Case: The Bradley Fighting Vehicle, a fixture of the U.S. Army's inventory, has been in service since 1981. It has been used in combat in the 1991 Gulf War, in Somalia in 1998, in Bosnia in 1999 and in Afghanistan in 2001. Although it has been deployed reasonably successfully in combat, the case of the Bradley Fighting Vehicle (BFV) is an example of a project whose original scope was altered so greatly that the project finally achieved a life of its own, seemingly divorced from its original goals. An armoured personnel carrier (APC) is a large tracked vehicle with minimal offensive firepower. Its job is to take troops riding inside into battle areas as quickly as possible. In combat the APC works with other armoured vehicles to develop and exploit breakthroughs on the battlefield. The Bradley, manufactured by FMC Corporation was conceived and designed in the early 1960s to replace the army's M113 APC. Original specifications of the Bradley design included: 1. The capability to transport the entire infantry squad (12 soldiers) 2. A top speed to keep paced with other armoured vehicles 3. Strong side armour to protect the crew and infantry riding in the vehicle 4. The ability to travel through water and 5. Minimal offensive firepower to travel light Although the initial plans suggest a fast turnaround for the project, almost two decades later the Army received a vehicle: 1. that could transport only six personnel 2. Was so lightly armoured that enemy weaponry could easily penetrate its sides 3. Sank like a stone when attempting to cross rivers and 4. Carried a hefty full component of machine guns, a 25mm cannon and anti-tank missiles. Its realisation was completely out of proportion to the role on the battlefield originally conceived for it. What went wrong? Perhaps the biggest problem that hampered the development of the Bradley almost from the beginning was the failure of the army to come to a definitive agreement on the role the Bradley was to play on the modern battlefield. As mentioned earlier, the army began simply with the need to replace its older APC, Army brass designed it to be deployed against Warsaw Pact forces in Europe. However, they quickly added another requirement: that the Bradley serve in the dual role of armoured scout. These two missiles were not compatible. Heavy armour, large size and weaponry only for defensive purposes were the qualities that defined an APC. An armoured scout needed to trade armour plating for extra speed. Further a scout's mission was also more offensive, requiring that the vehicle be outfitted with a full complement of weapons, including a turret with cannon, machine gun, and anti-tank missiles. The army's lack of clarity for the Bradley's basic mission doomed it to serve poorly in both roles. It also dramatically lengthened the development cycle. Redesign followed redesign and modification followed modification, rapidly consuming the budget and stretching development out through the administration of five US presidents. Once put into production at FMC Corporation, the Bradley was also plagued by poor quality control. Employee whistleblower Henry Boisvert and others routinely witnessed sham testing, falsified documents, and poor quality control on the assembly lines. Army tests were no better conducted as the Air Force officer in charge of operational testing and evaluation, Colonel Burton, discovered. Some live fire tests were rigged and some results were fabricated. In order to maintain an acceptable top speed, the Bradley sacrificed standard armour plating in favour of a form of aluminium that burned easily while giving off deadly fumes. Further to support the weapon complement necessary for the vehicle to serve as an armoured scout, the interior of the vehicle was much smaller. Since 1981 when the Bradley originally rolled off the assembly line, more than 6700 have been put into service by the US Army. From the outset, the vehicle has faced a mixed reception. Advocates argue that it serves a useful role in the modern, highly mobile army. Critics point out that as a result of its poor initial project scope and the Army's willingness to make numerous dramatic changes to the role of the Bradley midway through development, the army was left with a dangerous lemon. All of this cost the army over $14 billion. Source: Pinto (2019) Answer ALL the questions in this section.

Question 1: When is scope creep useful and when is it dangerous? Under what circumstances should an organization refuse to freeze project design specifications for valid reasons? Relate your response to the case study.

Question 2 Discuss what the Bradley project suffered from and explain how this problem directly affected the Bradley's final design.

Question 3 Suppose you were brought in as a consultant for the Bradley development during the1960s. What would have been some of the warning signs of development problems you could have observed?

Question 4 Develop a strategy for managing the various stakeholders' scope requirements on the Bradley project. In terms of its scope, are there middle ground compromises you can identify?

Reference no: EM133349007

Questions Cloud

What are the funds required for a start up recruitment : What are the funds required for a start up recruitment company? The business model, funds required, costs, revenue streams so that the company is sustainable
What do you think are his greatest strengths : What do you admire about him/her? What do you think are his/her greatest strengths? What qualities attributed to his/her success as a role model? Explain your
How does the organization ensure the situation : As a Project Manager, how does the organization ensure the situation does not reoccur in the Telestar International Case study?
Does democracy require equality of income or wealth : Does democracy require equality of income or wealth? Discuss why democracy might make a country more or less egalitarian?
Discuss what the bradley project suffered : Discuss what the Bradley project suffered from and explain how this problem directly affected the Bradley's final design
What the five requirements that enhance decision making : What the five requirements that enhance decision making organization what are the reason of time overrun in your project
Differences between piagets and eriksons theories : Explains the similarities and differences between Piaget's and Erikson's theories.
Discuss the seven common characteristics : discuss the seven common characteristics of highly successful strategic projects - Strategic Project Management
Identify the key roles who may be involved in this business : Identify the key roles/team who may be involved in this business analytic project team. Justify the recommendation with valid reference by discussing

Reviews

Write a Review

Project Management Questions & Answers

  BUS 407 Project Management Assignment

BUS 407 Project Management Assignment help and solution, Emirates College of Technology - assessment writing service - Explain the project idea

  Detail a dispute resolution method

Detail a dispute resolution method and identify an organization which is involved in the dispute resolution process. At least one apa style reference.

  Goods production and service operation

What are five similarities between goods production and service operation?

  Explain primary stakeholders of the project

The project was a very expensive multimillion US dollar construction of a sporting facility, in Montego Bay, Jamaica The facility would span over 350 acres of l

  Compare and contrast project management approaches

Compare and contrast project management approaches and their appropriateness for managing a variety of project types.

  What are the main types of contingent pay

What are the guiding principles for grade and pay structures?-  What is contingent pay?-  What are the main types of contingent pay?

  Analyzing the barriers of effective communication

ANALYZING THE BARRIERS OF EFFECTIVE COMMUNICATION IN CONTEXT OF ENGINEERING PROJECT - You must submit both Draft Proposal and Final Proposal in Word format

  Effectiveness and efficiency of the project team

Which of the techniques below would not likely improve the ?effectiveness and efficiency of the project team

  Create a talking heads style

create a Talking Heads style video in which you, as a manager (or HRD professional), present a ‘verbal pitch' to a senior management team

  Perform some of the risk management steps

Propose four possible risk events that could be triggered by the COVID-19 pandemic and explain how they might affect the project

  Agile project management differs from traditional project

Research on Agile Project or How Agile Project Management Differs from Traditional Project.

  What you intend to do each week to ensure timely completion

A project plan that briefly outlines what you intend to do each week to ensure timely completion of your capstone project.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd