Reference no: EM13252145
5-2 Earned Value Calculation
Your project has four activities. Below is the current status of each activity.
Activity A was to have cost $150,000 when complete. Its costs so far are $45,000. It is 35% complete. The activity has completed 5 weeks of a planned 15-week schedule.
Activity B is at the end of week 2 of a planned 4-week effort. It is 45% complete. It was to cost $100,000 when finished. Its costs to date are $50,000.
Activity C is finished. It finished 2 weeks late. It cost $100,000. And it was planned to have cost $110,000.
Activity D is beginning its fourth of a planned 6-week schedule. It has cost $200,000 so far. It was estimated to cost $450,000 when finished. It is approximately 55% complete.
Using this data, calculate the following.
1. What are the PV, EV, and AC for each of the activities and the complete project?
2. What are the SV, CV, SPI, and CPI for each of the activities and the complete project?
3. Assess the project performance to date? Do you get to have the celebration?
State prison system
: For the month of January, Bay Accountants worked 2,000 hours for Lake Lumber, 600 hours for Marty’s Marina, and 1,000 hours for the State Prison System. Bay bills clients at $160 an hour; its labor costs are $60 an hour. A total of 4,000 hours were w..
|
Calculate the surface charge density of each sphere
: two conducting spheres, one of radius 6.0 cm, and the other of radius 120 cm, each have a charge of 20 nC, calculate the surface charge density of each sphere
|
State what is the value of kp for the reaction
: A 12.0 g sample of solic NH4Cl is heated in a 5.00 L container to a high temperature. At equilibrium, the pressure of NH3 (g) is 1.22 atm. What is the value of Kp for the reaction
|
Discuss the diversity-consensus dilemma
: Discuss the diversity-consensus dilemma, including when it is most likely to occur and one possible strategy that a group leader can take to work through the dilemma.
|
Earned value calculation
: Your project has four activities. Below is the current status of each activity. Activity A was to have cost $150,000 when complete. Its costs so far are $45,000. It is 35% complete. The activity has completed 5 weeks of a planned 15-week schedule
|
Find the magnetic deflecting force acts on the proton
: A uniform magnetic field , with magnitude 1.2 mT, is directed vertically upward throughout the volume of a laboratory chamber. What magnetic deflecting force acts on the proton as it enters the chamber
|
Explain the octet and duet rule
: Define the Octet and Duet rule and how it explains the charges on common ions and both covalent and ionic bonding (for representative elements only)
|
Calculate the random access memory
: Calculate the random access memory (RAM) in megabytes necessary to store a multidimensional array that is 20 × 40 × 120.
|
Find the initial rate at which its temperature changes
: A blackened, solid copper sphere that has a radius equal to 4.5 cm hangs in an evacuated enclosure whose walls have a temperature of 23°C. find the initial rate at which its temperature changes
|