Establish a cost estimating relationship

Assignment Help Project Management
Reference no: EM131922273

Project Management Question:

Suppose we have collected the following cost and performance data on rocket motors for missile propulsion systems.

Establish a cost estimating relationship (CER) between cost & thrust and establish a CER between cost & length.

Which one looks to be the better CER?

Cost ($)Thrust (pounds)Length (inches)
33,003 1,000 36
34,712 1,200 40
27,253 500 24
39,767 2,000 42
51,093 5,000 62
62,073 10,000 98
36,818 1,500 40
79,466 25,000 124
68,628 15,000 78

 

Reference no: EM131922273

Questions Cloud

Develop a working excel model that puts weights : For your risk management assignment, do some of your own research into effective project risk management factors and techniques.
What is the authors topic main question and argument : What is the author's topic, main question, and argument? Give a quote from the reading that establishes their argument and be prepared to discuss it in class.
What would you do if the culture was detrimental to project : Identify how a project's culture is developed. How do you know when the culture is benefiting the project and how do you enforce this culture?
Choose two tools to research and discuss with your classmate : Choose two tools to research and discuss with your classmates. Include a picture in your description of each tool and at least two references.
Establish a cost estimating relationship : Suppose we have collected the following cost and performance data on rocket motors for missile propulsion systems.
Explain the difference in the two mens political philosophy : Try to explain the difference in the two men's political philosophy. As always you need to have an initial post and at least two responses.
Discuss the hurricane katrina disaster was properly managed : Discussion on whether or not you believe the handling of the Hurricane Katrina disaster was properly managed by the New Orleans Police Department.
Describe the process of using the wbs to develop cost : Describe the process of using the WBS to develop cost estimates. How are these estimates aggregated into total cost estimates?
Calculate the cost and schedule variance : A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low.

Reviews

Write a Review

Project Management Questions & Answers

  Explains three different leadership styles

Prepare a report that Identifies and explains three different leadership styles and critically evaluate the differences between them.

  Detemine the npv profiles of two projects

Suppose you are considering two projects, A and B, that each have a required rate of return of 10%. Both projects cost $5,000 and have a Net Present Value of $50. Project A has an IRR of 16% and Project B has an IRR of 15%. What is the crossover rate..

  Describe dells goals regarding quality

Describe Dell's goals regarding quality.-  How does Dell monitor quality?- How does customer satisfaction relate to Dell's quality control?

  Show the importance of teamwork in organizations

Importance of Teamwork in Organizations - Explain a problem to be solved and evaluate the characteristics of the perfect team to address the problem.

  A jit system uses kanban cards to authorize movement

A JIT system uses kanban cards to authorize movement of incoming parts. In one portion of the system

  Project planning and project management presentation

Prepare a presentation covering the following: the benefits of project planning and project management within the various types of organizational systems

  Review how companies manage knowledge and information

BSBINM601: Manage knowledge and information - Review how companies manage knowledge and information today in order to support decision making

  Sketch the graphs of the average cost function

Sketch the graphs of the average cost function and the marginal cost function on the same set of coordinate axes. Include any oblique asymptotes.

  Basic service blueprint for ebags current product line

Develop a basic service blueprint for eBAGS' current product line. After analyzing your blueprint, would you recommend to eBAGS managers that they consider business process reengineering?

  Mixed model sequencea production line assembles 2 models of

mixed model sequencea production line assembles 2 models of hair dryer standard s and deluxe d. each s requires 4

  Develop a strategic project plan on haya water company

develop a strategic project plan on Haya water company - Select and apply appropriate tools and techniques for the planning and management of a project

  Factors important in understanding decision situation

What is the decision facing Mattel?- What factors are important in understanding this decision situation?- What are the alternatives?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd