In 2016, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,100,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2016, is as follows:
Accounts receivable (from construction progress billings): $35,000
Construction in progess: $150,000
Less: Billings on construction contract: (143,000)
Cost and profit of uncompleted contracts in excess of billings: 7,000
Required:
1. What was the cost of construction actually incurred in 2016?
2. How much cash was collected in 2016 on this contract?
3. What was the estimated cost to complete as of the end of 2016?
4. What was the estimated percentage of completion used to calculate revenue in 2016? (Do not round intermediate calculations. Round your percentage answer to 2 decimal places.)
What examples of regulatory efforts might prohibit entrance
: What examples of regulatory efforts might prohibit entrance into a free market? Would regulatory oversight of environmental pollution for a cement factory create any externalities?Must be about 250 words APA format with at least one credible referenc..
|
What are some examples of regulated communities
: What are some examples of regulated communities holding the most power over government's regulatory authority? What are the risks under this scenario?NEEDS TO BE 250 Words following APA format with at least one credible reference
|
Selection of balanced scorecard items
: The International Accountants' Association is a professional association. Its current membership totals 110,000 worldwide. The association operates from a central headquarters in New Zealand but has local membership chapters throughout the world. The..
|
Qualifies as capital lease calls for annual lease payments
: A lease agreement that qualifies as a capital lease calls for annual lease payments of $26,269 over a six-year lease term, with the first payment at January 1, the lease’s inception. The interest rate is 5%. If lessee’s fiscal year is the calendar ye..
|
Estimated percentage of completion used to calculate revenue
: In 2016, Long Construction Corporation began construction work under a three-year contract. The contract price is $2,100,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. What was the cost ..
|
Calculate the missing amounts for each year
: The following selected data are adapted from the November 27, 2011, and November 28, 2010, consolidated balance sheets
|
Domestic production activities deduction
: Sarah Ham, operating as a sole proprietor, manufactures printers in the United States. For 2015, the proprietorship has QPAI of $400,000. Sarah's modified AGI was $350,000. The W–2 wages paid by the proprietorship to employees engaged in the qualifie..
|
Prepare master budget for first four months of operations
: Morganton Company makes one product and it provided the following information to help prepare the master budget for its first four months of operations: The budgeted selling price per unit is $60. Budgeted unit sales for June, July, August, and Septe..
|
Consolidated balance sheets and income statements
: Apple Inc. Selected data from the September 24, 2011, and September 25, 2010, consolidated balance sheets and income statements for the years then ended for Apple Inc. follow.
|