Activity 4.5 - MS Project Practice: AOA Network Diagram
Network Diagrams are often used during project planning to give the project manager a visual map of the key activities of the project. Activity-On-Arrow (AOA) is often used to demonstrate the concept of activity sequencing. Consider Figure 4-30 (page 172 in your textbook) to answer the following questions. All duration estimates are in days, and the network proceeds from Node 1 to Node 9.
Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
Identify all the paths on the network diagram and note how long they are, how to represent each path.
What is the critical path for this project and how long is it?
What is the shortest possible time it will take to complete this project?
Enter the information into Project 2010 or Excel. See the Brief Guide to Microsoft Project 2010 in Appendix A in your textbook for detailed instructions on using this software. View the network diagram and task schedule table to examine the critical path and float or slack for each activity. Print the Gantt chart and network diagram views and the task schedule table to include in your Word Document. Write at least a paragraph that interprets this information for someone unfamiliar with project time management.
Instruction: Provide the answer in Excel file, make sure to cover all the questions mentioned above, required accurate procedure and solution as per described.
Make an accurate forecast of the demand
: The manager of TAPAI PULUT outlet needs to make an accurate forecast of the demand for their product (tapai pulut). The manager has collected the following demand data for the past 8 months
|
What does the lord offer his sheep
: What does the Lord offer his sheep, and what must the sheep do in return, in Psalm 23?Psychological Realism is a method of writing a story in whic?
|
The united states and has sales opportunities in a foreign
: Assume the role of Marketing Manager. Select a product (good or service) that is sold in the United States and has sales opportunities in a foreign market. Apply your critical thinking skills and the knowledge you have acquired throughout this course..
|
Product versus period costs and fixed versus variable costs
: At a dinner party you hosted, a friend of yours who is a college accounting professor-upon hearing you had started your own business-told you to make sure to properly categorize product versus period costs and fixed versus variable costs. The frie..
|
Draw an aoa network diagram representing the project
: Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
|
Calculate and display the weight of the object
: Write a program that calculates the weight of an object on the Earth, Moon, and Mars. Specifically, your final program will choose from a menu to determine the gravity then calculate and display the weight of the object on that body.
|
What is the highest expense for business operations
: 1.What is the highest expense for business operations? How can managers monitor and keep this cost as low as possible? Explain. 2. What is the highest expense for business materials? How can managers monitor and keep this cost as low as possible? Exp..
|
Reorganizations and consolidated tax returns
: Suppose you are a CPA, and you have a corporate client that has been operating for several years. The company is considering expansion through reorganizations.
|
Diesel engine designer watches can be extremely sturdy
: Diesel engine is surely an Italian firm as their principal earnings emanates from offering apparel. These are renowned pertaining to Skinny jeans and also other equipment which have been geared towards diesel watches impacting your junior. The cor..
|