Estimate the pullout length required for each reinforcement

Assignment Help Civil Engineering
Reference no: EM13304651

Three reinforcements are being considered for an MSE wall: A continuous geogrid having a reinforcement coverage ratio equal to 100 percent. A continuous metallic grid consisting of W4 bars having a diameter equal to 5.7 mm, a distance between longitudinal bars equal to 150 mm, a distance between transverse bars equal to 300 mm, and a reinforcement coverage ration equal to 100 percent A ribbed steel strip having a width equal to 50 mm, a distance between strips equal to 0.75 m, and a reinforcement coverage ration equal to 6.67 percent Estimate the pullout length required for each reinforcement to obtain a pullout resistance equal to 10 kN per meter width of the structure at a depth equal to 1 m below the top of the structure

Reference no: EM13304651

Questions Cloud

What is the amplitude of the ossilation : An air-track glider is attached to a spring. The glider is pulled to the right and released from rest att = 0. what is the amplitude of the ossilation
Calculate the volatility of a portfolio : Using the data in the following table, and the fact that the correlation of A and B is .00073, calculate the volatility (standard deviation) of a portfolio that is 60% invested in stock A and 40% invested in stock B.
What is the velocity when it reaches the bottom : A 2kg uniform cyclinder is released at the top of a 1.53 m 11 degree incline. What is the velocity when it reaches the bottom
What is the maximum debt ratio the firm can use : It can borrow at a rate of 7.5%, but the bank requires it to have a TIE of at least 4.0, and if the TIE falls below this level the bank will call in the loan and the firm will go bankrupt. What is the maximum debt ratio the firm can use?
Estimate the pullout length required for each reinforcement : A continuous geogrid having a reinforcement coverage ratio equal to 100 percent. A continuous metallic grid consisting of W4 bars having a diameter equal to 5.7 mm, a distance between longitudinal bars equal to 150 mm, a distance between transvers..
Obtain the density of mobile electrons in the material : The Hall effect can be used to determine the density of mobile electrons in a conductor. Find the density of mobile electrons in the material
Determine the volume of sludge after filtration : Assume that the sludge does not change density during filtration and that liquid removed from the sludge contains no sludge. Using mass-balance method. determine the volume of sludge after filtration.
What is the linear distance on the screen : In a double-slit experiment, what is the linear distance on the screen between adjacent maxima if the wavelength is 538 nm
Compare the reactor volume required to achieve efficiency : Compare the reactor volume required to achieve 95% efficiency for Completely Mixed Flow Reactor (CMFR) and a Plug Flow Reactor (PFR) for the following conditions. steady-state, first-order reaction, flow rate = 14m3 / day.

Reviews

Write a Review

Civil Engineering Questions & Answers

  Finding average time in system

If the time required to pay for parking is exponentially distributed with a mean of 15 seconds, find the average time in system.

  What is the uniform deterministic arrival rate

what is the uniform deterministic arrival rate if the vehicle queue is cleared in 35 minutes after vehicles begin to arrive (in veh/min.)?

  Determining the compressive strengths

Determine the compressive strengths of the following: A) A 6-in. diameter concrete cylinder that failed at ta test load of 135,000 B) A-3-in. diameter specimen that failed at a test load of 30,000

  Environmental soil cleaning company

How much money should an environmental soil cleaning company borrow to finance a site reclamation project if it expects revenue of $140,000 in the first year increasing by 3% per year over the 5-year cleanup period? The interest rate is 8%.

  Determine what is the length of the horizontal curve

a vertical curve on this highway connects +1% and +3% grade and is 420ft long. if a horizontal curve on highway is on a two-lane section with 12 ft lanes and has a central angle of 37 degrees and a superelevation of 6%, what is the length of the h..

  Compare total reactor volume require to remove the substance

Compare the total reactor volume required for 90% removal of a substance that decays according to first-order kinetics with a rate constant of 0.05 day -1 in a CM system that contains a single reactor against a system that contains three CM reacto..

  Determine time required to dry grain at relative humidity

A batch dryer with a grain depth of 20 inches contain 21,000 pounds of 20.7% (wb) moisturecontent shelled corn. An airflow of 75,000 pounds dry air per hour is supplied at a temperature of 175°F. The ambient air is 55°F at 100% relative humidity.

  Determine the resulting couple moment

Calculate the moments M_A and M_B about point A for the forces applied at points A and B. Then, determine the resulting couple moment M_R. Assume that a positive moment produces a counterclockwise rotation whereas a negative moment produces a cloc..

  Determine the total elongation of the steel rod

A steel rod having a cross sectional area of 1/2in^2 and length of 600ft is suspended vertically. It supports a load of 5000 pounds at the lower end. If steel weighs 490 lb/ft^3 and E=30,000,000 psi, find the total elongation of the rod

  Usage rates if the community has a declining growth rate

Determine how many years from now the consumption will reach its design capacity with current usage rates if the community has a declining growth rate.

  Presedimentation-uspended solids concentration of raw revers

Presedimentation can reduce the suspended solids concentration of raw river water from 500 mg/L to 200 mg/L. How many pounds of dry solids does this represent per million gallons?

  Estimate the area of circle using the lower and upper bounds

Write a simple MATLAB program that will estimate the area of a circle using the lower and upper bounds (using triangles). The user will input the diameter of the circle and the desired accuracy (relative error ) and the program must run

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd