Estimate the total cost for design

Assignment Help Civil Engineering
Reference no: EM133172924

Task 1 Civil Works Design

You are required to undertake a civil construction design project as outlined below. Your Assessor will take the role of the client for the purposes of this assessment task.

Design Specifications

1. The Problem

You are a civil designer working for the state department of transportation. You have been assigned responsibility for the design of a truss bridge to carry a two-lane highway across the river valley shown below.

90_Civil designer.jpg

2. Design Objective

Satisfy all of the specifications listed below, while keeping the total cost of the project as low as possible.

3. Bridge Configuration
1. The bridge may cross the valley at any elevation from the high water level to 24 meters above the high water level.
2. If the elevation of the bridge is below 24 meters, excavation of the river banks will be required to achieve the correct highway elevation.
3. To provide clearance for overhead power lines (shown above), the highest point on the bridge may not exceed an elevation 32.5 meters above the high water level (8.5 meters above the top of the river banks).
4. The bridge may consist of either standard (simple supports) or (arch supports). If necessary, the bridge may also use one intermediate , located near the centre of the valley. If necessary, the bridge may also use cable , located 8 meters behind one or both abutments.
5. Each main truss can have no more than 100 and no more than 200 .

6. The bridge will have a flat, reinforced deck. Two types of concrete are available:

1. Medium-strength concrete requires a deck thickness of 23 centimetres (0.23 metres).
2. High-strength concrete requires a deck thickness of 15 centimetres (0.15 meter).

7. In either case, the deck will be supported by transverse spaced at 4 metre intervals. To accommodate these floor beams, your must have a row of joints spaced 4 meters apart at the level of the deck. These joints are created automatically when you begin a new design.
8. The bridge deck will be 10 meters wide, such that it can accommodate two lanes of traffic.

4. Member Properties

• Materials. Each member of the truss will be made of either carbon steel, high- strength low-alloy steel, or quenched and tempered steel.
• . The members of the truss can be either solid bars or hollow tubes. Both types of cross-sections are square.
• Member Size. Both cross-sections are available in a variety of standard sizes.

5. Loads

The bridge must be capable of safely carrying the following loads:

• Weight of the deck.
• Weight of a 5-cm thick , which might be applied at some time in the future.
• Weight of the steel floor beams and supplemental bracing members (assumed to be 12.0 applied at each deck-level joint).
• Weight of the main trusses.
• Either of two possible truck loadings:

• Weight of one standard H25 truck loading per lane, including appropriate allowance for the dynamic effects of the moving load. (Since the bridge carries two lanes of traffic, each main truss must safely carry one H25 vehicle, placed anywhere along the length of the deck.)
• Weight of a single 480 kN Permit Loading, including appropriate allowance for the dynamic effects of the moving load. (Since the Permit Loading is assumed to be cantered laterally, each main truss must safely carry one-half of the total vehicle weight, placed anywhere along the length of the deck.)

6. Structural Safety

The bridge will comply with the structural provisions of the state specified standards, to include:

• Material densities

• Load combinations
• Tensile strength of members
• Compressive strength of members

7. Cost

The cost of the design will be calculated using the following cost factors:

• Material Cost:

• Carbon steel bars - $4.50 per kilogram
• Carbon steel tubes - $6.30 per kilogram
• High-strength steel bars - $5.00 per kilogram
• High-strength steel tubes - $7.00 per kilogram
• Quenched and tempered steel bars - $5.55 per kilogram
• Quenched and tempered steel tubes - $7.75 per kilogram

• Steel Production(fabrication) Cost: $1000.00 per each steel pattern
• Connection Cost: $500.00 per joint
• Site Cost:

Required:

Part 1: (Design Analysis)

• Reinforced concrete deck (medium strength) - $5,150 per 4-meter panel
• Reinforced concrete deck (high strength) - $5,300 per 4-meter panel
• Excavation - $1.00 per cubic meter (See the Site Design Wizard for excavation volume)
• Supports (abutments and pier) - Cost varies (See the Site Design Wizard for specific values)
o $6,000 per anchorage

Refer to design model 1 document. Given the below forces:
Determine the horizontal and vertical components of reaction at the support.

Determine the forces in members 17, 19, 20, 16 and 21. State if the members are in tension or compression. Note that all angles are 45 degrees.

Part 2: (Estimation)

1. Make a detailed list of all constraints and requirements to the bridge design.

2. Three different materials available for the design of the bridge:
• Carbon steel,
• High-Strength Low-Alloy steel and
• Quenched and Tempered Low-Alloy Steel
Describe the differences between these materials. Which material is the best choice for a given structural design?

3. One of the most important decisions in the bridge design is the selection of a cross- section type, solid bar or hollow tube, for each member in the structural model.
At what locations should each type of cross section be used? (Hint: you should consider the effect of the different cross-sections on member strength in both tension and compression.)

4. A good engineer will try to find the best balance between the site cost (such site excavation, adding piers or cables) and the truss cost. Explain what is meant by this statement and provide some examples.

5. You are given two proposed designs that meet the design specifications. Estimate the total cost for each design and accordingly provide a recommendation on which model is more economical.

6. For each design model, address its environmental impact on the surroundings such as the river channel.

7. Based on all your analysis (cost + environmental), which is the optimum design?

8. Perform a risk assessment for the project taking into account all lifespan stages:
• the existing conditions
• the application of the design
• maintainability of the works

Attachment:- Civil Works Design.rar

Reference no: EM133172924

Questions Cloud

What are variable costs involved with andoy bakery operation : In the second year of business, total costs increase to 1,200,000, What are the variable costs involved with Andoy's bakery operation
What is artificial intelligence : What is artificial intelligence, blockchain, and the Internet of Things? Discuss how one of these technologies is currently being implemented?
Evaluate an existing business plan : What you think the structure should be (based on your own insights, research and judgement),
Determine the target adr using the hubbart formula : Question - ABC Lodging, a 20-room hotel, requires $2,000,000 for construction. Determine the target ADR using the Hubbart Formula
Estimate the total cost for design : Estimate the total cost for design and accordingly provide a recommendation on which model is more economical
Several collaborative relationships : Several collaborative relationships between choreographers and designers are mentioned in this chapter, including lighting designers, costume designers
Recruitment-selection-promotion and career management : You may explore a Recruitment, Selection, Promotion/Career Management, Retention, Termination, Downsizing concept, issue, or trend.
How does language shape reality : 1. What are the top five communication skills/personality traits that employers value most? Be able to provide examples of each Communication skills, teamwork s
Prepare a schedule to allocate net income : Prepare a schedule to allocate net income, assuming: 1. Bonus is based on net income after interest but before bonus and salaries

Reviews

Write a Review

Civil Engineering Questions & Answers

  Engineering ethics and ethical issue

what is the engineering ethics course where to write about any engineering ethical case and discuss the ethical issue?

  Engineering ethics and concept and cases

what is the engineering ethics case related to civil engineering with reference and discuss all the engineering ethics issues which covered the "Engineering etics concepte and cases?

  Transportation and management

In the construction management, there is a lot of procurement route that are necessary and suitable for the construction industry.

  Supporting Investment Promotion: ERNST & YOUNG

Ernst & young is currently providing support to various sectors. In this regards it was felt that if this report is able to document good practices currently being adopted or planned in ceramic sector.

  Personalized Cancer Therapy-A step forward

Cancer is the uncontrolled growth of abnormal cells in the body resulting in tumours that can be benign or malignant (cancerous cells). A proper treatment is necessary to fight with this serious disease.

  Discuss the different environmental companies

Discuss the different agencies, institutes, centers, different environmental companies that are active in UAE.

  Develop a simple urban constructed wetland design

Develop a simple urban constructed wetland design.

  Evaluate company performance in relation to GRI standards

Evaluate company performance in relation to GRI standards and comment on Stigler's theory.

  Water system design

Determine the corresponding error in the computed discharge

  Hydraulic behaviour in open channel

Describe how test flumes and associated equipment are used to assess and confirm hydraulic behaviour in open channel

  Write a paper on steel sustainability

Write a paper on steel sustainability.

  Writing case study about bridge collapse

Writing case study about bridge collapse

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd