During a project earned value analysis

Assignment Help Business Management
Reference no: EM13960542

Of the three problems below, choose and solve one problem. Show your work. Along with your answer, define each term and explain the significance (meaning) of the solution.

1. During a project, Earned Value Analysis is performed and gives the following numbers:

EV: 523,000; PV: 623,000; AC: 643,000.

Which results are correct?

A. CV: +120,000; SV: +100,000

B. CV: +100,000; SV: +120,000

C. CV: -100,000; SV: -120,000

D. CV: -120,000; SV: -100,000

2. You found the following Earned Value Analysis information for a recently closed out project:
SPI = 0.7, CPI = 1.0

A. The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.

B. The project's deliverables have all been finished. The project came in ahead of schedule but on budget.

C. The project's deliverables have all been finished. The project came in on schedule but over budget.

3. You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile

been finished.
You perform Earned Value Analysis and find the following results:
EV: 250,000; PV: 200,000; AC 275,000
BAC is 500,000.
What is right?
A. EAC = 550,000

B. EAC = 525,000

C. EAC = 500,000

D. EAC = 425,000

Reference no: EM13960542

Questions Cloud

What value if interet was compounded quarterly : Type of investment: 36 month CD at 2% compounded daily What value if interet was compounded quarterly? How much is investment worth after 36 months?
Reaction paper that focuses on community treatment orders : Write a 3-5 page reaction paper that focuses on your key issue. You should summarize your issue, including the debate that exists surrounding that issue, and weigh in with an informed opinion
Summarize the business research project or article : Locate a business research article. This project should be one that you perceive to be conducted in an ethical manner. Write a 700- to 1,050-word paper in which you create a set of ethical research guidelines for the research:
Determine the period for planet kep to orbit if the distance : A 2.4 gram penny is on a turntable. It starts from rest at a radius of 0.14 meters and the turntable speeds up until the penny flies off with a tangential speed of .88 m/s. What coefficient of static friction (to three decimal places) exists betwe..
During a project earned value analysis : Of the three problems below, choose and solve one problem. Show your work. Along with your answer, define each term and explain the significance (meaning) of the solution.
Calculate the percent markdown after rebate for the product : Calculate the percent markdown after rebate for the product found in part 1. List three pros and three cons to the practice of markdowns/markups. Debate these points.
How does studying humanities help society in today world : How does studying humanities help society in today's world? How did the 19th century social reformation, such as the European revolution of 1848, influence theatre in multiple countries and religions
Venture capitalists seek to maximize economic returns : Venture capitalists seek to maximize economic returns. Considering all the risks in the development or expansion of business ventures, how do venture capitalists make money? How do venture capital firms balance their portfolios to minimize risks..
What is the speed of the satellite in its orbit : A satellite of mass 150kg is launched into orbit above the surface of the Earth in a circular orbit. what is the speed of the satellite in its orbit? What is providing the centripetal force on it? Find its value.

Reviews

Write a Review

Business Management Questions & Answers

  Caselet on michael porter’s value chain management

The assignment in management is a two part assignment dealing 1.Theory of function of management. 2. Operations and Controlling.

  Mountain man brewing company

Mountain Man Brewing, a family owned business where Chris Prangel, the son of the president joins. Due to increase in the preference for light beer drinkers, Chris Prangel wants to introduce light beer version in Mountain Man. An analysis into the la..

  Mountain man brewing company

Mountain Man Brewing, a family owned business where Chris Prangel, the son of the president joins. An analysis into the launch of Mountain Man Light over the present Mountain Man Lager.

  Analysis of the case using the doing ethics technique

Analysis of the case using the Doing Ethics Technique (DET). Analysis of the ethical issue(s) from the perspective of an ICT professional, using the ACS Code of  Conduct and properly relating clauses from the ACS Code of Conduct to the ethical issue.

  Affiliations and partnerships

Affiliations and partnerships are frequently used to reach a larger local audience? Which options stand to avail for the Hotel manager and what problems do these pose.

  Innovation-friendly regulations

What influence (if any) can organizations exercise to encourage ‘innovation-friendly' regulations?

  Effect of regional and corporate cultural issues

Present your findings as a group powerpoint with an audio file. In addition individually write up your own conclusions as to the effects of regional cultural issues on the corporate organisational culture of this multinational company as it conducts ..

  Structure of business plan

This assignment shows a structure of business plan. The task is to write a business plane about a Diet Shop.

  Identify the purposes of different types of organisations

Identify the purposes of different types of organisations.

  Entrepreneur case study for analysis

Entrepreneur Case Study for Analysis. Analyze Robin Wolaner's suitability to be an entrepreneur

  Forecasting and business analysis

This problem requires you to apply your cross-sectional analysis skills to a real cross-sectional data set with the goal of answering a specific research question.

  Educational instructional leadership

Prepare a major handout on the key principles of instructional leadership

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd