Question 1: Fletcher Company collected the following data regarding production of one of its products. Compute the total direct materials cost variance.
Direct materials standard (1 lbs. @ $3/lb.) $3 per finished unit
Actual direct materials used 30,000 lbs.
Actual finished units produced 26,000 units
Actual cost of direct materials used $80,600
Option 1: $12,000 favorable.
Option 2: $2,600 unfavorable.
Option 3: $12,000 unfavorable.