Effect on the optimal solution

Assignment Help Basic Statistics
Reference no: EM13928698

1. Southern Sporting Good Company makes basketballs and footballs. Each product is produced from two resources rubber and leather. The resource requirements for each product and the total resources available are as follows:

Resource Requirements per Unit
Product
Rubber (lb.)
Leather (ft2)
Basketball
3
4
Football
2
5
Total resources available
500 lb.
800 ft2

a. State the optimal solution.

b. What would be the effect on the optimal solution if the profit for a basketball changed from $12 to $13? What would be the effect if the profit for a football changed from $16 to $15?

c. What would be the effect on the optimal solution if 500 additional pounds of rubber could be obtained? What would be the effect if 500 additional square feet of leather could be obtained?

2. A company produces two products, A and B, which have profits of $9 and $7, respectively. Each unit of product must be processed on two assembly lines, where the required production times are as follows:

Hours/ Unit
Product
Line 1
Line2
A
12
4
B
4
8
Total Hours
60
40

a. Formulate a linear programming model to determine the optimal product mix that will maximize profit.

b. Transform this model into standard form.

3. Solve problem 2 using the computer.

a. State the optimal solution.

b. What would be the effect on the optimal solution if the production time on line 1 was reduced to 40 hours?

c. What would be the effect on the optimal solution if the profit for product B was increased from $7 to $15 to $20?

4. For the linear programming model formulated in Problem 2 and solved in Problem 3.

a. What are the sensitivity ranges for the objective function coefficients?

b. Determine the shadow prices for additional hours of production time on line 1 and line 2 and indicate whether the company would prefer additional line 1 or line 2 hours.

5. Formulate and solve the model for the following problem:

Irwin Textile Mills produces two types of cotton cloth - denim and corduroy. Corduroy is a heavier grade of cotton cloth and, as such, requires 7.5 pounds of raw cotton per yard, whereas denim requires 5 pounds of raw cotton per yard. A yard of corduroy requires 3.2 hours of processing time; a yard of denim requires 3.0 hours. Although the demand for denim is practically unlimited, the maximum demand for corduroy is 510 yards per month. The manufacturer has 6,500 pounds of cotton and 3,000 hours of processing time available each month. The manufacturer makes a profit of $2.25 per yard of denim and $3.10 per yard of corduroy. The manufacturer wants to know how many yards of each type of cloth to produce to maximize profit. Formulate the model and put it into standard form. Solve it.

a. How much extra cotton and processing time are left over at the optimal solution? Is the demand for corduroy met?

b. What is the effect on the optimal solution if the profit per yard of denim is increased from $2.25 to $3.00? What is the effect if the profit per yard of corduroy is increased from $3.10 to $4.00?

c. What would be the effect on the optimal solution if Irwin Mils could obtain only 6,000 pounds of cotton per month?

6. Continuing the model from Problem 5.

a. If Irwin Mills can obtain additional cotton or processing time, but not both, which should it select? How much? Explain your answer.

b. Identify the sensitivity ranges for the objective function coefficients and for the constraint quantity values. Then explain the sensitivity range for the demand for corduroy.

7. United Aluminum Company of Cincinnati produces three grades (high, medium, and low) of aluminum at two mills. Each mill has a different production capacity (in tons per day) for each grade as follows:

Aluminum Grade
Mill
1
2
High
6
2
Medium
2
2
Low
4
10

The company has contracted with a manufacturing firm to supply at least 12 tons of high-grade aluminum, and 5 tons of low-grade aluminum. It costs United $6,000 per day to operate mill 1 and $7,000 per day to operate mill 2. The company wants to know the number of days to operate each mill in order to meet the contract at minimum cost.

a. Formulate a linear programming model for this problem.

8. Solve the linear programming model formulated in Problem 16 for Unite Aluminum Company by using the computer.

a. Identify and explain the shadow prices for each of the aluminum grade contract requirements.
b. Identify the sensitivity ranges for the objective function coefficients and the constraint quantity values.
c. Would the solution values change if the contract requirements for high-grade alumimum were increased from 12 tons to 20 tons? If yes, what would the new solution values be?

9. Solve the linear programming model developed in Problem 22 for the Burger Doodle restaurant by using the computer.

a. Identify and explain the shadow prices for each of the resource constraints
b. Which of the resources constrains profit the most?
c. Identify the sensitivity ranges for the profit of a sausage biscuit and the amount of sausage available. Explain these sensitivity ranges.

10. The manager of a Burger Doodle franchise wants to determine how many sausage biscuits and ham biscuits to prepare each morning for breakfast customers. The two types of biscuits require the following resources:

Biscuit
Labor (hr.)
Sausage (lb.)
Ham (lb.)
Flour (lb.)
Sausage
0.010
0.10
---
0.04
Ham
0.024
---
0.15
0.04

11. The franchise has 6 hours of labor available each morning. The manager has a contract with a local grocer for 30 pounds of sausage and 30 pounds of ham each morning. The manager also purchases 16 pounds of flour. The profit for a sausage biscuit is $0.60; the profit for a ham biscuit is $0.50. The manager wants to know the number of each type of biscuit to prepare each morning in order to maximize profit. Formulate a linear programming model for this problem.

Reference no: EM13928698

Questions Cloud

Discuss the various systems development methodologies : Possession of information can influence decisions in organizations. Discussion how new systems development can change the order of those who control the information and how this disruption may lead to resistance to adopting the new systems.
Managing a large financial project : Your company has just hired a new CEO, and you make an appointment with her to discuss a large financial project that you have been managing.
How much of your personal feelings should you share : How should you approach your team - how much of your personal feelings should you share and What are sonic key actions you should take?
What is the difference between real and nominal gdp : What is the difference between real and nominal GDP? Does GDP accurately reflect the nation's welfare
Effect on the optimal solution : What would be the effect on the optimal solution if the profit for a basketball changed from $12 to $13? What would be the effect if the profit for a football changed from $16 to $15?
Fixed asset investment : five-year project has an initial fixed asset investment of $345,000, an initial NWC investment of $37,000, and an annual OCF of -$36,000. The fixed asset is fully depreciated over the life of the project and has no salvage value
Advising about a software purchase : Your local art museum recently purchased a quad-core computer with 16 GB of RAM. The curator read an article about an art collection inventory system software package that could go on the new computer. You have a long experience with end users has..
What are the different types of unemployment : How do they affect the economy in terms of growth, labor force, and price of labor
Why do you think davidson goes to great lengths : Why do you think Davidson goes to great lengths to describe these differences? Do you think there really are any differences? After having read about the many achievements of Athens laid out in the textbook, how does this expose on the sexuality an..

Reviews

Write a Review

Basic Statistics Questions & Answers

  Statistics-probability assignment

MATH1550H: Assignment:  Question:  A word is selected at random from the following poem of Persian poet and mathematician Omar Khayyam (1048-1131), translated by English poet Edward Fitzgerald (1808-1883). Find the expected value of the length of th..

  What is the least number

MATH1550H: Assignment:  Question:     what is the least number of applicants that should be interviewed so as to have at least 50% chance of finding one such secretary?

  Determine the value of k

MATH1550H: Assignment:  Question:     Experience shows that X, the number of customers entering a post office during any period of time t, is a random variable the probability mass function of which is of the form

  What is the probability

MATH1550H: Assignment:Questions: (Genetics) What is the probability that at most two of the offspring are aa?

  Binomial distributions

MATH1550H: Assignment:  Questions:  Let’s assume the department of Mathematics of Trent University has 11 faculty members. For i = 0; 1; 2; 3; find pi, the probability that i of them were born on Canada Day using the binomial distributions.

  Caselet on mcdonald’s vs. burger king - waiting time

Caselet on McDonald’s vs. Burger King - Waiting time

  Generate descriptive statistics

Generate descriptive statistics. Create a stem-and-leaf plot of the data and box plot of the data.

  Sampling variability and standard error

Problems on Sampling Variability and Standard Error and Confidence Intervals

  Estimate the population mean

Estimate the population mean

  Conduct a marketing experiment

Conduct a marketing experiment in which students are to taste one of two different brands of soft drink

  Find out the probability

Find out the probability

  Linear programming models

LINEAR PROGRAMMING MODELS

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd