Develop the schedule for the project

Assignment Help Project Management
Reference no: EM133393452

Problem #1:
Imagine on this project you have only two resources who have the exact same skills and can do any of the tasks and when assigned to a task their time is 100% dedicated to the task.

Activity Predecessor Duration Resource
A - 2 2
B A 2 2
C A 3 1
D B, C 4 2
E D 3 1
F A 1 2
G E,F 5 2

Use the tab "Problem 1 Leveling" to provide two schedules:
(1) Develop the schedule for the project and highlight any period where there are resources overallocation issues.
(2) If there are periods that you have overallocated resources, then solve the overallocation issue and present a plan that is feasible (but given this simple project, present a feasible plan that results in the shortest time possible to complete the project).

Problem #2:
The tab "Problem #2 Crashing" - has the information for the project. Answer questions "A" to "F" by completing the tables (make sure to scroll down to find parts: D, E and F. Assume an indirect cost of $250/day and complete the tables provided.

Part B:

YOU MUST INCLUDE ALL POSSIBLE PATHS IN THE TABLE to the left.

Under the column with "path" heading, list the sequence of activities that makes each of the paths (For example KLMN and KPQR, etc). There may be more rows than needed.

Highlight which path(s) is(are) critical (change font size, or font color, or fill the cells with highlight). We must clearly be able to see that you have identified the critical path(s). The same is true for all following steps.

Part C: replace the "?" with the Total cost of the project. Assume an indirect cost of $250/day

Part D:
YOU MUST INCLUDE ALL POSSIBLE PATHS IN THE TABLE.
1st Crash - Reduce the project completion time by one day.
2nd Crash - Reduce the project completion time by one day.

The table to the left should show what you have crashed in each step and the costs. Update path durations as you crash. (watch the video on "Advance Crashing" found under the "Extra Videos" in Canvas, Module 5 - Or watch the live session recording to complete the table correctly.

Part E:
YOU MUST INCLUDE ALL POSSIBLE PATHS IN THE TABLE.
3rd Crash - Reduce the project completion time by one more day.
4th Crash - Reduce the project completion time by one more day.

The table to the left should show what you have crashed in each step and the costs. Update path durations as you crash. (watch the video on "Advance Crashing" found under the "Extra Videos" in Canvas, Module 5 - Or watch the live session recording to complete the table correctly.

Part F:
What is the shortest time to complete this project, how did you get to this timing? (Show your work clearly by filling the table to the left.) There maybe more columns than you need in the table provided.

Attachment:- Ind assignment.rar

Reference no: EM133393452

Questions Cloud

Foundational aspect of content management : Document categorization is an important foundational aspect of content management. Develop a simple document taxonomy for St. Rita's.
What are the 3 principal constituents of seeds : What are the 3 principal (essential) constituents of seeds? From what are they derived? Explain double fertilization. Explain its significance? Discuss the role
Explain what vascular tissue is and what function it has : Create a VENN DIAGRAM that compares and contrasts the similarities and differences between the VASCULAR and NON-VASCULAR plants. Please embed this Venn Diagram
What technique would you use to quantify the amount : You are interested in understanding what brain regions are active when an animal sees (observes) its pair bonded mate. What technique would you use and why?
Develop the schedule for the project : Develop the schedule for the project and highlight any period where there are resources overallocation issues and What is the shortest time to complete
Discuss importance of electrons in the transfer of energy : In your assigned readings, you learned how cells utilize energy. Discuss the importance of electrons in the transfer of energy in living systems.
Describe an occurrence of type of disaster : Describe an occurrence of this type of disaster that occurred within the last 5 years.
Why you think the trait in the scenario is dominant : Explain why you think the trait in the scenario is dominant or recessive. Based upon your response, describe why it would or would not be possible for
Permanent and temporary codes : Provide 10 examples of permanent and temporary codes and a description of what each code is used for. Be clear and concise,

Reviews

Write a Review

Project Management Questions & Answers

  What is the uniform commercial code

What is the Uniform Commercial Code (UCC) responsibility concerning a contractual dispute?

  What are best practices in outsourcing project work

What is outsourcing and what are the advantages/disadvantages of outsourcing - What are the different contract types and their risks (from the contractor

  Create a project charter

Based on research and project selected, create a project charter- The project charter should include the following:- Highlights on how the project you selected meets the selection criteria listed earlier.

  Implement with project rationale and justifications

This assignment requires you to apply what you have learned in the module to use by planning a new project to be implemented in your work place.

  Springville fire department

If you were the project manager, which method of scheduling (Gantt charts/PERT/CPM) would you use?

  How can a firm use the internet and technology

Why do you think stockholders of a firm that is performing very well would prefer that the firm pay only a low percentage of its earnings as dividends?

  What are the ways human resources can keep pace

What are the ways human resources can keep pace and what are the benefits that each provide to the employee and to the employer?

  What is parametric counterpart to wilcoxon signed rank test

What is the parametric counterpart to the Wilcoxon signed rank test for paired samples? Compare the assumptions involved in using the respective tests.

  Find how much would the value of the company change

Show the Change in value of the company if it accepts the replacement project - Find how much would the value of the company change if it accepts the replacement project?

  Discuss ways in which scope creep occurred on projects

BUS 201 University of Nevada, Was the project manager able to reverse scope creep? Is it possible to reverse scope creep and what is the impact?

  Ethical or legal concerns must be in the area of technology

Research and find a company in the realm of business and technology that has encountered a situation where actions or behaviors from either the organization or members of the organization have been considered unethical and legal or ethical and illega..

  Flotation cost as a percentage of funds raised

Raven paid $950,000 in direct legal and other costs and $320,000 in indirect costs. What was the flotation cost as a percentage of funds raised?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd