Draw the network-what is the critical path

Assignment Help Operation Management
Reference no: EM13808841

The following represents a project that should be scheduled using CPM:

Times (DAYS)

Activity Immediate Predecessors a m b

A. - 1 3 5

B - 1 2 3

C A 1 2 3

D A 2 3 4

E B 3 4 11

F C,D 3 4 5

G D,E 1 4 6

H F,G 2 4 5

a. Draw the network.

b. What is the critical path?

c. What is the expected project completion time?

d. What is the probability of completing this project within 16 days?

Reference no: EM13808841

Questions Cloud

What external and internal factor affect and how we identify : What external and internal factors affect how we identify ourselves racially/ethnically? How important is it to have or claim such an identity?
Mexican vs united states culture : Mexican vs united states culture
Cost of equipment maintenance and of scrap : Your competitor's cost of equipment maintenance and of scrap (goods that do not meet quality standards and must be discarded) is .5% lower than yours. The engineers have repeatedly found from thorough analysis that the fact that you've been in bus..
Apply a sociological perspective to the social world : Apply a sociological perspective to the social world
Draw the network-what is the critical path : a. Draw the network. b. What is the critical path? c. What is the expected project completion time?
World of business management : Spend some time doing some research and identify someone who might be considered an "icon" of leadership. Your choice does not have to be limited to the world of business management.
Why communication can be affect by culture and relationships : Explain how and why communication can be affected by the following: Culture and Relationships.
Identify three common challenges in managing data : Identify three common challenges in managing data, and describe one way organizations can address each challenge using data governance
Patterns in making government work : Patterns in Making Government Work

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd