Estimate the total cost for design

Assignment Help Civil Engineering
Reference no: EM133172924

Task 1 Civil Works Design

You are required to undertake a civil construction design project as outlined below. Your Assessor will take the role of the client for the purposes of this assessment task.

Design Specifications

1. The Problem

You are a civil designer working for the state department of transportation. You have been assigned responsibility for the design of a truss bridge to carry a two-lane highway across the river valley shown below.

90_Civil designer.jpg

2. Design Objective

Satisfy all of the specifications listed below, while keeping the total cost of the project as low as possible.

3. Bridge Configuration
1. The bridge may cross the valley at any elevation from the high water level to 24 meters above the high water level.
2. If the elevation of the bridge is below 24 meters, excavation of the river banks will be required to achieve the correct highway elevation.
3. To provide clearance for overhead power lines (shown above), the highest point on the bridge may not exceed an elevation 32.5 meters above the high water level (8.5 meters above the top of the river banks).
4. The bridge may consist of either standard (simple supports) or (arch supports). If necessary, the bridge may also use one intermediate , located near the centre of the valley. If necessary, the bridge may also use cable , located 8 meters behind one or both abutments.
5. Each main truss can have no more than 100 and no more than 200 .

6. The bridge will have a flat, reinforced deck. Two types of concrete are available:

1. Medium-strength concrete requires a deck thickness of 23 centimetres (0.23 metres).
2. High-strength concrete requires a deck thickness of 15 centimetres (0.15 meter).

7. In either case, the deck will be supported by transverse spaced at 4 metre intervals. To accommodate these floor beams, your must have a row of joints spaced 4 meters apart at the level of the deck. These joints are created automatically when you begin a new design.
8. The bridge deck will be 10 meters wide, such that it can accommodate two lanes of traffic.

4. Member Properties

• Materials. Each member of the truss will be made of either carbon steel, high- strength low-alloy steel, or quenched and tempered steel.
• . The members of the truss can be either solid bars or hollow tubes. Both types of cross-sections are square.
• Member Size. Both cross-sections are available in a variety of standard sizes.

5. Loads

The bridge must be capable of safely carrying the following loads:

• Weight of the deck.
• Weight of a 5-cm thick , which might be applied at some time in the future.
• Weight of the steel floor beams and supplemental bracing members (assumed to be 12.0 applied at each deck-level joint).
• Weight of the main trusses.
• Either of two possible truck loadings:

• Weight of one standard H25 truck loading per lane, including appropriate allowance for the dynamic effects of the moving load. (Since the bridge carries two lanes of traffic, each main truss must safely carry one H25 vehicle, placed anywhere along the length of the deck.)
• Weight of a single 480 kN Permit Loading, including appropriate allowance for the dynamic effects of the moving load. (Since the Permit Loading is assumed to be cantered laterally, each main truss must safely carry one-half of the total vehicle weight, placed anywhere along the length of the deck.)

6. Structural Safety

The bridge will comply with the structural provisions of the state specified standards, to include:

• Material densities

• Load combinations
• Tensile strength of members
• Compressive strength of members

7. Cost

The cost of the design will be calculated using the following cost factors:

• Material Cost:

• Carbon steel bars - $4.50 per kilogram
• Carbon steel tubes - $6.30 per kilogram
• High-strength steel bars - $5.00 per kilogram
• High-strength steel tubes - $7.00 per kilogram
• Quenched and tempered steel bars - $5.55 per kilogram
• Quenched and tempered steel tubes - $7.75 per kilogram

• Steel Production(fabrication) Cost: $1000.00 per each steel pattern
• Connection Cost: $500.00 per joint
• Site Cost:

Required:

Part 1: (Design Analysis)

• Reinforced concrete deck (medium strength) - $5,150 per 4-meter panel
• Reinforced concrete deck (high strength) - $5,300 per 4-meter panel
• Excavation - $1.00 per cubic meter (See the Site Design Wizard for excavation volume)
• Supports (abutments and pier) - Cost varies (See the Site Design Wizard for specific values)
o $6,000 per anchorage

Refer to design model 1 document. Given the below forces:
Determine the horizontal and vertical components of reaction at the support.

Determine the forces in members 17, 19, 20, 16 and 21. State if the members are in tension or compression. Note that all angles are 45 degrees.

Part 2: (Estimation)

1. Make a detailed list of all constraints and requirements to the bridge design.

2. Three different materials available for the design of the bridge:
• Carbon steel,
• High-Strength Low-Alloy steel and
• Quenched and Tempered Low-Alloy Steel
Describe the differences between these materials. Which material is the best choice for a given structural design?

3. One of the most important decisions in the bridge design is the selection of a cross- section type, solid bar or hollow tube, for each member in the structural model.
At what locations should each type of cross section be used? (Hint: you should consider the effect of the different cross-sections on member strength in both tension and compression.)

4. A good engineer will try to find the best balance between the site cost (such site excavation, adding piers or cables) and the truss cost. Explain what is meant by this statement and provide some examples.

5. You are given two proposed designs that meet the design specifications. Estimate the total cost for each design and accordingly provide a recommendation on which model is more economical.

6. For each design model, address its environmental impact on the surroundings such as the river channel.

7. Based on all your analysis (cost + environmental), which is the optimum design?

8. Perform a risk assessment for the project taking into account all lifespan stages:
• the existing conditions
• the application of the design
• maintainability of the works

Attachment:- Civil Works Design.rar

Reference no: EM133172924

Questions Cloud

What are variable costs involved with andoy bakery operation : In the second year of business, total costs increase to 1,200,000, What are the variable costs involved with Andoy's bakery operation
What is artificial intelligence : What is artificial intelligence, blockchain, and the Internet of Things? Discuss how one of these technologies is currently being implemented?
Evaluate an existing business plan : What you think the structure should be (based on your own insights, research and judgement),
Determine the target adr using the hubbart formula : Question - ABC Lodging, a 20-room hotel, requires $2,000,000 for construction. Determine the target ADR using the Hubbart Formula
Estimate the total cost for design : Estimate the total cost for design and accordingly provide a recommendation on which model is more economical
Several collaborative relationships : Several collaborative relationships between choreographers and designers are mentioned in this chapter, including lighting designers, costume designers
Recruitment-selection-promotion and career management : You may explore a Recruitment, Selection, Promotion/Career Management, Retention, Termination, Downsizing concept, issue, or trend.
How does language shape reality : 1. What are the top five communication skills/personality traits that employers value most? Be able to provide examples of each Communication skills, teamwork s
Prepare a schedule to allocate net income : Prepare a schedule to allocate net income, assuming: 1. Bonus is based on net income after interest but before bonus and salaries

Reviews

Write a Review

Civil Engineering Questions & Answers

  Calculate what is the critical value for x in inches

When X exceeds some critical distance the slider will "lock" and no longer move regardless of the force applied. If the coefficient of friction for the slider bearing is 0.1, what is the critical value for X in inches

  What is the flow through the culvert

Find the volume of the solid S. The base of S is the region enclosed by the parabola y=4-3x^(2) and the x-axis. Cross sections perpendicular to the y-axis are squares.

  What is the critical capacity of the approach

What is the critical capacity of the approach and average delay per vehicle under this conditions.

  What is necessary volume of lagoon to meet requirments

Wastewater enters and anerobic pond at a BOD of 246 mg/L and a flowrate of 0.1 m^3/s. The waste degrades at a rate of 0.40d. Effluent from the lagoon must have a BOD of 23.9mg/L.

  Estimate the time between when the concentration ratios

A conservative tracer is applied to the ground surface and leached through the vadose zone by rainfall. The average volumetric water content is 0.40 over the upper 4 meters and 0.30 over the remaining 3 meters above the water table

  Determine the mass flowrate through boiler

The inlet of loe pressure turbine is 500Kpa and 500°C. Condenser operates at 10 Kpa. Determine the mass flowrate through boiler needed to produce 5000KW of power.

  Determine the corresponding value

Link ABrotates through a limited range of angle β, and its end Acauses the slotted link ACto rotate also. For the instant represented where β= 60 and = 0.6 rad/sconstant, determine the corresponding value of r r'.

  Calculate aeration basin size and the wate sludge rate

A completely mixed activated-sludge plan is being designed for a wastewater flow of 3.0 mgd. The BOD of 225 mg/l is 200 mg/l soluble. The effluent soluble BOD requirement is 7 mg/l (70 percent of the total 10 mg/l).

  Direction of flow in a conical tube

A conical tube of length 8 m fixed vertically with its smaller end upwards. The velocity head and pressure head at upper ends are 1.27 m and 2.50 m respectively.

  What is the volume of the iron in the entire paper clip

A typical paper clip weighs 0.59 gram and consists of BCC Iron. The density of iron is 7.87 gram/cm3 and its atomic radius is 0.124 nm.

  Estimate what is the critical slope of the channel

A trapezoidal channel cut into rock has a bottom width of 4 ft, side slopes of 1:1 and a channel slope of 0.0005. What is the critical slope of the channel.

  What is the encrypted message entropy

If this message is encrypted with DES using a random 56-bit key, what is the encrypted message's entropy? And why

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd