The marketing department at State University is working on a project with the following information. The Activity Time is also referred to as the Normal Activity Time and is the time it takes to complete the activity based on the normal times.  The Crash Time is the time it takes to complete the activity if this activity is crashed.                                                                        

  

Activity

  
  

Immediate   Predecessors

  
  

Activity   Time (Days)

  
  

Activity  Cost (Total)

  
  

Crash   Time (Days)

  
  

Activity   Crash Cost (Total)

  
  

A

  
  

--

  
  

6

  
  

$10,000

  
  

4

  
  

$12,000

  
  

B

  
  

--

  
  

4

  
  

$5,500

  
  

2

  
  

$7,300

  
  

C

  
  

A, B

  
  

3

  
  

$6,000

  
  

2

  
  

$7,500

  
  

D

  
  

C

  
  

6

  
  

$4,000

  
  

4

  
  

$6,400

  
  

E

  
  

C

  
  

4

  
  

$3,500

  
  

2

  
  

$5,100

  

a)  What is the critical path for this project, what is the project completion time, how much total work time (in days) is required for this project, and what is the cost for completing this project using the Activity Time?  Also identify the slack time for each path.  The slack time for each path should be based on the time to complete the critical path.

b)  Suppose that the school wants to complete the project in 13 days by crashing the most economical activity.  Which activity(ies) should it crash and how much will the project cost increase

c)  Suppose that the school wants to complete the project in 12 days by crashing the most economical activity.  Which activity(ies) should it crash and how much will the project cost increase from your answer in a)

d)  Start with the original Activity Times in answering this part.  In addition to the cost information provided above, indirect project costs total $600 per day.  The company also incurs $300 in penalty costs for each day the project lasts beyond eleven days.  What is the minimum cost schedule for this project?  What is the cost of this schedule and what is the project completion time?      

Reference no: EM13110892

Questions Cloud

Find difference between sub therapeutic and antibiotics : What is the difference between sub therapeutic and therapeutic antibiotics?
Do elderly men has small ferritin variance than younger men : For 26 younger men sample standard deviation was 84.2 mg/L. At .01 level of significance, do these data support conclusion that ferritin distribution in elderly men has smaller variance than in younger men?
Determine at what pressure will pure h2o start to boil : determine at what pressure will pure H 2 O  start to boil if its temperature is seventy five degree Celsius
Determine how would the mw value be affected : If the gas was not pure butane but 10 mole percent propane and 90 mole percent butane then determine how would the MW value be affected?
Estimate the cost of schedule and project completion time : The marketing department at State University is working on a project with the following information. The Activity Time is also referred to as the Normal Activity Time and is the time it takes to complete the activity based on the normal times.
Illustrate audience characteristics you need to consider : Illustrate what are some considerations that you must keep in mind given the diversity of the audience? Illustrate what would you do to ensure that your message is effective?
One step tests of hypothesis : An insurance company, based on past experience, estimates the mean damage for a natural disaster in its area is $5,000. After introducing several plans to prevent loss
Draw a phylogenetic tree of photosynthetic organisms : Draw a phylogenetic tree of photosynthetic organisms. Include the following in your tree: angiosperms, photosynthetic bacteria, non-photosynthetic bacteria, animals, photosynthetic protists, non-photosynthetic protists, gymnosperms, monocots, bryo..
Determine what is the longest possible wavelength of light : Determine what is the longest possible wavelength of light that could ionize an atom of bismuth if the first ionization energy of bismuth is Ei1 = +70 kJ/mol.?

Reviews

Write a Review

Operation Management Questions & Answers

  Completing the venture opportunity screening exercises

Completing the Venture Opportunity Screening Exercises is designed to clear up the uncertainties and risks associated with that venture concept.

  What positioning strategy you will consider

You are planning to introduce 3 Lines of products. What positioning strategy you will consider so that the target market should buy the products.

  Identify key gaps in planning for the exit

Identify key gaps in planning for the exit. Provide recommendations on the exit strategy. Is the sale the right one? What steps ought to be taken to maximize the sales-price?

  Find the stock worth today

A security analyst is forecasting dividends for Boston Electric over the next four years, as follows: $1 (Y1), $1.50 (Y2); $2.00 (Y3); $2.75 (Y4). In addition, the analyst expects that the stock could be sold for $62.25 four years from now.

  Creating swot analysis

Create a SWOT analysis. Included in this report should be the company's official mission statement and how you feel the company is meeting its mission.

  Discuss the distinguishing characteristics of mature group

Identify and discuss the four distinguishing characteristics of a mature (well-functioning) group. Give an example of a mature group you have participated in and the application of these characteristics.

  The circulation manager of the new york times

The circulation manager of The New York Times in State College, PA is trying to decide how many copies of the upcoming Sunday edition of the paper to order so as to meet the demand of local customers

  Prepare your recommendation for bushwood

Prepare your recommendation for Bushwood if their objective is to minimize costs. Assume that service times for each option follow exponential distributions.

  Provide example of ethical leadership

Give an example of ethical leadership. What are the characteristics of ethical leadership? And why do you think ethical leadership is important.

  Illustrates what are the identification

Illustrates what are the Identification also description of human implications, potential resistance factors also the drivers of the change.

  Determine the current capacity of the entire process

The following diagram describes a process that consists of eight separate operations, with sequential relationship and capacities (units per hour) as shown:

  What order quantity minimizes total annual inventory cost

They sell 100 printers per month. The manufacturer has offered the following price schedule. What order quantity minimizes total annual inventory cost?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd