Atkinson Engineering Company (AEC) develops quick fat burning exercise machine. This exercise machine can burn the fat very quickly with little effort. Gym Fitness Club (GFC) gave first order to supply 12 units. AEC produced and supplied these 12 units to GFC. Three factors involved, technical labor hours, assembly labor hours and cost of material. The first unit produced by AEC took 125 technical labor hours, 45 assembly labor hours and material cost was $1275 per unit. They determined learning rate of 70% in technical labor hours, and 85% in assembly labor hours. AEC pay $40 per hour to their technical labors and $30 per hour to their assembly labors.

Gym Fitness Club placed another order (1st follow-on contract) for 28 units immediately after receiving the first order. Learning in both factors continues and AEC pay rate to its labor and cost of material is not changed.

(a) What would be the total cost of this follow-on contract? 80504 DOLLARS

(b) What will be the cost of 10th unit of this follow on contract? 2948 DOLLARS

(c) GFC placed another order for 140 more units. Suppose there was significant delay between the second order and this follow-on order. During this time, equipment, personnel from technical and assembly department were released to other projects. AEC increased 15% pay rate of technical and assembly labors and cost of material increased by 20%.

(c-i) Assume that conditions are totally in AEC favour; that means the learning continues, what would be the total cost of this 2nd follow-on contract?

(c-i) Assume that conditions are totally not in AEC favour; that means the learning achieved by completing previous two orders didn’t continues at all, what would be the total cost of this 2nd follow-on contract?

Reference no: EM132227325

Questions Cloud

Determining appropriate integrated communication mix : Identify and analyze 4 factors that you consider are foremost in determining an appropriate integrated communication mix.
Communication in the digital age virtual session : After viewing the “Your Body Language” talk assigned for this “Communication in the Digital Age” virtual Session,
Currently positioned in the product life cycle : Identify where Moisturizing Black Soap Shampoo is currently positioned in the product life cycle.
Emotional intelligence in labor and delivery : What is your opinion of Dr. Jones’s emotional intelligence (EI)? Based on a scale of 1–10, with 1 being lowest, how would you rate Dr. Jones? Why?
Develops quick fat burning exercise machine : Atkinson Engineering Company (AEC) develops quick fat burning exercise machine.
Reasoning behind whole foods generic level strategy : What is the reasoning behind Whole Foods’ generic level strategy?
Responsible for the day to day operation of the restaurant : Santana is a manager at a local Tex-Mex restaurant where she is responsible for the day to day operation of the restaurant.
Extraordinary preparation when meeting client organization : Explain why a salesperson don't just need preparation but need extraordinary preparation when meeting the client organization?
What other processes can an airline examine : What other processes can an airline examine? why is each important?

Reviews

Write a Review

Operation Management Questions & Answers

  Estimate for the difference between two population means

All other things held constant, increasing the level of confidence for a confidence interval estimate for the difference between two population means will result in a wider confidence interval estimate.

  What is the economic production quantity

Pioneer Electronics is thinking about making their own video cards which have an demand of 21,940 units. What is the Economic Production (run) Quantity?

  What is the economic production? quantity

Race One Motors is an Indonesian car manufacturer. At its largest manufacturing? facility, in? Jakarta, the company produces subcomponents at a rate of 310 per? day, and it uses these sub components at a rate of 12,100 per year? (of 250 working? days..

  Increase or decrease work pressure and stress

Explain how personality, satisfaction, motivation and job characteristic can make an individual more or less susceptible to the effects of work pressure and stress? What aspects of personality might tend to increase or decrease work pressure and stre..

  What are the information needs at ikon

What are the information needs at Ikon and what alternatives does Ikon have to meet these needs and what are the advantages and disadvantages of ERP software in meeting these needs?

  Entitlement or earned based on performance

Discuss whether or not you believe that discretionary employee benefits should be an entitlement or earned based on performance.

  When congressional committees require

When congressional committees require that agency decisions be submitted to them before the agency implements them,

  Discuss the academic rigor found in the books

Writing block has been a condition that has plagued writers, but it should not have the same kind of paralyzing impact to a researcher because academic writing is the celebration of the research. A researcher is not pulling things from the thin air, ..

  Failure of strategy-implementation efforts

Although there are many marketing variables that impact the success or failure of strategy-implementation efforts, two variables are central to the process. What are these variables? Discuss why they are so important.

  Acquire to satisfy predicted demand under these conditions

A company manufactures a product using machine cells. Each cell has a design capacity of 250 units per day and an effective capacity of 230 units per day. At present, actual output averages 200 units per cell, but the manager estimates that productiv..

  Develop an effective cost estimating proposal

Develop a complete Outline, listing the required steps to develop an effective cost estimating proposal (according to Stewart). A. In Outline Form: 1. Formulate major topics, and necessary sub-topics to describe a detailed C.E. Plan 2. Identify most ..

  Inventory beginning ending average backlog costs

Wormwood, Ltd., produces a variety of furniture products. The planning committee wants to prepare an aggregate plan for the next six months using the following information: Period 1 2 3 4 5 6 Total Forecast 160 150 160 180 170 140 960 Output Regular ..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd