NETWORK DATA
Activity Duration Predecessors
A 6 None
B 12 A
C 10 A
D 9 B,C
E 15 B,C
F 11 B,C
G 3 D
H 8 D
I 10 F
J 6 G
K 5 E,F,H
L 10 I,J,K

Reference no: EM1338043

Questions Cloud

Explain sequestration and small businesses : Explain Sequestration And Small Businesses and How would it affect the business in your plan
Computing the weekly product yield of file cabinets : The percentage of good-quality cabinets averages 83% per week, and the percentage of poor-quality cabinets that can be reworked is 60%. Determine the weekly product yield of file cabinets.
Examining internal resources and value building : Discuss four basic perspectives  when examining internal resources and value building.
Describe any of the internetworking : examine the impact of Global Intellectual Property Law upon the Telecommunication industry and upon businesses. Does it have a positive impact or none at all?
Developing the work flow sequence : Develop the work flow sequence specified in the problem shown below. Do not consider any of the scheduling information provided below in your work.
Define entrepreneurial spirit and starting your own business : Explain Entrepreneurial spirit and starting your own business and What do you think Berkshire Hathaway and Jordan's have each gained from the merge
Cultural influences on early civilizations : What forces contributed to the cultural makeup of early civilizations? What social issues arose because of this cultural makeup?
Process for developing cost estimates : There is a lot of talk about the process for developing cost estimates but the schedule process is not as well defined.
Write a description on supervisor : Think of different supervisors you've worked for. If possible select two: one who shows what you believe are the best qualities of a good manager and one who shows the worst.

Reviews

Write a Review

Project Management Questions & Answers

  Qualitative and quantitative risk analysis

What are the differences between qualitative and quantitative risk analysis? Explain.

  Describing non-numerical factors cause fluctuations

Identify and briefly describe some of the "non-numerical" factors that cause fluctuations in demand for the iPhone 4.

  Process involved in building the wbs

Is there the same kind of team process involved as in building the WBS?

  Calculating annual holding cost rate

Calculate the annual holding cost rate for FFF?

  Spotting irregularities useful for manufacturing companies

Besides spotting irregularities, like the case above, what are some other ways that ABC cost data are useful for manufacturing companies?

  Calculating completion time for the project

Calculate the completion time for the project. (Completion time = weeks)

  Explain purpose and rationale of risk identification process

Explain the purpose and rationale of the risk identification process and discuss the process to review the procurement that should be done during the brainstorming session.

  It project managers and traditional project managers

Then what is the difference between IT project managers and traditional project managers if there are so many similarities in project management discipline?

  Adequacy of project policies-procedures and techniques

Demonstrate the adequacy of project policies, procedures, and techniques.

  Compute the designed capacity and effective capacity

Describe and compute the Designed Capacity and Effective Capacity - Find out and interpret the significance of each three elements in a project

  Individual part of project team as a project manager

If you were a project manager, would you want this individual as part of your project team? What will you do to get him? How should an organization cope with this situation?

  Calculating every contingency cost

Should you, as the project manager, try to control and calculate every contingency cost you can think of?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd