Different types of flows in a process

Assignment Help Mathematics
Reference no: EM131737811

Managing Process Flows

Discussion Questions and Exercises

5.1 Explain in your own words the different types of flows in a process.

5.2 What is the relationship between WIP and the input and output rates over time?

5.3 A Burger King processes on average 1200 customers/day (over the course of 15 h). At any given time, 60 customers are in the store. Customers may be waiting to place an order, placing an order, waiting for the order to be ready, eating, and so on. What is the average time that a customer spends in the store?

5.4 A branch office of the University Federal Credit Union processes 3000 loan applica-tions per year. On the average, loan applications are processed in 2 weeks. Assuming 50 weeks/year, how many loan applications can be found in the various stages of processing within the bank at any given time?

5.5 In Exercise 5.3, it is mentioned that at any given time, one can find 60 customers in the store. How often can the manager of the store expect that the entire group of 60 customers would be entirely replaced?

5.6 The process of designing and implementing a website for commercial use can be described as follows. First, the customer and the web design team have an infor-mational meeting for half a business day. If the first meeting is successful, the cus-tomer and the web design team meet again for a full day to work on the storyboard of the site. If the first meeting is not successful, then the process is over, which means the customer will look for another web designer. After the storyboard is completed, the site design begins; immediately after that, the site is developed. The design of the site typically takes 10 business days. The development of the site requires 2 business days. While the site is being designed and developed, the contents are prepared. It takes 5 business days to complete an initial draft of the contents. After the initial draft is completed, a decision is made to have a marketing team review the initial draft. Experience shows that about 60% of the time the marketing review is needed and 40% of the time the final version of the contents is prepared without the marketing review. The marketing review requires 3 business days, and the preparation of the final version requires 4 business days. The contents are then put into the site. This activity is referred to as building. (Note that before the building can be done, the development of the site and the contents must be completed.) Building the site takes about 3 business days. After the site is built, a review activity is completed to check that all links and graphics are working correctly. The review activity typically is com¬pleted in 1 business day. The final activity is the approval of the site, which is done in half a business day. About 20% of the time, the sites are not approved. When a site is rejected, it is sent back to the building activity. When the site is approved, the design process is finished.
a. Draw a flowchart of this process.
b. Calculate the CT.

5.7 Consider the process flowchart in Figure 5.11. The estimated waiting time and pro-cessing time for each activity in the process are shown in Table 5.11. All times are given in minutes.
a. Calculate the average CT for this process.
b. Calculate the CT efficiency.

1733_figure.jpg

TABLE 5.11
Time Data for Exercise 5.7

Activity

Waiting Time
(Min)

Processing Time
(Min)

A

7

3

B

5

8

C

4

2

D

10

5

E

7

2

F

0

3

G

2

5

H

8

9

1

2

8

TABLE 5.12
Resource Assignments for Exercise 5.8

Activity  Resource Type
A R1
B R2
C R2
D R2
E R3
F R3
G R4
H R4
I R1

5.8 For the process in Exercise 5.7, assume that the resources in Table 5.12 are needed in each activity. Also assume that there are two units of R1, three units of R2, two units of R3, and two units of R4.
a. Calculate the theoretical process capacity and identify the bottleneck.
b. If the actual throughput has been observed to be 6 jobs/hour, what is the capacity utilization?

5.9 For the process flowchart in Figure 5.12, where the numbers between parentheses are the estimated activity times (in minutes), calculate the average CT.

5.10 Assume that the processing times (in minutes) for the activities in Exercise 5.9 are estimated as shown in Table 5.13. Calculate the CT efficiency.

5.11 Assume that four resource types are needed to perform the activities in the pro¬cess of Exercises 5.9 and 5.10. The resource type needed by each activity is shown in Table 5.14.
a. Considering that there are two units of resource 1, two units of resource 2, three units of resource 3, and three units of resource 4, calculate the capacity of the process.
b. If the actual throughput of the process is 2.5 jobs/h, what is the capacity utilization?

112_figure1.jpg

TABLE 5.13
Processing Times for Exercise 5.10

Activity Processing Time (Min)
A 13
B 2
C 15
D 13
E 20
F 28
H 25
I 11
J 15
K 12
L 5
M 5
N 11

TABLE 5.14
Resource Assignments for Exercise 5.11

Resource                                     Activities

1                                          A, E, and G

2                                           B, D, and J

3                                           C,I,K,andNI

4                                          F, H, L, and N:

5.12 Three teams (T1, T2, and T3) work in the process depicted in Figure 5.13, where the numbers in each activity indicate processing times in minutes. Calculate the capacity utilization of the process assuming that the throughput is 1 job/h.

5.13 Consider the business process depicted in Figure 5.14 and the time values (in minutes) in Table 5.15. Use CT efficiency to compare this process with a redesigned version where the rework in activity G has been eliminated and activities D, E, and F have been merged into one with processing time of 10 min and zero waiting time.

2323_figure2.jpg

figure 5.13

2273_figure3.jpg

figure 5.14

5.14 Nine people work in the process depicted in Figure 5.15. The numbers next to each activity are processing times in minutes. Table 5.16 shows the assignment of workers to activities.
a. Calculate the capacity of the process in jobs per hour.
b. Management is considering adding one worker to the process, but this would increase the operational cost by $23/h. Management knows that increasing the process capac¬ity by 1 job/h adds $30/h to the bottom line. Based on this information, would you recommend adding a worker, and if so, with whom should the new person work?

854_figure4.jpg

figure 5.15

847_figure5.jpg

figure 5.16

5.15 A process management team has studied a process and has developed the flowchart in Figure 5.16. The team also has determined that the expected waiting and process¬ing times (in minutes) corresponding to each activity in the process are as shown in Table 5.17.
a. Calculate the average CT for this process.
b. Calculate the CT efficiency.

TABLE 5.17
Time Data for Exercise 5.15

Activity

Waiting Time
(Min)

Processing Time
(Min)

A

20

12

B

15

18

C

5

30

D

12

17

E

3

12

F

5

25

G

8

7

H

5

10

1

15

25

1

5

20

K

4

10

1580_figure6.jpg

figure 5.17

5.16 A process-design team is analyzing the capacity of a process. The team has devel-oped the flowchart in Figure 5.17. The numbers between parentheses indicate the processing times in minutes, and the labels above or below each activity indicate the resource type (i.e., R1= resource 1). The process has one unit of resource R1, two units of resource R2, and three units of resource R3. Assume that a reworked job has the same chance to pass inspection as a regular job.
a. Calculate the theoretical process capacity and identify the bottleneck.
b. If the actual throughput rate of the process is 1 job/h, what is the capacity utilization?

5.17 Use the TOC and the data in Tables 5.18 and 5.19 to determine how many units of each job type should be completed per week in order to maximize profits. Consider that the availability is 5500 min for resource R1, 3000 min for resource R2, and 8000 min for resource R3.

5.18 An order fulfillment process has demand for three order types during the next 4 weeks, as shown in Table 5.20. The assignment of activities to workers and process¬ing time for each activity are shown in Table 5.21. All workers have 40 h/week available to work on this process. Use the TOC principles to find the number of orders of each type that should be processed to maximize total profit.

408_table.jpg

Textbook - BUSINESS PROCESS MODELING, SIMULATION AND DESIGN - SECOND EDITION by Manuel Laguna and Johan Marklund

Reference no: EM131737811

Questions Cloud

Discuss civic engagement and becoming community : Could you please assist me, Please choose one of the below sayings and explain how you feel it relates to service learning, civic engagement
What are the causes of doubt : Can one lead to the other? What are the causes of doubt? What are its effects? Is there a "solution" to doubt?
Discuss ways that customer service offerings are changing : Explain the difference between inbound calls and outbound calls
Discuss about ivan danko from red heat to viktor navorski : Compare Ivan Danko from Red Heat to Viktor Navorski from The Terminal. This assignment is for a very short essay.
Different types of flows in a process : Explain in your own words the different types of flows in a process - how many loan applications can be found in the various stages of processing
Increase the ratio of capital spending to gdp : The investment tax credit was designed to increase the ratio of capital spending to GDP and hence boost productivity growth. The credit was introduced in 1962.
Choose the significance level : Conduct a hypothesis for whether consumption and income are linearly related using a=0.01 . The standard error of the slope is 0.144.
Describe how the book is organized : Describe how the book is organized. What is the theme of the book? In other words, what is the main idea?
Discuss generally treasure ideas of personal freedom : People in modern industrial and post industrial societies generally treasure ideas of personal freedom, individuality and privacy

Reviews

Write a Review

Mathematics Questions & Answers

  Finding the exact value of the trigonometric function

This problem is basically belongs to Mathematics as well as it is about finding the exact value of the trigonometric function.

  Explain which is the larger number

Which is bigger - the cube root of 24, or the fraction 10/3 ?  Without using a calculator come up with at least two ways to explain which is the larger number that could be understood by a middle school student.

  Find the equations of the tangent lines at the given point

A graph of the plane curve x(t) = t3-4t, y(t) = t2. The graph crosses itself at the point (0, 4). Find the equations of the tangent lines at this point.

  What percentage of architects have z scores

Suppose that the scores of architects on a particular creativity test are normally distributed. Using a normal curve table (page 477-480), what percentage of architects have Z scores

  A new drug for combating obesity

Scenario: MRK Pharmaceuticals has just developed a new drug for combating obesity. During the preliminary drug trials, it was also found to be effective in lowering cholesterol. MRK must now submit the drug for FDA approvals. They must decide if they..

  Finally solve using factoring

Consider the equation (x - 1)(x + 2) = 5(x - 1). First, solve this equation by dividing each side of the equation by x-1.Second, solve the equation by first "FOIL"ing the left side, then simplifying by bring all terms to the left side of the equation..

  Explain what is a binomial factor

What is a binomial factor? In your own words, describe the process of factoring by grouping. Explain how the distributive property is used in this process. Give a detailed example of this process.

  Identify the population of interest to the researcher

He found that the average number of semester units completed was 12.96 units per student. Identify the population of interest to the researcher.

  Servant leadership mentality in an organization

In a 150-300 word post, discuss ways leaders and managers can create a servant leadership mentality in an organization. What are the pros and cons of servant leadership?

  Calculating probabilities

What is the total defect rate? I came up with 6%. A randomly selected product was defective. What is the probability that it came from Plant A?

  What shape will require the least amount of material

A Y-shaped metal bracket is to be made such that its height is 10.0 cm and its width across the top is 6.00 cm. What shape will require the least amount of material? See Fig. 27.52.

  Intellectual property clause regarding ownership of ip

Intellectual Property (IP) Clause regarding ownership of IP Write a paper of 700- to 1,050-words in which you explain the following: Explain any legal issues regarding your selected clause

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd