Explain what is the duration of the critical path

Assignment Help Operation Management
Reference no: EM13791046

1. The network below represents a project being analyzed by Critical Path Methods. Activity durations are indicated on the network.

a. What is the duration of the critical path?

b. Calculate the amount of slack time at activity H.

If activity I were delayed by ten time units, what would be the impact on the project duration?

2. A department chair wants to monitor the percentage of failing students in classes in her department, Each class had an enrollment of 50 students last spring. The number of failing students in the 10 classes offered that term were 1, 4. 2, 0. 0, 0, 0, 0, 0, and 3, respectively. Graphically evaluate the quality of this process.

3. Tobacco is shipped from North Carolina to a cigarette manufacturer in Cambodia once a year. The reorder point, without safety stock is 200 kilos. The carrying cost is $15 per kilo per year, and the cost o a stock out is $70 per kilo per year. Given the following, how much safety stock should be carried?

Lead Time Demand (kilos)

Probability

0

0.1

100

0.1

200

0.2

300

0.4

400

0.2

4. Janelle' s Car Wash takes a constant time of 4.5 minutes in its automated car wash cycle. Autos arrive following a Poisson distribution at the rate of 10 per hour. Janelle has asked you to calculate:

a. The average time a car will wait in line for the car wash.

b. The average number of cars waiting in line for the car wash.

Reference no: EM13791046

Questions Cloud

Contribution in the evolution of international banking : 1. Research the Rothschilds and briefly discuss its contribution in the evolution of International Banking. 2. Research the Medicis of Florence and briefly discuss its contribution in the evolution of International Banking.
Describe about the barnum effect : the Barnum effect
Tools for nonfinancial managers issues : Based on your readings or your own personal experience, how do different departments in a hospital receive financial information?
Contract negotiations and risks and operating margins : In the scenario, the contract negotiations between North Creek Healthcare and the community hospital concluded with an agreement on non-financial (legal) terms. Suggest the most critical element of the contract and the impact to the short-term and..
Explain what is the duration of the critical path : What is the duration of the critical path. Calculate the amount of slack time at activity H.
Write about counterargument and ideas for rebuttal : Write about At least one counterargument and ideas for rebuttal and At least two claims, building upon research and assignment.
Field of international banking and finance : Discuss how you will be applying the material you have learned in this class in your current or future career.
The impact of educational video games on the children : the impact of educational video games on the children
Regional alternative energy resource : If you were given the option, would you choose to purchase your energy from alternative resources? Explain your reasoning.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd