Draw an aoa network diagram representing the project

Assignment Help Project Management
Reference no: EM13962961

Network Diagrams are often used during project planning to give the project manager a visual map of the key activities of the project. Activity-On-Arrow (AOA) is often used to demonstrate the concept of activity sequencing.

Activity

Initial node

Final node

Duration estimate

A

1

2

2

B

2

3

2

C

2

4

3

D

2

5

4

E

3

6

2

F

4

6

3

G

5

7

6

H

6

8

2

I

6

7

5

J

7

8

1

K

8

9

2

Consider Figure the attachment to answer the following questions. All duration estimates are in days, and the network proceeds from Node 1 to Node 9.

1. Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.

2. Identify all the paths on the network diagram and note how long they are, using Figure 152) as a guide for how to represent each path.

3. What is the critical path for this project and how long is it?

4. What is the shortest possible time it will take to complete this project?

5. Examine the network diagram and task schedule table to analyze the critical path and float or slack for each activity.

Write at least a paragraph that interprets this information for someone unfamiliar with project time management.

Reference no: EM13962961

Questions Cloud

Nutritional elements per pound of feed : A farmer can purchase 3 kinds of feed for his stock, with various percentages of each of 4 nutrients, called A, B, C, and D.  A mixture of feeds gives proportional amounts of nutrients.  The following table gives the minimum da..
The triangle has the angles 45,45,90 with a base of length : The triangle has the angles 45,45,90 with a base of length a. The dipole is located at the right base corner pointing in the -x direction.
How many trades must he made to break even : Use the contribution margin ratio CVP formula to compute Big Time's break even revenue in dollars. If the average trade leads to $800 in revenue for Big Time, how many trades must he made to break even?
Annual production capacity : The Sentry Lock Corporation manufactures a popular commercial security lock at plans in Macon, Louisville, Detroit, and Phoenix.  The per unit cost of production at each plant is $35.5, $37.5, $39, and $36.25, respectively, while the annual product..
Draw an aoa network diagram representing the project : Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
Small businesses are undercapitalized : Suppose that 30% of all small businesses are undercapitalized. Forty percent of all undercapitalized small businesses fail and 20% of all small businesses that are not undercapitalized fail. A small business is chosen at random. The probability th..
Describe your company operations and the market : For the company you selected, describe your company's operations and the market in which it operates. Search for the EVA, and free cash flow using the firm's annual report
Discuss the signal a large stock repurchase might foretell : Discuss the signal a large stock repurchase might foretell about management's outlook relative to the future of a company. Explain whether a repurchase of stock is typically a good or bad sign. Provide a rationale for your response
Understand and measure doppler shift : Now test this out. Move to the distance away from the tuning fork you calculated above. How would you describe the loudness of the sound now? Would you say it is twice as loud?

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd