Analytical questions require a clear development of the logic and/or mathematics that lead to the correct answer. A correct answer with no supporting material may be counted as incorrect. Be sure to answer each part (labeled "a", "b", etc.) and show your work in the section provided below each part. The point value for each part is shown.

Answer the questions below with regard to the following table.

ACTIVITY

Immediate predecessor

duration

A

--

6

B

A

20

C

A

5

D

C

2

E

C

6

F

D, E

6

G

B, F

1

(a) Draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task

(b) List the tasks on the critical path

(c) What is the expected project duration in weeks?

(d) What is the slack for each activity? 

Reference no: EM131041066

Questions Cloud

Computing depreciation under alternative methods : Putty Ice Cream Company bought a new ice cream maker at the beginning of the year at a cog,/ 59,000. The estimated useful life was four years, and the residual value was $1,000. Assume that the c; mated productive life of the machine was 16,000 ho..
Determine the maximum and average vertical shear stresses : A simply-supported beam of span 2 m is subjected to a lateral uniformly distributed load of 20 kN/m which causes a maximum vertical shear force of 20 kN at each support. Determine the maximum and average vertical shear stresses within the beam over..
How many of you have a subscription to netflix : How many of you have a subscription to Netflix? What is the value proposition of Netflix? What are the pros and cons of a subscription to Netflix as opposed to regular cable TV service
Violation of generally accpted accounting principles : True or False?? A certain contingent liability was evaluated at year end; the company felt it was probable that it would become an actual liability, and the amount could be reasonably estimated.
Draw the project network and list the earliest start : (a) Draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task (b) List the tasks on the critical path (c) What is the expected project duration in weeks?
Draw the project network and list the earliest start : (a) Draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task (b) List the tasks on the critical path (c) What is the expected project duration in weeks?
Which group represents the smallest number of people : Which of the following is the most common and lucrative way for a terrorist organization to acquire financial support?
Use of standards be appropriate in a non-manufacturing : Would the use of standards be appropriate in a non-manufacturing setting,such as a fast-food restaurant?
Company pollution prevention efforts : How important is corporate philosophy to a company's pollution prevention efforts? Please use an example of one or morecompanies to support your position.

Reviews

Write a Review

Operation Management Questions & Answers

  What is the effect of the lack of synchronization

What is the effect of the lack of synchronization among supply-chain members. The text mentions several common approaches to use when developing a strategy to close a capacity gap where utilization of a resource exceeds capacity available. Which of..

  Illustrate what are advantages also disadvantages of model

Illustrate what are advantages also disadvantages of each model as it pertains to coordination. Networking.

  Action for your business problem statement

Build alternative courses of action for your business problem statement and objectives from last week's discussion posting. You may change your scenario; however, this will entail more work.

  Draw backs of the moving average forecasting model

What are some of the problems and draw backs of the moving average forecasting model?

  Address the impact on the project parameters as a result

Address the impact on the project parameters as a result of these changes.

  What is costco reorder point for each brand of printer

At a local Costco, there are exactly 4 types of ink-jet printers. The weekly demand for printers is estimated to be normally distributed with mean 360. The 4 brands have equal market share on average at that Costco, and the standard deviation of d..

  Fresh mart is a popular grocery store in portland

Fresh Mart is a popular grocery store in Portland, which operates all day. During the late night shift customers arrive at the checkout counters according at 15 customers per hour. The management wants to operate only a single cashier during the l..

  An operations management subject area

Identify three areas of current concern for an Operations Management subject area, identify 5 journal articles discussing this concern and to provide insight and reflection toward recommendations of how to address these issues in the workplace..

  Materials planning committee for advanced technology

The Materials Planning Committee for Advanced Technology Corp., a global manufacturer of precision metal parts for medical analytical devices, is holding its weekly planning and control meeting on Monday at 8 A.M. in the quality control conference ro..

  Calculate the p-chart three stigma control limits to assess

Management in Webster, in Problem 16 is now concerned as to whether caulking tubes are being properly capped. If significant portion of the tubes are not being sealed, Webster is placing its customer in a messy situation. Calculate the p-chart three ..

  What should be included in the policy

After receiving several complaints of sexual harassment, the HR department of a city library decided to estlish a sexual harassment policy. What should be included in the policy? How should it be implemented?

  Computerized numerical controlled

Elon Corporation manufacturers parts for an aircraft company. It uses a computerized numerical controlled (CNC) machining center to produce a specific part that has a design (nominal) target of 1.275 inches with tolerances of 0.024 inch. Compute the ..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd