Estimates can be used as crash times

Assignment Help Operation Management
Reference no: EM1377358

Q. Discussion Questions:

1. Develop a network drawing for Hill Construction also Conclude the critical path. Explain how long is the project expected to take?

2. Illustrate what is the probability of finishing in 270 days?

3. If it were necessary to crash to 250 or 240 days, explain how would Hill do so also at illustrate what costs? As noted in the case, Assume which optimistic time estimates can be used as crash times

 

 

Reference no: EM1377358

Questions Cloud

Fully explain and define the functions and necessary : Fully explain and define the functions and necessary characteristics of an operative project manager.
Explain how do change agents affect your organization : Explain how can an organization overcome employees' resistance to change. Explain how does your organization respond to planned also unplanned change. Explain how do change agents affect your organization.
What are mize''s diluted earnings per share for 2013 : Shares of common stock outstanding during 2013. mize's 2013 net income was 160,000 and the income tax rate was 30 percent. What are Mize's diluted earnings per share for 2013.
If loss aversion denotes to people''s tendency to strongly : If loss aversion denotes to people's tendency to strongly prefer avoiding losses to acquiring gains, for the reason that losses are twice as powerful psychologically
Estimates can be used as crash times : If it were necessary to crash to 250 or 240 days, explain how would Hill do so also at illustrate what costs. As noted in the case, Assume which optimistic time estimates can be used as crash times.
Evaluate the correct inventory amount : Premier Bank and Trust is giving Alou Company a loan. Before doing so, management decides that added discussions with Alou's accountant may be desirable.
How are casino''s as well as gambling forums able to generate : How are Casino's as well as gambling forums able to generate a maximum profit while catering to both risk averse and risk loving people
Then prepare another detailed schedule that cracks : Then prepare another detailed schedule that cracks your project duration by nine months. Save both schedules as PDF files
Analyze three works of art from : Select three works of art that are from the similar time period or style and that have a same theme. Works must come from one of styles or time periods that we study in Unit four or Unit five.

Reviews

Write a Review

Operation Management Questions & Answers

  Describe process velocity also efficiency for the clinic

Oakwood Outpatient Clinic is analyzing its operation in an effort to improve performance. Describe process velocity also efficiency for the clinic.

  Illustrate what leadership approach would you have taken

Depended on the Hersey-Blanchard theory, should Terrill have been less participative. Should he have initiated more task structure for the engineers. Illustrate what leadership approach would you have taken in this situation.

  Why is participation considered such an effective technique

Why is participation considered such an effective technique for reducing resistance to change. Describe at least 3 other tactics which are also useful to reduce resistance to change.

  Explain how many seats should super discount overbook flight

Super Discount considers the cost of flying the plane from New York to L.A. a sunk cost. By explain how many seats should Super Discount overbook the flight.

  Illustrate what problems might an organization encounter

Illustrate what problems might an organization encounter in doing AAP that it might not encounter in regular staffing planning.

  Find out the value of the policy variable

Twelve containers are authorized for the part. Recall which p-bar is the average processing time per container not per individual part. Find out the value of the policy variable, α, which expresses the amount of implied safety stock in the system.

  What extent would attraction also retention initiative

A capacity alternative has an initial cost of $50,000 also cash flow of $20,000 for each of next four years. If cost of capital is 5 percent, net present value of this investment is approximately.

  Illustrate what size tool and fwad tractor would be needed

Assuming it needs to be pulled at 5 mph, illustrate what size tool and FWAD tractor would be needed. For each working day you can average 8 hours in the field and field efficiency is 80%.

  Peer-reviewed article that reports original research

Illustrate the business research and its purpose. Describe the business problem(s) under investigation.

  Appropriate research method for customer satisfaction

The solution is detailed and dsecribes the concepts very well. The solution is very simple to understand as well. All the steps are clearly shown which makes it very easy for anyone to follow. Overall, an excellent response to question being asked..

  What is the average hourly output

Assume the packing of the two components is totally automated also is small enough which you can ignore it. Illustrate what is the average hourly o/p, in terms of the number of units of packaged product (which includes one component A also one com..

  Which machine would you select when trying maximize payoff

the expected benefit of selecting machine B is $80,000 with a probability of 50percent also the expected benefit of selecting machine C is $60,000 with a probability of 75percent.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd