Develop the project schedule

Assignment Help Management Theories
Reference no: EM131175560

Assessment Task-

Part A: Developing the schedule

For part A of the assessment you must complete the following tasks and questions. Read all the questions before you commence the tasks. The schedule is to be developed in an appropriately named Microsoft Project 2013 file (see the name specified below) and the questions are to be answered in a Word document. As stated above, any assumptions must also be listed at the beginning of the Word document (after the coversheet).

1) Use Microsoft Project 2013 to develop the project schedule. Note that Ms Ellin Jannali has also asked you to include the following in your schedule:

a) The project title as the overall project summary (as task 0 and WBS number 0). All other tasks should be "indented" according to the WBS structure described in the case study.

b) The project name and start date be noted in the Project Information section in Microsoft Project.

c) The Microsoft Project workbook columns are set up as shown below:

d) The task names are to include the WBS identifiers prior to the name in the 'Task Name' column (1.2 Project kick off meeting) and the milestones are to be placed throughout the schedule, with the milestone identifier included at the start of the milestone name in the 'Task Name' column (M1. Initiation Gate: Charter approved). All milestones are to be highlighted yellow.

e) Resource allocation details are included.

f) Holidays are entered.

g) The critical path(s) automatically displayed in red on the bars of the Gantt chart view of your schedule

At this point there may be resource over allocation issues. Do not attempt to resolve these before answering question 2.  Save this version of your schedule asAuminthina_A1.mpp. You will be required to submit this file as part of your assignment submission.

2) At this point ignore any resource over allocations. For the purposes of this question only you can assume that there would be no resource constraints so do not attempt to resolve any resource over allocation (if any exists). Based on your Auminthina_A1.mpp schedule:

a) Use the "view tab" filter to display only the critical tasks. Provide a screenshot showing the task names and the Gantt chart of all the tasks on the critical path(s).

b) Did the annual holidays make any difference to the end date of your project? If so note the previous and changed end date. Explain why/why not there was/was not a change in end date.

c) If you were asked to complete the project 10 days earlier by reducing the duration of some of the tasks in the project. Fill in the table below stating what tasks you will reduce the duration of, by how much and how you will reduce the duration of each task.

d) Create a new version of the schedule with the changes you outlined in part (c) highlighted blue using the "background colour" icon on the task ribbon. Make sure that your changes have reduced the project duration by 10 days. Call this file Auminthina_A2.mpp. You will be required to submit this file as part of your assignment submission. This file is not to be modified/developed further.

3) Create another copy of your original question 1, Auminthina_A1.mpp in another file called AuminthinaA3.mpp. In this question, unlike question 2, assume that you will not have any additional resources assigned to the project even if there are resource over allocation issues. If your schedule had any resource over-allocation issues resolve these in thePartAQ3_resources.mpp file without adding any additional resources. For this assignment, do not "split tasks". Save this "modified" version of Auminthina_A3.mpp file. You will be required to submit the Auminthina_A3.mpp fileas part of your assignment submission.

a) Describe how you used (or how you would have used Microsoft Project) to resolve any resource over-allocation issues.

b) Does the fact that you cannot have any additional resources for this project have any impact on your project duration and end date? Explain.

4) Continue working with Auminthina_A3.mpp. In this file, include two additional milestone "markers" to show the following notifications:

a) The Architectural Reference Group needs notification and papers to be sent out five business days prior to being able to approve the detailed design (M3). Continue working with Auminthina_A3.mpp. In this file, include an additional milestone "marker" called 'N1 ARG Design Gate Notification' to highlight the latest date that the project manager should contact the Architectural Reference Group to provide notification and papers. The papers will consider of the Prototype detailed design documents that are created in task 3.5 Prototype detailed design.

i) According to Auminthina_A3.mppwhat is the latest date that notification and papers can be sent to the Architectural Reference Group?

ii) Is there an issue between the dates for notification and finalising the Prototype Detailed Design (3.5).

b) The Project Board needs notification and papers to be sent out ten business days prior to being able to approve GoLive (M6). Continue working with Auminthina_A3.mpp. In this file, include an additional milestone "marker" named 'N2 Project Board GoLive Gate Notification' to highlight the latest date that the project manager should contact the Project Board to provide notification and papers.

i) According to Auminthina_A3.mppwhat is the latest date that notification and papers can be sent to the Project Board?

Make sure that these new milestones have the appropriate predecessor relationships so that the dates will be automatically adjusted if there is any change to the schedule. On your schedule, highlight the rows that include these milestones in blue. This change is to be saved in your Auminthina_A3.mpp file.

5) Write a memo to the CEO, Ms Ellin Jannali, providing your project proposal and include following information:

a) an explanation of the project need and what it is trying to achieve.

b) the expected completion date of the project, assuming it commences on 1/10/16;

c) the total duration of the project;

d) an explanation of the main factors that cause the project to require that length of time and any recommendations that you might make if time was a priority for the project;

e) the estimated labourcosts for each of the resource types working on the project. Present the costs in a table similar to the following:

Table 5 - Labour Costs

Resource Name

Cost ($)

Business Analyst

 

Software Engineer

 

Test Engineer

 

Project Manager

 

Marketing Manager

 

Project Officer

 

Total labour costs:

 

Assume that you will send the project schedule (Auminthina_A3.mpp) as an attachment to the memo.  The information in the memo should correspond to the attached schedule. Some notes regarding memos can be found on the course website in the same area as this specification.

Part B: Modifying the schedule

Ms Ellin Jannali reviews your project proposal including the attached schedule and advices you you're your project has been chosen however requires some changes.

  • She states only one Software Engineer will be available for the project.
  • The task '3.1 Prototype basic design' needs to be reduced to 30 days.
  • The task '10.2 Close procurement' needs to be reduced to 1 day.

Based on the information given above complete the following tasks:

1. Copy your AuminthinaA3.mpp file into a file called Auminthina_B.mpp file. Amend the project schedule in your new Auminthina_B.mpp file incorporating the change requests from Ms Ellin Jannali. If this has created any resource over allocation issues resolve these before progressing to the next question. Save the changes. The Auminthina_B.mppfile is also to be included as part of your final assignment submission.

Have the changes impacted on the duration or costs of your project and if so in what way? Be very precise in your answering of questions 2 and 3 below. If the project is longer or shorter state the previous finish date the new end date and by how much the project has been shortened or lengthened. If the changes had an impact on the cost, mention what the previous cost was and what the cost was after the change and explain why there was or was not an impact.

2. Describe the impact of each of these changes on the project duration in a table similar to the following:

Table 6 - Impacts of Changes to Project Duration

Change

Impact on project duration

(longer, shorter or no impact)

By how much

Explanation

Reduction to one Software Engineer

 

 

 

Change to the duration of '3.1 Prototype basic design'

 

 

 

Change to the duration of '10.2 Close procurement'

 

 

 

Note that if a combination of the changes have had an additional impact that would not have occurred if the change was made in isolation clarify this in your explanation.

3. Describe the impact of each of these changes on the labour costs  for the projectin a table similar to the following:

Table 6 - Impacts of Changes to Labour Costs

Change

Impact on labour costs

(more, less or no impact)

By how much

Explanation

Reduction to one Software Engineer

 

 

 

Change to the duration of '3.1 Prototype basic design'

 

 

 

Change to the duration of '10.2 Close procurement'

 

 

 

Part C: Tracking Progress

In this part of the assignment you are to imagine that your project is underway and that it is time to produce one of a project performance report.

1. Copy Auminthina_B.mpp to Auminthina_C.mpp. Save the baseline for this version of your project.

2. You are back at work after the Christmas and New Years holidays. You are writing the project performance report for the period from the start of the project to the end of December 2016. You review the information provided to you by your project staff on the progress of the project and need to update your schedule accordingly. In your Auminthina_C.mpp file

a. Set the current date to 3January 2017, the status date to 31December 2016and include a solid, purple status date gridline in your project to ensure the status date is clearly visible in your Gantt Charts.

3. Most of the tasks up to the 31 December 2017, were completed as per the schedule. However the following data represents information on tasks where the performance was different to what was planned.

Attachment:- Assignment.rar

Reference no: EM131175560

Questions Cloud

Identify profitability ratio that creditor may be interested : Identify three profitability ratios that creditors may be interested in. Calculate the ratio for each company, and prepare a report to summarize your findings on the financial health of each company.
Find the rate at which the pressure is changing : For a particular gas it is known that when the pressure is 10,000 psi, its volume is 4 cubic inches. If the volume is increasing at 8 cubic inches per second, find the rate at which the pressure is changing when the pressure is 20,000 psi.
Find the approximate cost of producing the 30th toaster-oven : If the total cost of producing x toaster-ovens is given by the formula C1x2 = 40 + 12x + 0.2x2 find the approximate cost of producing the 30th toaster-oven.
Explore how a time driven abc cost system can be implemented : Discuss how a time driven ABC cost system can be implemented in the company you researched and the benefits that the use will yield to the business performance.
Develop the project schedule : Use Microsoft Project 2013 to develop the project schedule. Note that Ms Ellin Jannali has also asked you to include the following in your schedule: The project title as the overall project summary (as task 0 and WBS number 0). All other tasks sho..
Prepare a flexible budget for april : determined the following cost formulas and gathered the following actual cost data for April:  -Prepare a report showing the spending variances for April.- Prepare a flexible budget for April.
What monthly interest rate r is the bank charging : An $8,000 car loan is paid off with $250 monthly payments over three years, what monthly interest rate r is the bank charging? It can be shown that this problem translates into the equation
Differences between wired and wireless communications : Describe your perspective on communication technology such as wireless communication, the Internet, and smart phone technology. Provide at least three examples of communication technology you use in your daily life. Examine the underlying scientifi..
Identify the data collection methods used in that research : Identify the data collection methods used in that research and analyze that data, evaluate its validity, and then draw conclusions from it in the form of a summary.

Reviews

Write a Review

Management Theories Questions & Answers

  Provide environmental scanning of current conditions

Provide environmental scanning of current conditions in the area of expansion including economy, competition, political stability, and so forth

  Describe creativity, innovation, and the rules of innovation

Describe creativity, innovation, and the rules of innovation in your own words. Include the following in your response: One real-life management example of using creative intelligence One real-life management example of innovation

  Examine the relevance of the different techniques

Examine the relevance of the different techniques used to forecast the human resources available to an organization.

  Challenges of managing a virtual team

The challenges of managing a virtual team stem from the fact that a virtual team might span functional areas, time zones, geographic locations, languages, and cultures. Many people feel that communication is the biggest challenge of managing a vir..

  Observation and experience or use your knowledge gained

Aggregate planning involves having several production strategies which often are determined through trial and error. Staffing is one such area that can prove particularly difficult, especially with service firms where the cost of labor must be co..

  What do we mean by the term value innovation

What do we mean by the term value innovation? Can you identify a company not discussed in the text that has established a strong competitive position through value innovation?

  Further the role that benefits play in recruiting

let's consider further the role that benefits play in recruiting. Put yourself in the role of your organization's recruiter, what benefits might you use to attract Generation X and Y employees (under 45 years of age)? How do the benefits differ from ..

  Lean thinking identify processes in organisation you know

lean thinking identify processes in organisation you know well that could benefit from the kind of changes introduced

  The key words for this research exercise are information

the key words for this research exercise are information security personnel. go to the erau hunt library or locate

  Define vertical integration and horizontal integration

B203A -- explain the supply chain for Zara from raw material to consumer purchase and What are the disadvantages of Zara's "fast fashion" distribution system

  Communication is a process of deciding at the top

How much of your communication is a process of deciding at the top

  How the cango company has a problem with time management

Then write a 400 word summary in APA format about how the CanGo Company has a problem with Time Management and your recommendation to fix the issue with time management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd