Example of a liquidated damages clause

Assignment Help Business Law and Ethics
Reference no: EM133655911

Assignment:

1). Which of the following is an example of a liquidated damages clause?

a.This contract will automatically terminate in the event that the purchaser orders less than the quota for four consecutive weeks.

b. If the supplier fails to deliver the weekly supply of products to the retailer on or before the first day of each week, the supplier shall pay the retailer $100.00 for each day that the delivery is late.

c. The supplier shall not be liable to the retailer in respect of any losses, damages, costs or claims resulting from circumstances that are not within the control of the supplier.

d. This is the entire agreement between the parties, covering everything agreed or understood in connection with the subject matter of this transaction. No oral promises, conditions, warranties, representations, understandings, or interpretations were relied on by either party to execute this contract.

2). A contract under which businesses purchase inventory or supplies falls under which category?

a. Employment contract

b. Insurance contract

c. Contract for the purchase and sale of goods

d. Leasing contract

3). Family members or friends who enter into unwritten business agreements with one another may have difficulty proving they intended the agreement to be legally binding.

a.True

b. False

4). Written contracts are usually preferable to verbal contracts because...

a. Written contracts provide the parties with a record of their rights and obligations.

b. Written contracts provide proof of the parties' agreement in the event of a dispute.

c. All of the above

d. None of the above

5). If you shake hands on the essential terms of a business transaction, it will not be legally binding until a contract is written up and signed by the parties.

a. True

b. False

6). Advertising agreements commonly take the form of standard form contracts.

a. True

b. False

7). What constitutes a breach of contract?

a. A product fails to meet the quality specified in the contract

b. A product is not delivered

c. No payment is made

d. All of the above

8). A party to a contract might choose to include a condition subsequent clause in a contract:

a. if there is a risk of forfeiting a deposit if a deadline is missed.

b. if it does not want to be bound to the terms of the contract if a certain situation arises.

c. to avoid the high cost of litigation if the contract is breached

d. to ensure any dispute will be resolved according to the law in a designated jurisdiction.

9). Consideration means that the parties must provide something of value to each other.

a. True

b. False

10). If a term in a contract is ambiguous and the parties disagree on its meaning, how will a judge resolve the dispute?

a. In favour of the drafter

b. Against the drafter

11). Which one of the following agreements is most likely to be deemed legally binding?

a. Diana enters into an agreement to sell her diamond sapphire ring to Kate, her work colleague.

b. Janelle, a minor, enters into a loan agreement with Unibond Financial Services for $5,000.00

c. Wendy suffered from a severe mental disability for many years and entered into an agreement to sell her rare stamp collection

d. Norm and Cliff, two businessmen, negotiate an agreement after sharing a bottle of whiskey, and two cases of beer.

Reference no: EM133655911

Questions Cloud

What could be done to better manage a prison : Why is it important to consistently implement policies and procedures within a prison? In your opinion, what could be done to better manage a prison?
Should the press have the freedom to publish anything : Should the press have the freedom to publish anything? What limitations on student publications violate the student's rights under the First Amendment?
Why is insanity a legal term-not a psychiatric distinction : Consider serial killer Ed Gein. After reading about him in Chapter Three, do you believe he was suffering from psychosis, or rather was he a psychopath?
Why is crime scene management important : Why is crime scene management important?
Example of a liquidated damages clause : Which of the following is an example of a liquidated damages clause? A contract under which businesses purchase inventory-supplies falls under which category?
Should migrants and trafficking victims be treated the same : Should migrants and trafficking victims be treated the same or differently in regard to services provided upon rescue or arrival at their destination?
What are rules rules that can be violated by us citizens : What kind of enforcement cases are brought against them when individuals or entities violate agency regulations.
What are issues in education and mississippi code of ethics : What are three (3) court cases related to Issues in Education and Mississippi Code of Ethics Standards 4 and 7, that are within 10 years?
Research the nexis-uni legal database lawsuit : Research in the NEXIS-Uni legal database LAWSUIT: Amazon Callously Fired Employee For Seeking Time Off After Both Parents Died.

Reviews

Write a Review

Business Law and Ethics Questions & Answers

  Legal environment of business caselet

The assignment in Law deals with the topic "Legal Environment of Business". A case study about Mary, a newly joined employee who is working in the USA and Europe. She faces few issues at her work place in Europe and tries to talk to her manager who s..

  Business ethics & legal issues caselet

This assignment is about the concept of Business Ethics & Legal Issues. The laws relating to these can be found in Antitrust laws. These laws are concerned with those large corporations which have a majority of market share, mergers and acquisitions.

  Questions on business law and ethics

Examples of securities that are exempted from the registration provisions of the 1933 Act and involving misstatement of material facts in a prospectus.

  Discuss the doctrine of ratification of pre-incorporation

With the aid of a decided cases, discuss the doctrine of ratification of pre-incorporation contract.

  Discuss the extent of phoenixing activity

It has been estimated that about 6,000 phoenix companies operate in Australia, costing government and the community hundreds of millions of dollars per year and impacting on individuals.

  Application of law to facts

Company Law, Application of Law to Facts and Conclusion.

  Question on business law and ethics

This assignment related to business law.

  Questions on business law

Answer all the questions under business law.

  Iidentify the issue raised by the facts

Iidentify the issue(s) raised by the facts, identify the relevant legal principles, apply the relevant legal principles to the facts, reach a conclusion.

  Evaluation of software development

Prepare a report and present an evaluation of the subsequent methodologies for software development in terms of cost, resources and time.

  Business value and ethics

Business value and ethics,  Bart agrees to put Sam's Super Bowl champion-ship autographed football in his sports store to sell for $1,500. Sam agrees to pay Bart a 15% commission for selling the ball. If Joe comes in the sports store and offers Bart ..

  Explain what is meant by income by ordinary concepts

Advise what tax consequences arise in respect of the payments.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd