Draw a project network from the following information:

Activity Predecessor Duration
a none 2
b a 4
c a 3
d a 2
e b 3
f c 6
g c d 5
h e f 6
i g 5
j h i 5

Activities b and h can be shortened to a minimum of 2 weeks. Which activity would you shorten to reduce the project duration by 2 weeks? WHY? Must show critical path.

Reference no: EM1343362

Questions Cloud

Formation and operation of partnership : Formation and Operation of partnership - Explain what are the individual capital balances of the remaining partners?
Incentives to invest : What happens if the country you chose provides incentives to invest? Now that your organization is profitable, the country is taking incentives back
Health care organizations political games : Health Care Organizations Political Games - Find three potential political games that health professionals may pursue in health organizations.
The interview with a manager : If so, what factors do you think have caused these changes and has changing technology affected the way you manage
Draw a project network from given information : Activities b and h can be shortened to a minimum of 2 weeks and which activity would you shorten to reduce the project duration by 2 weeks
Effectiveness of the project manager : Evaluation form after project termination for effectiveness of the project manager
Evaluate technical performance : Can the project manager effectively deteremine the functional employee on technical performance? If not, then on what information can the project manager base his evaluation?
Advantages and disadvantages of micromanagement : Micro-Management - Explain what are the advantages and disadvantages of micromanagement?
Checklist versus weighted factor method of selecting project : Show the pros and cons of the checklist versus the weighted factor method of selecting projects - Important information about checklist versus the weighted factor method

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd