Reference no: EM132590591
XYZ Manufacturing has identified two major activities, set ups and equipment maintenance. The following are estimated annual cost for each activity and expected quantity of the cost drivers for next year:
Overhead Item Expected Cost Cost Drivers Expected Quantity
Setup costs RM 960,000 Number of setups 4,800 set ups
Maintenance RM 640,000 Machine hours 64,000 Mhrs
The following is one of the jobs that XYZ Manufacturing is planning to work on nest year:
Job X
Direst material RM 10,000
Direct Labor RM 15,000
Units completed 650 units
Direct labor hours 180 DLHrs.
Number of setups 12 setups
Machine hours 360 MHrs.
Question A. Using traditional method and direct labor hours as cost driver , estimate the total costs to complete Job X. Next year XYZ Company expected 40,000 direct labor hours were needed.
Question B. Calculate Job X total costs using activity based costing method