Reference no: EM13793672
Earned Value Problems
Of the three problems below, choose and solve one problem. Show your work. Along with your answer, define each term and explain the significance (meaning) of the solution.
1. During a project, Earned Value Analysis is performed and gives the following numbers:
EV: 523,000; PV: 623,000; AC: 643,000.
Which results are correct?
A. CV: +120,000; SV: +100,000
B. CV: +100,000; SV: +120,000
C. CV: -100,000; SV: -120,000
D. CV: -120,000; SV: -100,000
2. You found the following Earned Value Analysis information for a recently closed out project: SPI = 0.7, CPI = 1.0
A. The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
B. The project's deliverables have all been finished. The project came in ahead of schedule but on budget.
C. The project's deliverables have all been finished. The project came in on schedule but over budget.
3. You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished. You perform Earned Value Analysis and find the following results:
EV: 250,000; PV: 200,000; AC 275,000
BAC is 500,000.
What is right?
A. EAC = 550,000
B. EAC = 525,000
C. EAC = 500,000
D. EAC = 425,000
Role of business information systems
: Role of Business Information Systems
|
How chose inventory policy for local retailer and why
: Consider a local retailer and analyze its inventory policy (as best you can). Make some determination of the retailer's policy on inventory levels, stock-outs, backorders, and safety stock. Provide reasons why you chose those policies for that par..
|
Summary for nostro
: Normal 0 false false false EN-US X-NONE X-NONE Summary for Nostro
|
Earned value problems
: Earned Value Problems, During a project, Earned Value Analysis is performed and gives the following numbers
|
Write about hedonism and stoicism ethical theories
: Write about one of the following ethical theories: Ethical egoism, Hedonism and Stoicism. Your written response is a critical review of the theory, and its application to ethical and unethical behavior in the criminal justice system.
|
The 4 phases of demographic transition
: Describe the 4 phases of demographic transition, including if the population is stable, growing, or declining in each.
|
About apple swott analysis
: Normal 0 false false false EN-US X-NONE X-NONE Apple SWOTT Analysis
|
Values statements are aligned with proposed strategic plan
: How you intend to ensure the organization's vision, mission, people strategies, and values statements are aligned with the proposed strategic plan.
|