Developing a cost schedule for total project cost

Assignment Help Project Management
Reference no: EM1339539

Q1) Consider the following table of crash times and costs for the above project.

Activity
normal time crash time normal cost crash cost

A 3 1 9000 17000
B 6 3 20000 40000
C 2 1 5000 10000
D 5 3 18000 24000
E 4 3 15000 18500
F 3 1 30000 39000
G 9 4 80000 98000
H 3 2 10000 20000a

In the above table normal and crash times are in weeks. Costs are in dollars and represent the costs associated with the job in the specified period. For instance, Phase A will normally take 3 weeks and cost $9000, OR $3000 PER WEEK. To crash the job to one week, the total cost will be $17000 for the week, thus it will cost $4000 for each week crashed.

a. What is the minimum cost to crash the project one (1) week? What activity will be crashed?

b. What is the least amount of time the project can take if fully crashed? What will the project cost fully crashed?

c. Develop a cost schedule for total project cost from finishing in the normal time to maximum crashing, ie. cost to finish in normal time , cost if crashed one week, cost if crashed two weeks, etc. to minimum time to complete.

Reference no: EM1339539

Questions Cloud

About bracero agreement : Background: The rise of fascist powers and American entry into World War II created a man power shortage in United States.
Explain copyright and privacy in it : Explain Copyright and Privacy in IT and What is the difference between a copyright and a patent on a computer program
Calculate the expected return on the stock : A stock has a beta of 1.05, the expected return on the market is 10% and the risk-free rate is 3.8%. Calculate the expected return on the stock
Illustrate what economic events or changes : Illustrate what economic events or changes will "shift" demand and supply curves, and separately "move" demand or supply along their respective curves.
Developing a cost schedule for total project cost : Develop a cost schedule for total project cost from finishing in the normal time to maximum crashing, ie. cost to finish in normal time , cost if crashed one week, cost if crashed two weeks, etc. to minimum time to complete.
Determine the expected return : Determine the expected return on a portfolio that is equally invested in two assets
Evaluate capital projects : Of the six key methods used to evaluate capital projects, which one do you prefer?
Good practice to acknowledge limitation of research : Many will argue that it is considered a good practice to acknowledge the limitation of your research/project.
Explaining member of a manager-managed llc : Eric is a member of a manager-managed LLC but is not a manager. This LLC invests in real estate and manages it as rental property in a college town.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd