclosed by the cylinder y - z2 and tne planes z - 0 and y- z3. If this volume V

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd