Explain a WBS created for a project

Assignment Help Project Management
Reference no: EM132949834

Question: A major national insurer decided to evolve new business development practices. The project to implement this idea started in 2000 and was led by a succession of key senior vice presidents (VPs) as part of their executive growth.

Twelve years later, the organization had still not finished with its stated purpose due to changing requirements, new ideas, a succession of leaders, and executive ambivalence. This effort had all the appearance of a major strategic initiative-three hundred people, a "war room" with a great storyboard, and lots of spokespersons. Key staff members were quick to extol the great progress made. However, when the new CEO asked, "Why are we doing this?" there was no coherent answer. Result: Within days, the entire program was scrapped. In less than a week, the project offices were vacant and phone calls went unanswered.

When the project died, no one noticed except the executives who had been the project advocates. They were out of a job. For the first part of your post, address the following question:

Analyze the root cause of this situation. There was a huge disconnect between project management and the organizational strategy and strategic direction in this scenario. How could this gap have been bridged? Then, address one of the following bullets. Analyze the triple-constraints relationship among a project scope, cost, schedule, and quality. If quality is held constant and the scope is widened, what will happen to the cost and schedule?

Explain a WBS created for a project you have worked on. Did the team refer to the WBS while sequencing work and creating a risk plan? What was the outcome? If not, describe how the team determined tasks and sequencing.

Evaluate the outcome. Cite additional challenges to a project that might result from poor work breakdown practices. The final paragraph (three or four sentences) of your initial post should summarize the one or two key points that you are making in your initial response. Justify your answers with examples and reasoning. Comment on the postings and views of at least two peers. Your posting should be the equivalent of 1 to 2 pages (500-1000 words) in length.

Reference no: EM132949834

Questions Cloud

Analyze the different types of procurement contracts : Analyze the different types of procurement contracts. Include an evaluation of the risk level associated with each type of contract. Propose the procurement
How much monthly interest will be added to the account : How much monthly interest will be added to his account? Assume that the balance is computed by the average daily balance method.
What was the balance of utilities payable at the beginning : At the end of 2021, utilities payable equals $50,000 and utilities expense equals $175,000. What was the balance of utilities payable at the beginning of 2021?
What is the company wacc for mullineaux corporation : Its cost of equity is 11.4 percent, and the cost of debt is 6.1 percent. The relevant tax rate is 24 percent. What is the company's WACC?
Explain a WBS created for a project : Explain a WBS created for a project you have worked on. Did the team refer to the WBS while sequencing work and creating a risk plan? What was the outcome
Prepare the consolidated financial statements of Berry Ltd : Prepare the consolidated financial statements of Berry Ltd and its controlled entity for the reporting period ending 30 June 2020
What is the company wacc for huntington power co : What is the company's WACC for Huntington Power Co? Assume the company's tax rate is 23 percent. Common stock: 480,000 shares outstanding, selling for $78.
What is the firm market value capital structure : What is the firm's market value capital structure? (Do not round intermediate calculations and round your answers to 4 decimal places, e.g., .3216.)
Should B product be processed further : The cost of further process per unit is $5 per unit, and can be sold for $36 per unit. Should B product be processed further

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd