Do a network diagram and a pdm for the given project

Assignment Help Project Management
Reference no: EM131028077

CASE STUDY: CONSTRUCTION

Craig Construction: Home Improvement Project

Having completed the quality planning of the project, Nash wanted to set the expectations of schedule performance with Craig. He asked Craig, "What is the order in which you are planning to do the job?"

Craig answered, "Let's see...I will write down the activities for you."

Nash asked Craig to let him know the order in which the activities had to be completed. Craig took out paper and started writing down the activities with their duration& He wrote which of the activities would take precedence over the others.

Nash looked at the list and asked Craig, "So the only activities that can be done at the same time are the window installation and the roof and sky-light installation?"

Craig replied, "Yes."

Nash entered all this information into Microsoft Project.

Case Questions

a) Draw a network diagram and conduct critical path analysis.
b) Do a scenario analysis for installation of windows lasting four days.
c) If Craig hires one more person for $80 a day and tries to bring back the installation of windows to two days, what is the crash cost?
d) How can you fast-track the project? How many days can you save by fast-tracking?

Reference no: EM131028077

Questions Cloud

Determine the overall power gain and dissipated power : Two amplifiers are cascaded. The first has supply power of 2W, an input resistance of 1 M Ω, and an input voltage of 2 mV rms. The second has a supply power of 22 W, a load resistance of 8Ω, and output voltage of 12V rms. Determine the overall po..
Do you see emerging forces that may reshape csr in future : What are the five environmental forces propelling greater interest in CSR? Explain using real-life examples to illustrate your points. Do you see emerging forces that may reshape CSR in the future?
Affect organizational culture positively or negatively : If your employer asked you to review the decision not to hire an African American applicant for a job, what would you need to consider? Discuss several areas in which HR can affect organizational culture positively or negatively.
Determine efficiency and power dissipated in them amplifier : Under high-signal test conditions, a certain audio amplifier supplies a 24 V rms 1-kHz sinusoidal voltage to an 8- Ω load. The power supply delivers 4 A at a voltage of 50 V to the amplifier. The signal power supplied by the input source is neglig..
Do a network diagram and a pdm for the given project : Do a network diagram and a PDM for this project. Do a scenario analysis for the installation of windows lasting four days. Input all the information provided by Craig into Microsoft Project.
General environmental analysis-technological segment : The men's warehousing: General Environmental Analysis, i.e Economic segment, political/ Legal segment, socio-cultural segment, Technological segment, Global segment and Driving Forces.
Would this affect their status as independent contractors : Suppose Celia and Mary want to require the men, when they are not selling, to do inventory and clean up the boutique. Celia and Mary also set the men’s working hours. Would this affect their status as independent contractors? If so, can they still pa..
Find power dissipated in amplifier - efficiency of amplifier : A certain amplifier has an input voltage of 100 mV rms, an input resistance of 100kΩ, and produces an output of 10Vrms across an 8-Ω load resistance. The power supply has a voltage of 15 V and delivers an average current of 2 A. Find the power dis..
What is your current approach to personal evaluation : What is your current approach to personal evaluation and how do you plan to sustain teach ability and encourage evaluation in your life while completing the master’s program?

Reviews

Write a Review

Project Management Questions & Answers

  Explain about communication principle

Will you briefly describe this principle and what it is about - which one is the most important and why and how does this communication principle help one understand organizational communication

  Should a project manager continue patting team members

Based on your experiences of working with a team member from a different culture, should a project manager continue to pat team members on the back in a gesture of appreciation for a great job done or is it best to avoid this gesture?

  Buiness management

Evaluate your current or former manager on each of the five components of emotional intelligence and explain how you can apply the principles of emotional intelligence to your current situation?

  Formula for expected production and costscountry heather

formula for expected production and costscountry heather manufactures flowerpots. it expects to sell 40000 flowerpots

  Expand for the enterprise-level projecttodays organizations

expand for the enterprise-level projecttodays organizations must recognize that the profile of enterprise-level

  Checklist versus weighted factor method of selecting project

Show the pros and cons of the checklist versus the weighted factor method of selecting projects - Important information about checklist versus the weighted factor method

  How has the passage and enactment of numerous federal and

how has the passage and enactment of numerous federal and state laws affected the employment selection process?identify

  Factors that influence the choice of accounting systems

Summary of the attached power points to illustrate understanding of topics covered. 2) Find the the latest research on the topic. Resources should include journals, book , video and digital/audio resources etc. 3) Based on the latest references, c..

  Describe the benefits that shall be derived from the project

Write a 500 to 700 word project proposal summary: Describe the project. Outline the principle project stakeholders. Describe the benefits that shall be derived from the project

  Project managers to resist changes to the project baseline

Why is it important for project managers to resist changes to the project baseline and under what conditions would a project manager make changes to a baseline?

  Draw the aon project network

(a) Draw the AON project network. Only nodes and directed arrows are required in the network for full credit. (b) Calculate the expected activity time for each activity. (c) Calculate the variance of the activity time for each activity.

  Probability of project completed by desired completion date

Which of the following alternatives gives the probability that the project will be completed by the desired completion date?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd