Activity D has an optimistic time of three days, a pessimistic time of nine days, and a most likely time of four days. Determine its expected time and variance.
Activity E has an optimistic time of 9 days, a most likely time of 12 days, and a pessimistic time of 15 days. Estimate its expected time and standard deviation.
Activity J has a duration of 7 and an earliest finish time of 21. If J's latest start time is 16, this must mean that J's slack is:
a in a gantt chart the vertical axis represents which of the following?bull timebull revenuebull
Okan, explain but spends which time straightening the shelves of products in his department. Which of the subsequent is the most likely response of the group towards Okan.
Wheaten Enterprises, Inc. has fixed operating costs of $10,000; the selling price per unit of its product is $25, and its variable cost per unit for this product is $15. Calculate the firm’s operating breakeven point in units.
Management may choose to build up capacity in anticipation of demand or in response to developing demand. Cite advantages also disadvantages of both approaches.
What were the solutions used to address the problem. Was the case you described a special-cause or common-cause. Do you feel the solution or approach used appropriate for the cause
Description of proposed technology solution, including such things as; the type of system, the name of any primary software to be used, whether the system is operated locally or remotely, etc.
Imagine this is the only position of its kind in the organization. From this perspective, design a performance appraisal program to assess your job performance.
Your agency has just signed a new client, LibraTech, that wants to introduce their new eReader into the marketplace in a way that will scare the competition.
Explain why it is important to gain employee cooperation before beginning a job analysis program. Describe other issues and means that can aid in the job analysis process.
Discuss to what extent these two aspects of control work together in successful organizations. Be sure to give an example or two to support the position you take on this.
Garden Variety Flower Shop uses 1000 clay pots a month. The pots are purchased at $3 each. Annual carrying costs per pot are estimated to be 25% of cost, and ordering costs are $25 per order.
An electrical utility needs to generate 6,500 megawatts of electricity today. It has five generators. If any electricity is generated by a given generator, that generated must be started up and a fixed start-up cost is incurred.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd