Explain what are the critical path activities

Assignment Help Operation Management
Reference no: EM13731732

Problem 1

The following data were obtained from an in-house MIS project-

Activity Duration Predecessors 

A        3 Days   ---          

B        6 Days   ---          

C        3 Days   B            

D        2 Days   A            

E        3 Days   C,D          

F        2 Days   A            

G        4 Days   F            

H        7 Days   B

I        2 Days   C,D

J        4 Days   H,I

K        8 Days   H,I

L        5 Days   E,G,Ja) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity C? Show your calculations.

d) What is the slack or float for Activity F? Show your calculations.

e) What is the slack or float for Activity E? Show your calculations.

f) What is the slack or float for Activity J? Show your calculations.

Problem 2.

A project to remodel an office area has the following activities.

Activity

Duration

Predecessors

A

3 months

---

B

2 months

---

C

3 months

---

D

4 months

A, B

E

3 months

A

F

2 months

B, C

G

2 months

F

H

1 month

G

I

4 months

D, E, F

J

5 months

H

a) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity B? Show your calculations.

d) What is the slack or float for Activity D? Show your calculations.

e) What is the slack or float for Activity F? Show your calculations.

f) What is the slack or float for Activity I? Show your calculations.

Problem 3

Information from a room addition project:

 

 

Duration

Predecessors

 

A

2 wks

 

 

B

3 wks

 

 

C

5 wks

 

 

D

7 wks

A

 

E

3 wks

B

 

F

2 wks

C

 

G

4 wks

F

 

H

1 wk

A

 

I

8 wks

D, E, G

 

J

5 wks

F

 

K

2 wks

D, E, G, H

 

 

 

 

 

a) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity A? Show your calculations.

d) What is the slack or float for Activity F? Show your calculations.

e) What is the slack or float for Activity H? Show your calculations.

f) What is the slack or float for Activity K? Show your calculations.

Problem 4

InformAtion from a site renovation project:

Task     Duration            Predecessors

A          2 wks               _

B          5 WKS             A

C          3 WKS             B

D          15 WKS           B

E          8 WKS             C

F          10 WKS           C

G         2 WKS             D

H          6 WKS             E, F, G

I           5 WKS             H

a) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity C? Show your calculations.

d) What is the slack or float for Activity F? Show your calculations.

e) What is the slack or float for Activity I? Show your calculations.

f) What is the slack or float for Activity K? Show your calculations.

Reference no: EM13731732

Questions Cloud

Is the following argument valid or invalid : Is the following argument valid or invalid? If valid, explain whether it is deductive or inductive. If invalid, explain why: "Mrs. Kelvin has accused me of intentionally denting her rear fender
What is the service level implied by ben''s reorder point : Suppose Ben decides to reorder 35 mm film when there are 86 rolls left in stock. How much safety stock is implied by this reorder point. What is the service level implied by Ben's reorder point of 86 rolls
Decision and discuss the effects : Explain which change model you would follow for the short-term change and which you would follow for the long-term change. Provide rationale for your decision and discuss the effects that these changes would have on the employees, managers, and ex..
How much each country consume each good : Think of a 2 country world, say the US and the UK. Each country produces two goods, say food and cloth. Suppose 7 hours of labour are required to produce one unit of either good in the UK, whereas in the US it takes 2 hours to produce one unit food a..
Explain what are the critical path activities : What are the critical path activities. What is the project's scheduled completion time. What is the slack or float for Activity C
About database design and methodology : We learned about database design and methodology. You are the database administrator for your company, which has just acquired a company called SNHU Appliances. You are deciding what the best approach is. Should you merge your database with the new c..
Specify the most significant advantages and disadvantages : Specify the most significant advantages and disadvantages that could be realized by the organization in adopting a server virtualization infrastructure. Prepare a plan for implementing Hyper-V (or an alternate solution, such as VMware) as a solution ..
General aggregate statistics: total number of tickets sold : Present the data in a professionally formatted worksheet such that it is easily viewed/understood. Since visualization aids in understanding data, include an appropriate chart to illustrate each set of data. Lastly, analyze the data and provide any c..
What strategies could you and new soft drink company use : According to Porter's discussion of industry analysis, is Pepsi Cola a substitute for Coca Cola? what strategies could you and your new soft drink company use to impact the dominance of Pepsi and Coke in the global marketplace? Why

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd