Evaluate the cause and continue producing way

Assignment Help Project Management
Reference no: EM1345514

You began a process charting procedure 5 weeks ago. Today, for the first time sample ranges are falling below the lower control limit on the range chart. You plan to stop the process, reasoning that customers will be upset. Your friend Dave argues, however, that the quality changes are due to an operator training program and are good.

What should you do?

A. It sounds like Dave is right, so try to evaluate the cause and continue producing this way.

B. It sounds like Dave is right so do nothing

C. Stop production and get the process right

D. Investigate the chart construction because values cannot fall below the lower control limit on a range chart

Reference no: EM1345514

Questions Cloud

Managing exchange rate risk : Assume China suddenly decided to change its mind. Overnight, instead of increasing its value China decided to devalue downwards the Yuan by 20% in order to increase the attractiveness of its exports.
Is my teams enthusiasm part of the problem : What do you do? Was Joe's comment symptomatic of a larger problem within his group and was he simply exhausted from a tight deadline? Is my team's enthusiasm part of the problem? Or is this one of those squeaky wheel problems?
Find out the equivalent resistance outside the battery : Fairgoers ride a Ferris wheel with a radius of 4.35m, the bottom of which is 1.75m from the ground. The wheel completes one revolution every 30s. A passenger drops his keys when he is three quarters of the way up and at the 10 o'clock position. Wh..
Increasing the stock variance : The standard deviation of the market index portfolio is 20 percent. Stock A has a beta 1.5 and residual standard deviation of 30 percent.
Evaluate the cause and continue producing way : Stop production and get the process right and investigate the chart construction because values cannot fall below the lower control limit on a range chart
The central bank can do so by stimulating consumption : The Central Bank of Muji wishes to eliminate the recessionary gap while expansionary monetary policy. The central bank can do so by stimulating consumption and planned investment.
Staffing level requirements for project team : Describe in scholarly detail how you would use WBS as aid to finding staffing level requirements for project team?
Rank the magnitudes of the forces : Rank the magnitudes of the forces exerted on the following particles from largest to smallest. In your ranking, display any cases of equality. (Use only ">" or "=" symbols. Do not contain any parentheses around the letters or symbols.)
Find the price of stock : Piedmont Enterprises currently pays a dividend of $1 per share. This dividend is expected to grow at a 20% per year for the next two years, after which it is expected to grow at 6% per year for the foreseeable future.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd