As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:
Task Duration Immediate Followera 0.2 bb 0.4 cc 0.2 fd 0.4 ee 1.2 gf 1.2 gg 1.0 end
Do each of the following:a. Draw the precedence diagram.b. Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time.c. Determine the minimum number of stations needed.d. Assign tasks to workstations.e. Compute the percentage of idle time for the assignment in part d.
What are the economies of scale in operations management class size? As class size increases, what symptoms of diseconomies
When a small number of large forecast errors needs to be guarded against, what is the measure of forecast accuracy should be used between MAD and MSE?
Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.
You are the manager of the best-performing subsidiary in an MNE. Because bonuses are tied to subsidiary performance, your bonus is the highest of all subsidiary managers
Does it matter what type of information is being gathered? (i.e., purchase patterns versus contact information).
Communication is a two-way process. Communication is a series of loops. A message must be sent and the message must be received.
Assume that Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E.
Which factors apply to the marketing being described in this scenario?
Discuss the relationship between objectives, strategies, and policies.
Develop a material requirements plan that will yield 100 units of product A at the start of week.
Complete with a short discussion for each question. The second question will take several paragraphs to answer thoroughly.
Computer upgrades have a nominal time of 80 minutes. Samples of five observations each have been taken, and the results are as listed.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd