Write a 350-word paper that compares and contrasts the approaches to costing in E17.15 and E18.10. Distinguish production procedures that match with process costing from those that correspond with job order costing. Additionally, explain how job order costing, when used in conjunction with activity-based costing, can contribute to the allocation of indirect costs.

EXERCISE 17.15

Using ABC to Determine a Bid Price

Spear Custom Furniture uses an activity-based cost accounting system to apply overhead to production.

The company maintains four overhead cost pools. The four cost pools, and their budgeted amounts for the upcoming period, are as follows:

Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $40,000
Materials handling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20,000
Set-ups . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10,000
Quality control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45,000

Four cost drivers are used by Spear to allocate its overhead cost pools to production. The four cost drivers, and their budgeted total levels of activity for the upcoming period, are shown below:

Machine hours (to allocate maintenance costs) . . . . . . . . . . . . . . . . . . . . . . . 600 hours
Material moves (to allocate materials handling costs) . . . . . . . . . . . . . . . . . . 400 moves
Set-ups (to allocate set-up costs) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100 set-ups
Number of inspections (to allocate quality control costs) . . . . . . . . . . . . . . . . 300 inspections

The company has been asked by Cosmopolitan University to submit a bid for tables to be used in a new computer lab. The plant manager feels that obtaining this job would result in new business in future years. Estimates for the Cosmopolitan University project are as follows:

Direct materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $14,000
Direct labor (500 hours) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $15,000
Number of machine hours . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
Number of material moves . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
Number of set-ups . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Number of inspections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

a. Estimate the total cost of manufacturing the tables for Cosmopolitan University.

b. Determine the company's bid price if bids are based upon the total estimated manufacturing cost of a particular project, plus 75 percent.

EXERCISE 18.10

Process Costing through

Two Departments:

Department I

Accessory World makes floor mats for the automobile industry. Finished sets of mats must pass through two departments: Cutting and Coating. Large sheets of synthetic material are cut to size in the Cutting Department and then transferred to the Coating Department, where each set is sprayed with a chemical coating for improved durability. The following information pertains to May activity the Cutting Department:

Cost data:
Total cost of beginning inventory on May 1 . . . . . . . . . . . . . . . . . . . . . . . . . $ 44,800
Direct materials costs incurred in May. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 200,000
Conversion costs incurred in May . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87,200
Physical units data:
Units in process, May 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8,000 sets
Units started in May . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50,000 sets
Units in process, May 31 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10,000 sets
Percentage of completion data:
Direct materials, May 1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100%
Conversion, May 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80
Direct materials, May 31. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100%
Conversion, May 31 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

a. Prepare a schedule showing: (1) the number of mat sets transferred from the Cutting Department to the Coating Department in May, and (2) the number of mat sets started and completed by the Cutting Department in May.

b. Compute the equivalent units of input resources for the Cutting Department in May.

c. Compute the cost per equivalent unit of input resource for the Cutting Department in May.

d. Prepare the summary journal entry required to transfer the cost of completed mat sets from the Cutting Department to the Coating Department in May.

e. Compute the total cost assigned to the Cutting Department's ending inventory on May 31.

EXERCISE 18.11

Process Costing through

Two Departments:

Department II

Exercise 18.11 is an extension of Exercise 18.10.

The following information pertains to May activity in Accessory World's Coating Department:

Cost data:
Total cost of beginning inventory on May 1 . . . . . . . . . . . . . . . . . . . . . . . . . $45,300
Direct materials costs incurred in May. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11,925
Conversion costs incurred in May . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84,525
Cut sets transferred in during May. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ?
Physical units data:
Units in process, May 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6,000 sets
Units started in May . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ? sets
Units in process, May 31 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9,000 sets
Percentage of completion data:
Direct materials, May 1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60%
Conversion, May 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80
Cut sets transferred in, May 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ?
Direct materials, May 31. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70%
Conversion, May 31 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90
Cut sets transferred in, May 31 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ?

a. Compute how many cut mat sets were started in the Coating Department during May.

b. Prepare a schedule showing: (1) the number of mat sets transferred out of the Coating Department in May, and (2) the number of mat sets started and completed by the Coating Department in May.

c. Compute the equivalent units of input resources for the Coating Department in May.

d. Compute the cost per equivalent unit of input resource for the Coating Department in May.

e. Prepare the summary journal entry required to transfer the cost of finished mat sets from the Coating Department's Work in Process Inventory to the company's Finished Goods Inventory in May.

f. Compute the total cost assigned to the Coating Department's ending inventory in process on May 31.

EXERCISE 19.2

Value-Chain Activities

Assume you have just been hired as the management accountant in charge of providing your firm's managers with product cost information. Identify the activities you might undertake for the following four value chain components:

a. Research and development
b. Production
c. Marketing
d. Customer service

PROBLEM 19.1A

Identifying Value-Added
and Non-Value-Added
Activities

Castner Corporation is considering implementation of a JIT inventory system. The company's industrial engineer recently conducted a study to determine the average number of days spent in each activity of the production process. The following table summarizes her findings:

Production Activity Number of Days

Inspecting materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3
Storing materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .17
Moving materials into production . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3
Setting up production equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Cutting materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6
Bending materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Assembling finished products . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Painting finished products . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5

Instructions

a. Identify Castner's value-added production activities.
b. Identify Castner's non-value-added production activities.
c. Calculate Castner's total cycle time.
d. Determine Castner's manufacturing efficiency ratio.
e. Which of the above activities might be reduced or eliminated if Castner implemented a JIT system?
f. What ethical issues might be related to eliminating some of the non-value-added activities?

Reference no: EM131123565

Questions Cloud

Estimate the sustainable sales growth rate for the munich co : Munich has a target dividend payout of 40 percent of net income. Based on the 2010 financial statements relationships, estimate the sustainable sales growth rate for the Munich Corporation for 2011. Show how your answer in Part A would change if Muni..
Discuss the continuity of the function : Please answer the following equation Q1.) Discuss the continuity of the function g(x) = (x^2-1) / (x-1).
Reflect on the life of the historical figure : How the historical figure was shaped by his time period and environment - Find the perfect anecdote to demonstrate the qualities of the person.
Essay by discussing and contextualizing the topic : 1) If the student's introduction is short, can the student introduce the topic mater of the essay by discussing and contextualizing the topic addressed by the student? (Optional)
Estimate the total cost of manufacturing the tables : Estimate the total cost of manufacturing the tables for Cosmopolitan University. Determine the company's bid price if bids are based upon the total estimated manufacturing cost of a particular project, plus 75 percent.
Planning for a great school year : PLANNING FOR A Great School Year-very fall, children begin the school year with a backpack full bureaucratic barriers in your way. Navigating those obstacles sucof new notebooks, pencils and other school supplies.
What would be your estimate of the additional funds needed : A. What would be your estimate of the additional funds needed next year to support a 30 percent increase in sales? B. How would your answer in Part A change if the expected sales growth were only 15 percent?
Reduce its flight schedule to save money : If its original routes are as illustrated here, which flights can be discontinued to retain service between all pairs of cities (where it may be necessary to combine flights to fly from one city to another)?
Announced his dislike for mexicans and muslims : Donald Trump has announced his dislike for Mexicans and Muslims, immigrants and other minority groups. He wants to institute laws against foreigners who are entering as refugees, and possibly for those who are already in. The White House Press sec..

Reviews

Write a Review

Cost Accounting Questions & Answers

  Cost accounting assignment

Evaluate Method of measuring costs associated with production, budgeting process, normal job-order costing system , master budget, cycle time.

  Prepare the journal entries

Prepare the journal entries to record the bond issue and interest expense.

  Advise as to the liability of all the parties

Write a report on given case study and Advise as to the liability of ALL the parties both under common law and the Corporations Law.

  Prepare revenues budget

Prepare Revenues budget and Production budget in units

  Effect of exchange rate changes on cash and cash

Effect of exchange rate changes on cash and cash

  Corporate governance

You are to reflect on how this case of China Sky relates to what the arguments for and against allowing audit firm partners and/or employees to join audit committees.

  Cost-benefit analysis

A cost-benefit analysis of electronic medical records in primary care

  Non-annual interest rates and annuities

Theory of Interest- Non-annual interest rates and annuities

  Job costing in service organizations

How is job costing in service organizations different from job costing in manufacturing environments?

  Accounting for bad debt expense

Accounting for bad debt expense

  Accounting and partnership problems

Accounting and Partnership problems

  Development of relevant cash flows

Development of relevant cash flows - Cost estimating and financial analysis

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd