Elucidate what is the critical path

Assignment Help Operation Management
Reference no: EM1373370

Q. The R&D department is planning to bid on a large project for the development of a new
communication system for commercial planes. The accompanying table shows the activities,
times also sequences needed:

Activity Immediate Predecessor Time (weeks)

A - 3
B A 2
C A 4
D A 4
E B 6
F C, D 6
G D, F 2
H D 3
I E, G, H 3

a. Draw the ne2rk diagram.

b. Elucidate what is the critical path?

c. Suppose you need to shorten the completion time as much as possible also you have the option of shortening any or all of B, C, D also G every one week. Which would you shorten?

d. Elucidate what is the new critical path also earliest completion time?

 

Reference no: EM1373370

Questions Cloud

Create a report for your ceo which outlines the value : As the IT manager, you have been tasked with convincing your Corporation's CEO which the time has come purchase a new operating system also the latest office tools for the Corporation's computers. Create a report for your CEO which outlines the val..
Question on international trade : Assume we decline to sell goods to any country that decrease or halted its exports to us. Who would profit and who would lose from such retaliation?
Elucidate what should nancy bush do : she fears which the supervisors will be biased towards making the component in house, as they tend to favour retaining more work for their people. Elucidate what should Nancy Bush do.
Estimate using air carrier service to ship the cards : Baseball Card Emporium (BBE) of Lewistown, Pennsylvania, is a distributer or of baseball cards to sports card retailers. Estimate using air carrier service to ship the cards.
Elucidate what is the critical path : Elucidate what is the critical path. Suppose you need to shorten the completion time as much as possible also you have the option of shortening any or all of B, C, D also G every one week. Which would you shorten.
Price elasticity of demand : Determining at least two websites or articles to help you answer the following questions about the petroleum industry. It is to be done is précis of the major points of the article or Web site, and to be referenced.
Elucidate human capital capabilities for law enforcement : Elucidate what human capital capabilities for law enforcement are necessary to make database more effective. Elucidate what are the relevant considerations to balance the police's ability to investigate versus the citizens' need to privacy.
Impact of past and current fiscal policies, monetary policie : Create three Microsoft PowerPoint slides in which you summarize the following data, Include an evaluation of impact of past and current fiscal policies, monetary policies, budget deficits or surpluses on economy and on the airline industry industry.
Difference between a project phase and a process group : What type of project organization would work best in this situation, and what is the difference between a project phase and a process group?" How would you answer this question

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd