Do you get completion for iteration

Assignment Help Computer Engineering
Reference no: EM132110157

You are the project manager for a project to add functionality to your company's web site. The project has been broken down into four iterations (releases).

Each of the iterations will take 20 days to complete at a cost of $20,000 per iteration. Today is the end of what should be iteration three.

The current status of the project is as follows: Iteration One complete, spent $20,000 Iteration Two complete, spent $25,000 Iteration Three half done, spent $17,000 Iteration Four Not started.

Please provide the following values: PV, EV, AC, CPI, SPI, EAC, ETC, BAC Also, do you get 75% completion for iteration 3?

If so how did you come up with this answer when it says that iteration 3 is half (50%) complete?

Reference no: EM132110157

Questions Cloud

Perform the gauss elimination method : In this project, you will write the MATLAB code to perform the Gauss elimination method presented in class by completing the following steps:
Which activity has the greates amount of slack : Compare and escribe the advantages/disadvantages of displaying the schedule as a network versus a Gantt chart.
How does corporate law classify the role : How does corporate law classify the role undertaken by Larry leading up to the registration of Lifesaver Pty Ltd? What are the duties that such a person
Achieve your ideal image-your measurable goals : Circle one primary strategy from among these three basic approaches to learning and development - Using your primary strategy, what actions do you need
Do you get completion for iteration : Each of the iterations will take 20 days to complete at a cost of $20,000 per iteration. Today is the end of what should be iteration three.
Develop a database for any department : Your project topic is "Food Court". You may develop a database for any department(s) or service(s) related to a food court.
What is the value of the assets of the business : FNSACC501 Financial business performance analysis and calculations Assignments, Wentworth Institute, Australia. What is the value of the assets of the business
Illustrate the concepts from your written report : Summarize the paper and share your key ideas, via a PowerPoint presentation, with the CTO and steering committee of the organization.
Cluster sampling and stratified sampling : The difference between cluster sampling and stratified sampling would be: There is no difference. It is two names for the same type of sampling.

Reviews

Write a Review

Computer Engineering Questions & Answers

  What is the polymorphic assingment

Why do C++'s capabilites of (polymorphism, encapsulation, inheritance) make programming difficult?what is the polymorphic assingment.

  Which of the following was one reason why electronic

Which of the following was one reason why electronic (computer-based) information sharing was challenging in the not too distant past

  Define your usage of the mailing list

plan an E-R Diagram showing each entity, its attributes, and it relationships to the other entities. State any assumptions you make. Also Describe your usage of the mailing list, including the dates and subjects of the postings.

  Understanding rms values and peak values of voltage current

Understanding rms values and peak values of voltage/current, A personal computer that has a built in monitor and keyboard requires 40W at 115V(RMS).

  How much time will pass before cyclic redundancy checksum

If company transmits a continuous stream of data at 128000 bits per second how much time will pass before cyclic redundancy checksum lets an error slip through?

  Describe how osi model layers can effect a network design

There are two different types of switching technologies available in today's market. One lives on one layer, while the other resides in a different layer.

  Briefly describe your group project reflections

Briefly describe your group project reflections (some of the challenges encountered) in designing your e-business website

  Developing uml sequence diagram for uploading document

For the existing Blackboard system, a system utilized for virtual classroom, grades, messages, and announcements, develop ONE UML Sequence Diagram for uploading the document to Blackboard.

  Where the size is the number of doubles to be sorted

Asks for values and stores them into an array of double. Sorts the values in ascending order according to the following algorithm, where size is the number of doubles to be sorted.

  Create a bi dashboard by using appropriate data analysis

You will need to understand the data provided and determine how data should be loaded and linked in your dashboard application. In the process of doing this, should you find some fields provided to be unnecessary for your dashboard, you can choose..

  Write an analysis of four papers on topic in Robotics

SIT740 Research and Development in Information Technology Assignments. Write an analysis of four papers on a given topic in AI & Robotics

  What the internet has to offer to educate people in this

project portfolio management methoda project portfolio management is to ensure that projects are aligned with strategic

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd