Develop the decision tree to maximize ventrons expected

Assignment Help Computer Engineering
Reference no: EM132177425

Question ;

The Ventron Engineering Company has just been awarded a $2 million development contract by the US Army Aviation Systems Command to develop a blade spar for their Heavy Lift Helicopter program.

The blade spar is a metal tube that runs the length of, and provides strength to, the helicopter blade. Due to the unusual length and size of the heavy lift helicopter blade Ventron is unable to produce a single piece of the required dimensions using existing extrusion equipment and material.

The Engineering Department has prepared two alternatives for developing the blade spar: (1) sectioning or (2) an improved extrusion process. Ventron must decide which process to use. Backing out of the contract at any point is not an option. A risk report has been prepared by the engineering department. The information from this report is explained next.

The sectioning option involves joining several shorter lengths of extruded metal into a blade spar of sufficient length. This work will require extensive testing and rework over a 12 month period at a total cost of $1.8 million. Although this process will definitely produce an adequate blade spar, it merely represents an extension of existing technology.

To improve the extrusion process, on the other hand, it will be necessary to perform two steps: 1) improve the material used at a cost of $300,000, and 2) modify the extrusion process at a cost of $960,000. The first step will require six months of work and, if the first step is successful, the second step will require another six months of work. If both steps are successful the blade spar will be available at that time, that is, a year from now.

The engineers estimate that the probabilities of succeeding in steps one and two are to 0.9 and 0.75 respectively. However if either step is unsuccessful which will be known only in six months for step one and in a year for step two, Ventron will have no alternative but to switch to the sectioning process and incur the sectioning cost on top of any costs already incurred.

Development of the blade spar must be completed within 18 months to avoid holding up the rest of the contract. If necessary the sectioning work can be done on an accelerated basis in a six-month period but the cost of sectioning will increase from $1.8 million to $2.4 million.

The Director of Engineering, Dr. Smith, wants to try developing the improved extrusion process. He reasons that this is not only cheaper for the present project but if successful its expected side benefits for future projects could be sizable. Although the side benefits are difficult to gauge Dr. Smith's best guess is an additional $2 million. Of course, these side benefits are obtained only if both steps of the modified extrusion process are completed successfully.

1. Develop the decision tree to maximize Ventron's expected monetary value (EMV). This includes the revenue from this project, the side benefits, if applicable, from the extrusion process, and relevant costs. You don't need to worry about the time value of money; that is, no discounting or net present values are required.

2. What value of side benefits would make Ventron indifferent between the two alternatives?

3. How much would Ventron be willing to pay right now for perfect information about both steps of the improved extrusion process? (this information would tell Ventron, right now the ultimate success or failure of both steps.)

Reference no: EM132177425

Questions Cloud

Set plenty of time aside to complete the lab : Set plenty of time aside to complete the lab, preferably in a single session with no distractions. You will notice a number of questions presented to you.
What is the standard deviation of the sample mean : What is the standard deviation of the sample mean? See pages 206-207 in your text.
Why is it that virtual memory paging does not suffer : Why is it that virtual memory paging does not suffer from external fragmentation and virtual memory segmentation does not suffer from internal fragmentation?
Develop a mathematical formulation of the problem : MPE0507 - Process Plant Optimization and Economics - Caledonian college of engineering - Explain various methods of network analysis applicable
Develop the decision tree to maximize ventrons expected : What value of side benefits would make Ventron indifferent between the two alternatives?
Calculate the profit-maximizing price : Using existing market research, we were able to calculate an estimated own-price elasticity of demand for a number of our most popular cable channels
Write a function with a header def verbalize num : Write a function with a header def verbalize number (number): that accepts a positive whole number with at most 27 digits as input.
Create a parse tree that shows that the string can be : A string of characters belongs to a language defined by a grammar, we must create a parse tree that shows that the string can be generated by the grammar.
What is the corresponding average total cost : (a) What is the corresponding average total cost (ATC) function? (b) What is the corresponding short-run marginal cost (SMC) function?

Reviews

Write a Review

Computer Engineering Questions & Answers

  Mathematics in computing

Binary search tree, and postorder and preorder traversal Determine the shortest path in Graph

  Ict governance

ICT is defined as the term of Information and communication technologies, it is diverse set of technical tools and resources used by the government agencies to communicate and produce, circulate, store, and manage all information.

  Implementation of memory management

Assignment covers the following eight topics and explore the implementation of memory management, processes and threads.

  Realize business and organizational data storage

Realize business and organizational data storage and fast access times are much more important than they have ever been. Compare and contrast magnetic tapes, magnetic disks, optical discs

  What is the protocol overhead

What are the advantages of using a compiled language over an interpreted one? Under what circumstances would you select to use an interpreted language?

  Implementation of memory management

Paper describes about memory management. How memory is used in executing programs and its critical support for applications.

  Define open and closed loop control systems

Define open and closed loop cotrol systems.Explain difference between time varying and time invariant control system wth suitable example.

  Prepare a proposal to deploy windows server

Prepare a proposal to deploy Windows Server onto an existing network based on the provided scenario.

  Security policy document project

Analyze security requirements and develop a security policy

  Write a procedure that produces independent stack objects

Write a procedure (make-stack) that produces independent stack objects, using a message-passing style, e.g.

  Define a suitable functional unit

Define a suitable functional unit for a comparative study between two different types of paint.

  Calculate yield to maturity and bond prices

Calculate yield to maturity (YTM) and bond prices

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd