Draw a gantt chart using msp

Assignment Help Project Management
Reference no: EM131570823

Please answer any ten of the following questions. If you complete all eleven, I will credit you for the best ten. Each question you answer will be worth ten percent of your final exam grade. Where a question has multiple parts, each part is equal.

1. For the network shown here, calculate the following:
a. Mean duration (μ)
b. Variance (σμ2)
c. Standard Deviation (σμ)
d. Probability that the network can be completed in 50 days or less.

1739_Figure.jpg

2. Given the following project to landscape a new building site:

Activity Immediate Predecessor Activity Duration (days) Resource Used
A - 2 X,Y
B A 2 X
C A 3 X
D B,C 4 X,Y
E D 3 W,X
F D 1 W,X,Y
G E,F 2 X,Y

a. Draw a Gantt chart using MSP.

b. Assume a 5-day week, find the critical path and project duration in days.

c. Given that each resource is assigned 100% to each task, identify the resource constraints.

d. Using the MSP default, level the resource and determine the new project duration and critical path.

e. Identify what alternative solutions can be used to shorten the project duration without overallocating the resources.

3. How might using software tools to report project information lead to problems with control?

4. Review the case and answer questions that follows: BestSoft Enterprises, a leading manufacturer of electronic devices such as television and handheld computers, is currently in the process of developing its next generation device, the model 2000c. A key feature of the 2000c is its color display. According to the original project schedule, the 2000c is to be released 1 month from now. Because the amount of time required to convert the existing software to capitalize on the color display was significantly underestimated, the project has fallen behind schedule. The project manager estimates that without additional resources, the development project will be 3 months late. He has also estimated that increasing the project's budget of $3 million by 30 percent would permit the project to be completed on schedule. The added budget would be used primarily to staff the project with additional software engineers.

If released on schedule, first quarter demand for the 2000c is forecast to be 200,000 units at an initial price of $450. Demand data for similar products suggest that unit sales will increase 5 percent per quarter over the product's 3-year life. Despite pricing pressures in the market, accounting data indicate that BestSoft is able to maintain a 20 percent contribution margin to profit and overhead through continuous process improvements and efficiencies accruing from producing in larger volumes.

Question 1: What has a larger impact on BestSoft's profits, delaying the 2000c's introduction by 3 months or increasing the project's budget by 30 percent?

Question 2: Are there other factors you would consider in addition to profit?

Question 3: What should BestSoft do? Why?

Question 4: How generalizable do you think the results of your analysis in this particular case are to other situations?

5. You are preparing a project to lay fiber optic cable. The first task is to mobilize the team. You estimate this will take one week and cost $3000. The second task is to lay the cable. This will take three weeks and will cost $45,000. The total length of the cable is 15 miles. The last task, which will take one week, is to Terminate and test the cable. You budget $5000 for this. At the end of the first week, you have completed mobilization, but it cost a total of $4500. At the end of the third week, you have completed five miles of cable at a total cost of $28,000 (installation only). It takes you a total of 10 weeks to complete the entire project, for a total cost of $65,000.

a. At the end of week 1:
i. What is your SPI? What is your CPI? iii. What is your EAC?

b. At the end of week 3:
i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?

c. At the end of the project:
i. What is your SPI?
ii. What is your CPI?
iii. What is your EAC?

6. Given the network below:
a. Draw and submit the AOA network
b. What is the critical path?
c. What is the duration of the network?
d. What is the normal (without crashing) cost?
e. What is the minimum duration?
f. What is the new price?

Task

Pred

Norm t

Norm $

Crash t1

Crash $

A

-

3

50

2

150

B

A

4

100

2

150

C

A

5

200

3

300

D

B

6

250

4

350

E

C

7

400

4

600

F

D, E

3

300

2

450

7. Identify which of the following statements is true and which is false:
a. The primary purpose of project evaluation is to give feedback to senior management for decision and control purposes.
b. The original criteria for selecting and funding a project are largely irrelevant for project evaluation.
e. The timing of an audit depends on the purpose of the audit.
d. It is best for the project manager and the project team to make the termination decision.

8. A project that cannot go over budget is considered (pick one):
a. Time constrained
b. Schedule constrained
c. Budget constrained
d. Performance constrained

9. A task has a normal duration of 9 days and crash duration (the minimum duration) of 7 days. Its normal cost (total for 9 days) is $4000 and its crash cost is $10000 (total for 7 days). What is the crash cost per day?
a. $14000
b. $7000
c. $5000
d. $4000
e. $3000

10. Identify which of the following statements is true and which is false:
a. The shortest time to complete a network is equal to the duration of the longest path through the network.
b. The actual project duration will be known with certainty when the project is completed.
c. The difference between EST and LFT is called slack.
d. The start to finish linkage is normally used in situations where it is desirable for two or more activities to finish at the same time.

11. A task is expected to take 20 hours of labor at $25 per hour (direct cost). The required material cost is $500. The organization adds a burden of 30% to all direct labor costs to account for overhead. It does not add any burden on top of material costs. The total task cost is:
a. $500
b. $1,150
c. $1,250
d. $1,300
e. $1,500

Verified Expert

This task provides a clear working example on network models. PERT and CPM concepts are explained clearly with normal cost and time compared with crash cost and time. The probability of completing the project within the specified time was also shown along with the workings. the earned value, actual value and present value workings are also included

Reference no: EM131570823

Questions Cloud

Analyze how the critical success factors apply to the facts : Analyze how the Critical Success Factors (CSFs) apply to the facts of any case study you can find and Provide examples to support your analysis.
Present your analysis to john in form of three page report : Present your analysis to John in the form of a two- to three page report in Microsoft Word following APA format. Make sure you provide a clear recommendation.
Write a health and wellness paper on becoming more confident : Bettering my self worth -- becoming more confident and less anxious/worrisome
What ailments are typically diagnosed : What ailments are typically diagnosed and treated via nuclear medicine procedures?
Draw a gantt chart using msp : PMAN635 - Draw a Gantt chart using MSP and How might using software tools to report project information lead to problems with control?
Identify at least two types of hardware : What personal knowledge management tools does this organization utilize? Identify at least two types of hardware .
Nominal returns on investments : Please respond to the following: Explain why investors are more concerned with the real returns than the nominal returns on their investments.
Developing a fire prevention program : Developing a Fire Prevention Program.Draw ideas from both your occupational and educational experiences and knowledge.
Discuss the secretion of cytokines from leucocytes : Integrins and selectin ligands are involved in the secretion of cytokines from leucocytes

Reviews

Write a Review

Project Management Questions & Answers

  Basic risk response or risk handling strategies

Discuss the four basic risk response or risk handling strategies: avoidance, transference, mitigation, and acceptance. Describe when each strategy applies.

  Billboard campaign on rape creates controversy

Refer to the video "Billboard Campaign on Rape Creates Controversy" in this week's materials. How can billboards such as the ones discussed in the video.

  My cultural anthropology class

In the current chapter we are in my cultural anthropology class, we explored Balinese cockfighting and Spanish bullfighting as examples of deep play. However, even in these societies, not all such events are deep. What makes an event deep? Give examp..

  How many knives should jan produce in each batch

The cost to set up the production process is $100, and it costs Jan $.80 to carry a knife for 1 year. How many knives should Jan produce in each batch?

  Evaluation of the project cost and schedule variances

Evaluation of the project manager's compression of the project schedule - Evaluation of the project cost and schedule variances

  Can you say yes to delvins request

Can you say yes to Delvin's request? If yes, which days would you lend him the backhoe? If not, why not? Thoroughly address the question in a 2-4 page paper.

  Explain your budget contingency plan

Explain your budget contingency plan and how much is budgeted for contingency. Explain your approach to estimating the project cost (e.g., top down, bottom up, etc.) and why that method was chosen

  Explaining use of wbs in a project

How and why you would use a WBS in a project? No particular project, just got stuck on this part of the assignment and needed some input.

  Project closure process are the lessons learned

An important take away of the project closure process are the lessons learned. What should have been done differently?

  Explain communication in groupsthis solution provides an

explain communication in groupsthis solution provides an show analysis on how communication in groups differs from

  Importance breakdown schedule in project management activity

Create the diagram, Create a work breakdown schedule and explain the importance within a project management activity.

  Transferring administrative duties-responsibilities-manager

How can having an office manager be beneficial; other than transferring administrative duties and responsibilities to a capable manager?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd