Draw the network flow diagram

Assignment Help Project Management
Reference no: EM13805703

The following project data in the dependency table was provided by ABC Ltd IT manager; it relates to a new ICT project to be undertaken.

Activity

 

Duration (Days)

 

PrecedingActivities

 

Start Date

A

 

4

 

-

 

1/06/15

B

 

7

 

A

 

5/06/15

 

C

 

7

 

A

 

12/6/15

D

 

6

 

A

 

19/6/15

E

 

2

 

C

 

25/6/15

F

 

5

 

C

 

27/6/15

G

 

9

 

C

 

02/07/15

H

 

6

 

B, E

 

11/07/15

J

 

6

 

D, F

 

17/7/15

K

 

9

 

H, G, J

 

23/7/15

You are required to:

(i) draw the network flow diagram.

ii) Identify the Critical path and its duration.

(iii) Draw Gantt chart to illustrate the project.

Reference no: EM13805703

Questions Cloud

Central bank directly controls both inside and outside money : Central bank directly controls both inside and outside money. Outside money is that part of the money supply produced by the private banking system. Inside money refers to the quantity of notes and coin in the economy.
General syntax of an sql : In a VBScript SQL Query statement, what Boolean operator can be used to test a set of conditions whereby all conditions must be true?
Amortization of premium affect amount of interest expense : What is the meaning of the following sentence: "Amortization affects the amount of interest expense." How does amortization of premium affect the amount of interest expense? How does amortization of discount affect the amount of interest expense?
Responsibility in implementing change in the department : What is the manager's role and responsibility in implementing change in the department? How should a manager successfully handle staff resistance to change?
Draw the network flow diagram : Draw the network flow diagram - Identify the Critical path and its duration.
Effects of errors in inventory valuation : Show the effect, if any, of each of the following errors on ending inventory, cost of goods sold, gross profit on sales, and net income by placing the appropriate symbol in each column. In use is the periodic inventory system. Use the following symbo..
Strategic concept of a joint venture : Define the strategic concept of a Joint Venture, provide an example of a successful JV and an example of a failed JV somewhere in the world -what are the leadership lessons learned from each example?
Dominant form of institutional venture capital firms operate : The dominant form of institutional venture capital firms operate as?
About the refunding analysis : Mullet Technologies is considering whether or not to refund a $175 million, 13% coupon, 30-year bond issue that was sold 5 years ago. It is amortizing $8 million of flotation costs on the 13% bonds over the issue's 30-year life. Mullet's investment b..

Reviews

Write a Review

Project Management Questions & Answers

  Compare and contrast earned value with planned value

Compare and contrast earned value with planned value. What should a project manager infer if earned value is greater than planned value? Your response should be at least 75 words in length

  Each project passes through different processes initiation

each project passes through different processes initiation planning execution monitoring and control and closing.

  Key planning priorities useful in completing team project

Write key planning priorities that could be most useful in completing a Team Project.

  Closing out a project

Closing Out a Project - how can one incorporate the information gleaned from this session into the future project plans and tools

  Discuss the influence of rationalism in politics

1. Discuss the influence of Rationalism in politics and how it impacts the public's view of government services.

  What would you estimate as itsi dividend growth rate

The Shamrock Dogfood Company (SDC) has consistently paid out 40 percent of its earnings in dividends. The company's return on equity is 16 percent. What would you estimate as itsi dividend growth rate?

  Project evaluation using the marryou just purchased a used

project evaluation using the marr.you just purchased a used car for 3000 and being enrolled in this course you are

  Organizational strengths and weaknesses

What are the organizational strengths and weaknesses?

  Evaluate the total cost of plan

Operations Management-Aggregate production planning - Evaluate the total cost of this plan.

  Functional and dysfunctional conflict on a project

What is the difference between functional and dysfunctional conflict on a project?

  Cost and time methodsas a project manager discuss the cost

cost and time methodsas a project manager discuss the cost and time methods you would chose to work with and why you

  How is conflict management critical to project management

What are the triple constraints and what key elements are interrelated

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd