Q. Blue Zuma Project
1. Status report include a table containing PV, EV, AC,BAC, EAC, SV, CV, & CPI ofr each activity & whole project.
a. Project progressing in terms of cost & schedule
b. Activities gone well? Not gone well?
c. PCIB & PCIC indicate in terms of elucidate how much of project has been accomplished to date?
d. Forecasted cost at completion (EACF) or Predicted VACF?
e. Interpret TCIP at this point.
f. Estimated date of completion?
g. Elucidate how well is project doing in terms of priorities?
2. If one of industrial engineers assigned to your project would be available to work on project from Aug 22-27, 2008? Illustrate what would you tell him?
Work in a team in an academic environment
: You have the opportunity to work in a team in an academic environment. Determine what have been best practices of a team, and what are some areas of improvement?
|
Elucidate how many students on average will be waiting
: Average arrival rate is 12 students per hour; also average service rate is 20 students per hour. Elucidate how many students, on average, will be waiting in line at any one time.
|
Describe organizational structure
: Describe organizational structure of your selected organization, and then compare also contrast it with two different organizational structures.
|
Elucidate how would you reconcile this finding with sutton
: Do you think being is same as Big Five trait of agreeableness. If so, do you think companies should screen out those who score low on agreeableness.
|
Elucidate how well is project doing in terms of priorities
: Elucidate how well is project doing in terms of priorities. If one of industrial engineers assigned to your project would be available to work on project from Aug 22-27, 2008. Illustrate what would you tell him.
|
Illustrate what is your forecast of profit for a store
: Sales (X, in millions of dollars) is related to Profits (Y, in hundreds of thousands of dollars) by regression equation Y = 8.21 + 0.76 X. Illustrate what is your forecast of profit for a store with sales of $40 million or $50 million.
|
Evaluate cost of lying off workers
: December demand rates of production crew both 1,600 units per month. Cost of hiring additional workers is $5,000 per 100 units. Cost of lying off workers is $7,500 per 100 units. Evaluate this plan.
|
Show which call center access time is in statistical control
: Suppose which standard deviation of process distribution is 5.77. If specifications for access time are 500 ± 18 sec., is process capable? Why or why not? Assume three-sigma quality.
|
Illustrate what kinds of things would likely requisite
: Illustrate what scheduling must she do? Illustrate what things might occur to disrupt schedules also cause hazel to reschedule. Elucidate how important is quality assurance to hazel's business.
|