Draw cost curves for all the projects?

Assignment Help Other Subject
Reference no: EM132523001

Problem Solving

Part -1

Project Costing and Cashflow, and Project Performance Control (EVA)

Problem 1

As senior engineer with a medium-sized construction-contracting organisation you are required to put together a tender for a sewer main extension construction project in Southport. Table details your proposed financial schedule with cumulative direct expenditure and income presented. From this process you determined that the total direct works cost (direct expenditure for labour, materials and other direct overhead costs) was $230,000 and the monthly indirect expenditure for the whole project was $4,000 (such as staff salaries, utility bills, vehicle cost etc), and the contract price should be $330,000. Assume incomes (revenues) were received at the end of each month. From the financial details provided in Table:

a) Determine monthly overdraft (OD).
b) Determine average overdraft, and maximum overdraft,
c) Mark up

Table Financial Expenditure and Income Report

Month

Cumulative Direct Expenditure ($)

Cumulative Income ($)

0

0

0

1

15000

0

2

43,000

22,500

3

67,000

36,000

4

83,000

62,500

5

104,000

89,000

6

130,000

122,000

7

156,000

146,000

8

188,000

170,000

9

210,000

205,000

10

230,000

265,000

11

230,000

293,000

12

230,000

330,000

Problem 2

After week 5 in the project, your project accountant provided you with the latest financial data for four construction packages you are managing (see Tables 1 to 3). Each of the four projects are pipelaying operations of the same time and cost magnitude and very similar site conditions i.e. 8 weeks scheduled time and $91,000 budgeted costs. However, each of these projects has a different site supervisor with different levels of experience and management ability.

Table 1 ACWP Financial Data

Actual Cost of Work Performed (ACWP) - Cumulative Spending (000's)

Project

Week Number

0

1

2

3

4

5

6

7

8

     A

0

1

3

3

4

40

 

 

 

B

0

2

5

5

19

50

 

 

 

C

0

2

5

5

16

50

 

 

 

D

0

3

12

12

20

60

 

 

 

Table 2 BCWS Financial Data

Budgeted Cost of Work Scheduled (BCWS) - Cumulative Spending (000's)

Project

Week Number

0

1

2

3

4

5

6

7

8

     A

0

3

7

13

28

50

73

84

91

B

0

3

7

13

28

50

73

84

91

C

0

3

7

13

28

50

73

84

91

D

0

3

7

13

28

50

73

84

91

Table 3 BCWP Financial Data

Budgeted Cost of Work Performed (BCWP) - Cumulative Spending (000's)

Project

Week Number

0

1

2

3

4

5

6

7

8

     A

0

1

3

9

20

40

 

 

 

B

0

2

5

5

23

40

 

 

 

C

0

2

4

4

22

60

 

 

 

D

0

3

10

10

39

60

 

 

 

From the above-mentioned projects financial information:

a) Draw cost curves for all the Projects? Include BCWS, BCWP and ACWP details and fully label the curves?

b) What are the Schedule Variance (SV) and Cost Variance (CV) for the four projects at week 5? Describe the status of each of the four projects A, B, C, and D detailed above?

c) In detail, describe what may have caused each of these situations in the four work packages? Explore advantages and disadvantages of each situation and outline some deeper management considerations that may have contributed.

Part 2 - Sample Questions

a) Identify key staff members that should be included in ISO 9000 accreditation in a construction organization. Describe five major benefits of the implementation of ISO 9000 which can bring to the employees within an organization.

b) Quality management evolved through four stages- what are the stages? Detail elements contributing to the cost of control and the cost of failure of control for a Quality Management System with a graphical explanation.

c) Discuss the differences between the Traditional Procurement System and the Design and Build System. Briefly describe the advantages, disadvantages and suitable project types of each system. Discuss with examples different contract strategies.

d) Explain clearly the factors affecting the selection of a contracting strategy by a client? Use an illustration to describe what is meant by ‘Prime cost Contract , Partnered Contract, Management Contract, BOOT, and Design build Contract and discuss their main advantages and disadvantages.

e) What are the critical success factors for achieving successful implementation of a Quality Management System (QMS)? Discuss some of the important benefits of ISO 9000.

f) Briefly describe the distinct operations (steps) that should be undertaken when estimating a tender. Briefly discuss the traditional contract operational sequence.

QUESTIONS

You are tendering for a demolition project of a hospital building in Surfers Paradise.

a) Briefly describe the required operations (steps) when estimating this tender. How would you break-down this estimate?

b) Identify five major risks which may be encountered in this project and suggest how you can minimize these risks.

c) Identify five environmental problems that may be encountered in this project and explain methods to deal with them.

QUESTION

The Queensland Government proposes to develop a high-speed train to link the Gold Coast and Brisbane. The Government would like the train to travel at speeds in the range of 150-225 km/hour. It is expected that the train will run express from the existing Coomera station to the South Bank station. The Government would like the elapsed time for travel between the Coomera and South Bank station to be approximately 30 minutes. Your company has been chosen as the consultants to prepare a feasibility report on the proposed fast-train network. Your report for the Queensland Government should address the following areas:

a) Project Appraisal: discuss issues associated with the project's feasibility.
b) Contract Strategy: discuss the advantages and disadvantages of a number of contract strategies suitable for a project of this kind. What contract strategy will you recommend and why? What contractual issues may evolve from this large project?
c) Finance Strategy: Detail a number of project finance options for the project and illustrate the advantages and disadvantages of each option. Describe your chosen finance option and discuss the funding arrangement clearly i.e. Government, private company, consortium, or a combination of these.
d) Risk Management Strategy: Detail the project's most sensitive risk factors, describe their level of impact on the immediate and long-term project performance and recommend strategies to reduce their impact.

QUESTION

After week 5 in the project your project accountant provided you with the latest financial data for the four construction packages you are managing (see Table 2). Each of the four projects are pipe laying operations of the same time and cost magnitude and very similar site conditions i.e. 8 weeks scheduled time and $99,000 budgeted costs. However, each of these projects has a different foreman with different levels of experience and management ability.

Table 2 Project Financial Data

Budgeted Cost of Work Scheduled (BCWS) - Cumulative Spending (000's)

Project

Week Number

0

1

2

3

4

5

6

7

8

A

0

3

7

30

45

60

71

89

99

B

0

3

7

30

45

60

71

89

99

C

0

3

7

30

45

50

71

89

99

D

0

3

7

30

45

50

71

89

99

Budgeted Cost of Work Performed (BCWP) - Cumulative Spending (000's)

A

0

3

3

20

35

40

 

 

 

B

0

2

5

10

23

40

 

 

 

C

0

2

4

20

22

60

 

 

 

D

0

3

10

25

39

60

 

 

 

Actual Cost of Work Performed (ACWP) - Cumulative Spending (000's)

A

0

4

4

30

35

40

 

 

 

B

0

2

5

15

40

50

 

 

 

C

0

2

5

35

45

50

 

 

 

D

0

3

12

20

45

60

 

 

 

From the above-mentioned project's financial information:

a) Draw the cost curve for Project A? Include BCWS, BCWP and ACWP details and fully label the curve?

b) What are the Schedule Variance (SV) and Cost Variance (CV) for the four projects at week 5? Describe the status of each of the four projects A, B, C, and D detailed above?

c) In detail, describe what may have caused each of these situations in the four work packages? Explore the advantages and disadvantages of each situation and outline some deeper management considerations that may have contributed?

d) Identify the under performing projects and suggest some management strategies to regain control of the schedule and/or cost situation?

QUESTION

A simple project consists of 4 tasks as follows
Planned:
Task A $60 per hour, 40 hrs/wk takes 3 wks, Starting Activity
Task B $40 per hour, 70 hrs/wk takes 3 wks, successor of A
Task C $40 per hour, 40 hrs/wk takes 5 wks, successor of A
Task D $50 per hour, 40 hrs/wk takes 2 wks, successor of both B and C
Actual case:
Task A $60 per hour, 40 hrs/wk takes 3.5 wks,
Task B $40 per hour, 80 hrs/wk takes 3 wks,
Task C $60 per hour, 40 hrs/wk takes 4 wks,
Task D $40 per hour, 40 hrs/wk takes 2.5 wks,
Monitor the project performance wk by wk and estimate the critical ratio for the weeks 3, 5, 8, & 10 (hints: first develop the bar chart-then EV Analysis, find out BCWS, BCWP, and ACWP for each wk)

QUESTION
As senior engineer with a medium-sized construction-contracting organisation you are required to put together a tender for a sewer main extension construction project in Southport. Table details your proposed financial schedule with cumulative expenditure and income presented. From this process you determined that the total works cost was $150,000 and the contract price should be $190,000. Consider an Indirect cost 10% of the total Direct cost and needed to distributed uniformly throughout the project life. From the financial details provided in Table:

a) Develop the month wise cashflow table (you do not need to draw graphs) showing monthly over draft.

b) Detail the mark-up, average overdraft and maximum overdraft.

Table Financial Expenditure and Income Report

Month

Cumulative Direct Expenditure ($)

Cumulative Income ($)

0

0

0

1

15000

0

2

23,000

22,500

3

47,000

30,000

4

58,000

42,500

5

74,000

59,000

6

80,000

72,000

7

106,000

86,000

8

118,000

100,000

9

135,000

115,000

10

145,000

150,000

11

150,000

180,000

12

150,000

190,000

QUESTION

As graduate engineer with a small construction-contracting organisation you are required to put together a tender for a sewer main extension construction project in Southport. Figure 1 details your proposed financial schedule with cumulative expenditure and income presented. From this process you determined that the total works cost was $161,080 and the contract price should be $179,080. From the financial details provided in Figure 1:

c) Draw the cash flow diagram for this project?

d) On the developed cash flow diagram detail the mark-up, average overdraft and maximum overdraft?

Reference no: EM132523001

Questions Cloud

Compute the return on common stockholders equity : Common stockholders' equity was $700,000 at the beginning of the year and $820,000 at the end of the year. Compute the return on common stockholders' equity.
What is the plain view doctrine : What is the plain view doctrine? What is inadvertence? Is it a plain view requirement? Give an example of inadvertence.
What is ending retained earnings at june : What would be the date for the Income Statement and Statement of Stockholders' Equity? What is ending retained earnings at June 30, 2019?
What is the equity holders parent Retained Earnings : On January 2, 2019, Polo Corporation purchased 80% of Seed Company's ordinary shares for $216,000. What is the equity holders parent Retained Earnings
Draw cost curves for all the projects? : Draw cost curves for all the Projects? Include BCWS, BCWP and ACWP details and fully label the curves and What are the Schedule Variance (SV) and Cost Variance
Make and interpret a confidence interval for the difference : Make and interpret a 99% confidence interval for the difference in the placebo and the new drug.
Prepare entries on appropriate dates to record declaration : The dividend is paid on December 31. Prepare the entries on the appropriate dates to record the declaration and payment of the cash dividend.
How many different linear arrangements are there of digits : How many different linear arrangements are there of the digits 1, 2, 3, 4, 5, 6 for which:
Determine the weights of the assets in rachel portfolio : Determine the weights of the assets in Rachel's portfolio. Calculate the geometric average return of the portfolio for this period.

Reviews

Write a Review

Other Subject Questions & Answers

  What does the poem look like structurally

What kind of words are used in the poem and how effective is that word choice? How would you describe the writer's writing style?

  Job performance descriptions and appropriate job performance

How will written job performance descriptions and appropriate job performance standards be helpful in any legal action taken by an employee against an organization based on termination for not performing as expected?

  How do you judge your ability to accomplish a goal

How do you judge your ability to accomplish a goal? The concept of self-efficacy refers to beliefs you possess regarding your own capabilities to complete.

  Prepare a persuasive letter to students at tru in which you

actually we are team and we have to do assignment to talk about social media and we choosed linkedin website so here

  Explain what is considered formal and casual

I needed help writing an introduction paragraph on formal and casual fads/styles  Explain what is considered formal and casual. Also write about the age group that wear certain styles

  Consider impact of health care policys evolution on medicaid

Discussion: Stakeholders in Health Care Policy- Consider the impact of health care policy's evolution on Medicaid and Medicare programs.

  Define your view of the analysis of disease and healing

What aspects of the topic readings (The Role of Spirituality in Health Care). do you find the most interesting? What is your view of the analysis of disease.

  How was the data collected and analyzed

How does the content in the purpose statement and research questions define the methodology used in the study?

  How separation of powers and checks and balances are working

Evaluate how separation of powers and checks and balances are working out in practice, today, justifying your assessment with persuasive reasoning and examples.

  Useful for enabling the owl to detect

The barn owl's right ear opens slightly upward while its left ear opens slightly downward. This asymmetry is most useful for enabling the owl to detect the ________ of a sound.

  Victim of sexual abuse

Based on the scenario listed below; do you agree or disagree that this child has been a victim of sexual abuse? Specify if you agree or disagree and support you

  Natural rate of unemployment-cyclical unemployment

Suppose that the natural rate of unemployment in a particular year is 5 percent and the actual rate of unemployment is 9 percent. Use Okun's law to determine the size of the GDP gap in percentage-point terms. If the potential GDP is $500 billion in t..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd