Reference no: EM131229654
A concrete block making company is developing an aggregate capacity plan from the following sales forecast for its 6" and 8" concrete blocks.
Product
Sales Forecasts (Concrete Blocks)
6" Block
1st Quarter (2,000 blocks)
2nd Quarter (1,500 blocks)
3rd Quarter (1,600 blocks)
4th Quarter (1,800 blocks)
8" Block
1st Quarter (1,200 blocks)
2nd Quarter (1,000 blocks)
3rd Quarter (800 blocks)
4th Quarter (1,000 blocks)
Ample machine capacity exists to produce the forecast. Each 6" concrete block takes an average of 20 labour-hours while each 8" concrete block takes an average of 15 labour-hours.
(a) Compute the aggregate number of labour-hours in each quarter.
(b) If each worker works 520 hours per quarter, how many workers will be required in each quarter?
(c) It costs $1,000 to hire a worker and $500 to lay off a worker, and inventory carrying cost is $100 for each 6" concrete block and $100 for each 8" concrete block (this means that if one 6" concrete block were held in inventory for a year, it would cost $100 for finance charge, insurance, warehousing expense, etc.). The plant works the same number of days in each quarter, 13 five-day weeks.
Evaluate two aggregate plans for next year - level strategy with inventory and chase strategy. Beginning inventory is 275 for 6" concrete blocks and 200 for 8" concrete blocks in the level capacity plan and zero for both types of concrete blocks in the matching demand plan. Assume that the quarterly demand pattern repeats from year to year.
Potentially cause for the patient
: Discuss what might happen when two case managers from different organizations both have responsibility for a patient. Under what circumstances might this occur? What problems does it potentially cause for the patient?
|
Describe bona fide occupational qualifications
: Describe bona fide occupational qualifications (BFOQ) and then write a persuasive paper where you argue for or against using BFOQ in the military. Please use research to justify your response.
|
Write an abstract based on your chosen topic
: Write an abstract based on your chosen topic and thesis. Read "What Is an Abstract?" in your Mocule 2 Cover Page and Abstract folder and watch the video "How to Insert a Running Head in Less Than Five Minutes" before starting.
|
How did corporate culture and motivation affect thomas
: How did corporate culture, leadership, power, and motivation affect Thomas' level of managerial hubris? Relate managerial hubris to ethical decision making and the overall impact on the business environment.
|
Developing an aggregate capacity plan
: A concrete block making company is developing an aggregate capacity plan from the following sales forecast for its 6" and 8" concrete blocks.
|
Projected average operating time
: A manager must decide between two machines. The manager will take into account each machine's operating costs and initial costs, and its breakdown and repair times. Machine A has a projected average operating time of 150 hours and a projected aver..
|
How do you think the workers will receive the new structure
: What recommendations and steps of action would you make in making this change? How do you think the workers will receive this new structure?
|
Design a professional development program
: Question: Assume that you have been assigned to design a professional development program to provide y our schools mentor teachers with knowledge about adult learning and development that will be valuable in helping them assist other teachers in t..
|
Local data processing center
: A computer operator at the local data processing center decides to visit work on a Monday evening. She has a key to the outside door, and since there is no key required for the computer room, she simply walks into the computer room.
|