PRTI is a company whose primary business' focus is on upgrading servers for manufacturing companies. The company has a thorough knowledge of all aspects of its business, and a structured approach to manage this type of project, as shown below.
There are some indirect costs for the project, estimated on a daily basis: the first 30 days have indirect costs of $500/day, and all subsequent days $800/day.
below. Task
Code
Immediate Predecessor
Normal
Time
(days)
Crash
Normal Cost
(x100)
Crash Cost
Review system requirements for upgrade
A
None
3
2
$5
$20
Plan for clients
B
1
$2
Gather information about your Project Server 2016 environment
C
---
$12
Plan to upgrade customizations
D
B & C
$28
$40
Prepare your environment for upgrade
E
9
6
$30
$90
Upgrade your databases and Project Web App site collections
F
4
$17
$34
Consolidate your Project Server 2016 databases to a Project Services database
G
$32
Attach the Project Services database to the web application
H
$4
Check your Project Services database for errors that can cause upgrade to fail
I
Upgrade the Project Services database
J
8
5
$16
Mount the Project Web App instance
K
H & J
$8
Check the Project Web App instance for issues that can cause upgrade to fail
L
Upgrade the Project Web App instance
M
$38
a) If the company requires a markup of 25%, what should be the total price charged for a normal [standard] project?
b) Examine and discuss PRTI's decision to propose a potential client to upgrade its server for a total amount of $50,000, completed in 31 days.
c) A key member of the project, recommended to the project manager to study the uncertainties exhibited in prior similar projects. The project management gathered the information and found that the duration of six of the tasks could be modeled as Beta distributions. Based on the following information (without "crushing"), what is the probability that a project could be completed between 30 and 38 days?
Activity
Normal Time
Optimist
Most Likely
Pessimist
14
0.5
12
1.5
Evaluate characteristics of new workplace. Assume you are a manager with over 20 years of experience. Illustrate what challenges have you faced as required competencies have changed.
Discuss three of the most common mechanisms for institutionalizing ethics in an organization.
What are some of the biggest challenges and opportunities that exist for managers in using organizational behavior concepts?
A strategic management plan addresses four different management functions: environmental scanning, strategy formulation, strategy implementation.
What are vulnerable populations? Why are they vulnerable? Where might you encounter vulnerable people in your daily life?
As a member of management for an organization, would you require employees to participate in firefighting operations? Why or why not? To what level would you require employees to participate in firefighting operations?
Determine which project might be implemented and why (e.g. feasibility study, breakeven analysis, etc). Describe the five phases of a project
Pre-existing Duty: Melissa Faraj owns a lot and wants to build a house according to a particular set of plans and specifications. Discuss whether or not construction companies can raise the price of completing construction contracts based on inflatio..
What impact does poverty have on other areas of the families' lives, such as mental health, substance abuse, physical health, etc?
Suppose that a household in a two-period model has income of $30,000 in period 1 and $25,000 in period 2, and interest rate is 75%.
Which decision trap are we trying to avoid when we evaluate a decision model using minimax regret?
Analyze this case in your mind and then state the legal issues to be considered.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd