Problems 5-1 through 5-2 (Graded)

5-1 Earned Value Calculation

Your project has four activities. Below is the current status of each activity.

Activity A was to have cost $150,000 when complete. Its costs so far are $45,000. It is 35% complete. The activity has completed 5 weeks of a planned 15-week schedule.

Activity B is at the end of week 2 of a planned 4-week effort. It is 45% complete. It was to cost $100,000 when finished. Its costs to date are $50,000.

Activity C is finished. It finished 2 weeks late. It cost $100,000. And it was planned to have cost $110,000.

Activity D is beginning its fourth of a planned 6-week schedule. It has cost $200,000 so far. It was estimated to cost $450,000 when finished. It is approximately 55% complete.

Using this data, calculate the following.

1. What are the PV, EV, and AC for each of the activities and the complete project?

2. What are the SV, CV, SPI, and CPI for each of the activities and the complete project?

3. Assess the project performance to date? Do you get to have the celebration?

Reference no: EM13273401

Questions Cloud

Fantasy sex normal or problematic : Most of us have from time to time fantasized about sexual events they we really do not want to occur. For example research tells us that over 30% of females fantasize about being raped, forced top have sexual intercourse or sexually assaulted. Where ..
Technology and globalizationgen : Technology and GlobalizationGEN499 wk5 dq1
Discuss how managed care sales and marketing : Discuss how managed care sales and marketing have evolved over recent decades, and how these may possibly evolve over the decades ahead.
Same time increasing accessibility of healthcare services. : Discuss which strategies you think will be effective in eliminating waste, control the costs of health services, while maintaining quality of those services and at the same time increasing accessibility of healthcare services.
Earned value calculation-what are the PV-EV and AC : Activity A was to have cost $150,000 when complete. Its costs so far are $45,000. It is 35% complete. The activity has completed 5 weeks of a planned 15-week schedule. Activity B is at the end of week 2 of a planned 4-week effort. It is 45% complete...
The sistine chapel appears in present-day culture : Consider how and where imagery from the Sistine Chapel appears in present-day culture. How has some of the imagery in the chapel become pop-culture icons?
What is general and special revelation : What is general and special revelation? What is the purpose of revelation?
Statements taken in violation of the miranda rule : Statements taken in violation of the Miranda rule may be used to impeach a defendant that testifies inconsistently with his confession. However, an involuntary confession cannot be used for impeachment. What justifies the distinction between these tw..
Stringmethod compareto to compare two strings : Write an application that uses Stringmethod compareTo to compare two strings i

Reviews

Write a Review

Other Subject Questions & Answers

  Cross-cultural opportunities and conflicts in canada

Short Paper on Cross-cultural Opportunities and Conflicts in Canada.

  Sociology theory questions

Sociology are very fundamental in nature. Role strain and role constraint speak about the duties and responsibilities of the roles of people in society or in a group. A short theory about Darwin and Moths is also answered.

  A book review on unfaithful angels

This review will help the reader understand the social work profession through different concepts giving the glimpse of why the social work profession might have drifted away from its original purpose of serving the poor.

  Disorder paper: schizophrenia

Schizophrenia does not really have just one single cause. It is a possibility that this disorder could be inherited but not all doctors are sure.

  Individual assignment: two models handout and rubric

Individual Assignment : Two Models Handout and Rubric,    This paper will allow you to understand and evaluate two vastly different organizational models and to effectively communicate their differences.

  Developing strategic intent for toyota

The following report includes the description about the organization, its strategies, industry analysis in which it operates and its position in the industry.

  Gasoline powered passenger vehicles

In this study, we examine how gasoline price volatility and income of the consumers impacts consumer's demand for gasoline.

  An aspect of poverty in canada

Economics thesis undergrad 4th year paper to write. it should be about 22 pages in length, literature review, economic analysis and then data or cost benefit analysis.

  Ngn customer satisfaction qos indicator for 3g services

The paper aims to highlight the global trends in countries and regions where 3G has already been introduced and propose an implementation plan to the telecom operators of developing countries.

  Prepare a power point presentation

Prepare the power point presentation for the case: Santa Fe Independent School District

  Information literacy is important in this environment

Information literacy is critically important in this contemporary environment

  Associative property of multiplication

Write a definition for associative property of multiplication.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd