Estimated duration of the project and float of each activity

Assignment Help Project Management
Reference no: EM131596293

PROJECT MANAGEMENT / MANAGEMENT OF ENGINEERING PROJECTS

A Project is comprised of 15 tasks.

Tasks 1, 2, 3 and 4 can start concurrently and their durations are 10, 11, 12 and 13 days respectively. Tasks 5, 6, 7 and 8 have durations of 10, 9, 8 and 7 respectively and task 5 can start 5 days after task 1 has started. Task 2 must be completed before task 6 can be started and task 7 follows on from task 3. Task 8 can be started 2 days after task 4 has been completed. Tasks 9, 10, 11 and 12 have durations of 5, 6, 7 and 8 days respectively. Tasks 13, 14 and 15 have durations of 5, 4 and 3 days respectively. Task 9 starts 3 days after task 5 finishes and task 10 starts once tasks 5 and 6 are complete. Task 11 cannot start before tasks 6 and 7 are completed and task 12 is dependent on the completion of tasks 7 and 8. Task 13 commences after tasks 9 and 10 are finished and task 14 cannot start until tasks 10 and 11 are finished. Task 15 can start 3 days after the start of task 11 but only if task 12 is complete. The project is complete when tasks 12, 13, 14 and 15 are complete.

Construct a work break down table showing the interdependencies of the tasks and show this graphically using a flowchart.

Construct an activity on node diagram to identify the critical path, estimated duration of the project and the float of each activity.

Reference no: EM131596293

Questions Cloud

How is linear regression related to correlation : How is linear regression related to correlation? Describe each element of the linear regression equation and the information that it contributes.
What is the cost of retained earnings : The flotation cost is $6. What is the cost of retained earnings?
Taste a bottle of meritage and report on these criteria : Taste a bottle of Meritage and report on these criteria when sharing your findings with the class. Remember to use Zraly's 60 Second Wine Expert methodology.
Compare and contrast the pictures of god found : How does the notion of God in Christianity differ from the notion of God in Islam?compare and contrast the pictures of God found ?
Estimated duration of the project and float of each activity : Construct an activity on node diagram to identify the critical path, estimated duration of the project and the float of each activity
The principle of diversification : The principle of diversification does not refer to which of the following statement.
Privatization of the social security system : Suppose that the privatization of the social security system raises the savings rate (and, hopefully, the investment rate) in the U.S.
Describe the primary ethical theory : Synthesize your learning from the course with the aim of determining an appropriate ethical position and moral practice regarding an ethical dilemma.
The american taxpayer relief act : The American Taxpayer Relief Act of 2013

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd