Important information about Project Variances-earned Value Analysis

A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI?

Reference no: EM1343635

Questions Cloud

Examination of change project : Examination of change project - Explain a change project that your present or past organization has been involved wit
Explain a work-related situation you feel could be improved : Project management - Explain a work-related situation you feel could be improved
Develop a cost estimation for a project : Information Systems Questions - What elements need to be considered in developing a cost estimation for a project?
Project management- classification of tasks : Project Management- classification of tasks - To organize such a project what kinds of tasks will you closely monitor so that the project does not slip.
Explain what are the spi and cpi : What are the cost and schedule variances for the project and What are the SPI and CPI?
Question related to project variances-earned value analysis : Explain what are the spending and schedule variances for the project? What are the SPI and CPI?
Operations management - production facility location : Where would you locate a clothing manufacturer that makes light-weight jackets out of cotton and what factors would influence your decision on where to locate that facility?
Chances of risk events : Explain what is the significance of this phenomenon to a project manager
Resist changes to the project baseline : Resist changes to the project baseline - Why is it important for project managers to resist changes to the project baseline

Reviews

Write a Review

Project Management Questions & Answers

  Macro and micro project risk management

Macro and Micro project risk management - describe the difference between Macro and Micro risk management.

  Changes to projects scope-schedule and cost impact

Describe how changes to a projects Scope, Schedule and Cost impact a project baseline.

  Important in decision to terminate a project

What are the different types or varieties of terminating a project? Explain when each type of project termination should be considered.

  Perform a limited scope risk assessment

Perform a limited scope risk assessment of A T & T, the telecommunications giant. Gather relevant intelligence on the company, such as the latest press releases, articles, and SEC 10K filings.

  What types of risks are inherent in a project

Project Management Risks - What types of risks are inherent in a project

  Principles of emotional intelligence

Describe how you can apply the principles of emotional intelligence to your current situation?

  Operation budgeting

How much was the rate variance and based on the above, how would you rate the head housekeeper, considering the dollars spent? Use figured to support your answer.

  Public activity in the u.s. economy

Provide the reasons why this activity is a major part of the public activity in the U.S. economy.

  Stakeholders and accounting ethics

Mike Singletary, president of Singletary industries, wishes to issue a press release to bolster his company's image and maybe even its stock price which has been gradually falling. Who are the stakeholders in this situation?

  Potential negative impacts on the organization

Identify potential negative impacts on the organization.

  Calculating pv ev and ac

With the Cost one calculates PV EV and AC.

  Determining early and late start and finish times

Determine the early and late start and finish times and the slack times for the activities. Identify the critical path.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd