Draw a path diagram for the project

Assignment Help Operation Management
Reference no: EM131159038

Have you read, studied, and understood all of the course materials, including the Module Home Page and the sources listed under Background Info?  If you haven't, then do so before attempting this homework.

The Galaxy project consists of 8 interdependent tasks, labeled A through H. You've consulted experts, and have determined an optimistic, likely and pessimistic completion time (in days) for each of the tasks. The dependencies, and the times, are listed below.

Task

Precursor(s)

Optimistic

Likely

Pessimistic

A

(start)

2

6

9

B

A

18

19

20

C

A

10

12

14

D

A

12

18

24

E

(start)

13

1

16

F

B, C, D

8

12

16

G

D, E

6

8

10

H

F, G

17

20

21

(end)

H

 

 

 

1. Draw a path diagram for the project.

2. Calculate the expected length of each task.  Fill in the following worksheet.

Task

Optimistic (O)

Likely (L)

Pessimistic (P)

Expected Task E = (O + 4L +P/6)

A

2

6

9

 

B

18

19

20

 

C

10

12

14

 

D

12

18

24

 

E

13

14

16

 

F

8

12

16

 

G

6

8

10

 

H

17

20

21

 

3. Use the following worksheet to determine the lengths of all possible paths. Determine the critical path. What is its length?

Path (Listing of tasks on the path)

Expected Path Length Ep = ∑E

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The Mojo Project consists of 14 interrelated tasks, A through N.  Their estimated normal completion times, normal costs, crash times and crash costs are given below. (Times in weeks; costs in thousands of dollars.)

Task

Predecessors

Normal Time

Normal Cost

Crash Time

Crash Cost

A

(start)

3

4

2

5

B

(start)

5

6

4

7

C

A

2

3

2

4

D

A

4

8

3

10

E

A

3

5

2

7

F

B

9

14

7

16

G

B

4

5

3

7

H

C, D

4

7

2

9

I

D

6

2

5

3

J

F

12

10

11

15

K

H

4

6

3

7

L

E, I, J

10

18

8

20

M

K, L

8

10

6

14

N

G

7

5

6

8

Use an online application (e.g., Sporkforge, 2014) to find the critical path, using the estimated normal times. Copy the output of the app into your upload as an image.

4. Which tasks are on the critical path?

5. What is the expected completion time of the project?

6. Which (if any) tasks should be crashed, to make up the lost time? Why?

7. What is the additional cost of crashing the project?

Provide references and citations.  At a minimum, you should reference the course materials.

For Part 1: Draw a PERT-CPM diagram clearly showing all the paths, plus the critical path. You may draw the diagram by hand, and paste a scanned image into your upload, but it must be totally legible.

For Part 2: A PERT-CPM diagram is not required.  Use an online app; paste an image of the app output into your paper.

Show, and explain, all the calculations supporting your answers.

Unambiguously state your answers.

There are no guidelines concerning length.  Write what you need to write - neither more, nor less.

Required Reading

Critical path calculator. (2008). Retrieved from sporkforge.com: https://sporkforge.com/sched/critical_path.php

*Rensvold, R. (2014d). PERT-CPM [course page].

Additional Reading

Campbell, S. (1982).  Critical path method.Appraisal Journal, 50(4); 607-15.

Foltz, B. (2012).  Operations management 101:  Critical path analysis part II (Video).  Retrieved on 8 Oct 2014 from https://www.youtube.com/watch?v=acSKQmVsVPg

Attachment:- Assignment.rar

Reference no: EM131159038

Questions Cloud

Which knee joint is absolutely larger and why : What differences exist between the sacral bones of Homo erectus and Australopithecus afarensis shown in Figure 10.4? Which species arrived first? What can we determine about the nature of bipedalism by comparing these two?
Calculate the present value of cash inflows : Calculate the present value of cash inflows associated with each project.  -  Select the optimal group of projects, keeping in mind that unused funds are costly.
Write an algorithm that finds sum of the degrees for a node : Write an algorithm that finds the sum of the degrees for a node, using the adjacency list representation.
Write an algorithm that print minimum spanning tree of graph : Write an algorithm that prints the minimum spanning tree of a graph. At the end, print the weight of the spanning tree. A suggested report format is shown in the following example.
Draw a path diagram for the project : The Galaxy project consists of 8 interdependent tasks, labeled A through H. You've consulted experts, and have determined an optimistic, likely and pessimistic completion time (in days) for each of the tasks. The dependencies, and the times, are l..
What are the different factors to be considered for reactor : During exocytosis in a skeletal muscle, there will be release of calcium ions fromintracellular vesicles in the sarcoplasmic reticulum in response to high levels ofRyanodine binding to Ryanodine Receptors in the transverse tubules.
What is the shortest possible completion time : What is the shortest possible completion time (SPCT)? The SPCT is the longest path through the graph from beginning to end. What is the earliest start time (EST) for each activity?
What lessons might the society of muslim women : What lessons might the Society of Muslim Women (SMW) be able to share with programs that seek to prevent wife abuse in other countries?
Write program that simulates a mouses movement through maze : Write a program that simulates a mouse's movement through the maze, using a graph and a depth-first traversal. When the program is complete, print the path through the maze.

Reviews

Write a Review

Operation Management Questions & Answers

  Assignment on measuring performance

Assignment on Measuring Performance. Gathering performance information is important; however, if it is not used appropriately, it will not lead to the desired outcome. Managers need to understand how to gather and use performance information and be..

  What is the annual inventory turnover

H & H store is a retailer of stationary and paper products. It has an annual cost of goods sold of $100,000 and an average inventory of $50,000. What is the annual inventory turnover? If the industry average is 3 turns per year, how does H & H compar..

  Calculate a cost for training

Your organization has identified an increase in injuries to workers who use the new plant. You are responsible for training in the area where the injuries occur. Your rate (for the exercise) is $360 per day. A training needs analysis concludes a trai..

  Total quality management-involvement of people

"involvement of people". This makes me think about how important team work is. How successful can any company be without teamwork. I enjoy watching sports and even the most talented teams (when looking at individual talent) will not be successful if ..

  Explain what may adversely affect the projects ability to

describe what may adversely affect the projects ability to succeed. consider the amount of change attitudes toward

  Briefly summarize the major sections

Create an introduction that tells what your report is about. Include the Problem Statement that you already created and revised in Part 1. Include terms that readers will need to know in order to understand the report.

  Why is multichannel retailing becoming important marketing

Why is multichannel retailing becoming an important marketing strategy? Use examples to support your statements.

  Comparison between portes notion of importance of careful

Draw a comparison between Portes notion of the importance of careful and sustained analysis of the social context and the red flags of poor decisions.

  Why would producers want exclusive distribution

Explain with reference to the following products: candy bars, batteries, golf clubs, golf balls, steak knives, television, and industrial woodworking machinery.

  Most unions have opposed free trade agreements

Most unions have opposed free trade agreements, such as NAFTA. On the other hand, most employer lobbying groups have supported such agreements. Is each side's viewpoint justified?  How? Please explain.

  Marketing in a global economy

According to the article, Italy poses a "reputational risk" for Starbucks. In a 2-3 page paper, examine some of the challenges Starbuck's faces in addressing that risk.

  Would you be comfortable being evaluated by your peers

Would you be comfortable being evaluated by your peers? By your subordinates? Why or why not? Which source of evaluations and feedback would you see as most credible? Why? How can we deal with the fact that a supervisor may NOT be able to observe an ..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd