Develop the budget for project by allocating cost over

Assignment Help Operation Management
Reference no: EM13232657

Assume that you have been selected to serve as the project manager for a management consulting project for a client based in the United States. You have developed the WBS and listed the activities for the assignment, which involve large-scale market research in a new market. You are responsible for project costs and are keen on developing realistic cost estimates and project budget. You have estimated the following effort:

WBS

Tasks

Duration

Resource Type

Effort in Days

1.1

Final proposal and contract documentation

4 Days

Junior Consultant

4




Legal Consultant

1




Vice President

1

1.2

Assignment kickoff workshop

2 Days

Junior Consultant

2




Senior Consultant

1




Vice President

1

2.1

Designing market research

5 Days

Product Expert

1




Junior Consultant

5




Senior Consultant

2

2.2

Pilot run of market research

10 Days

Junior Consultant

3




Intern

10




Senior Consultant

2

2.3

Final market research design and signoff

2 Days

Junior Consultant

2




Senior Consultant

1




Vice President

1

2.4

Market research 1

32 Days

Junior Consultant

20




Senior Consultant

2




2 Interns*

28

2.5

Market research 2

32 Days

Junior Consultant

20




Senior Consultant

2




2 Interns*

28

2.6

Data collation and analysis

5 Days

Junior Consultant

5




Senior Consultant

3




2 Interns*

5




Vice President

0.5

3.1

Final report preparation

3 Days

Senior Consultant

3




Junior Consultant

3




Vice President

0.5

3.2

Presentation to client

1 Day

Senior Consultant

1




Junior Consultant

1




Vice President

0.5

*Please note the use of 2 resources in this case.
The rates per day for the resources are as follows:

Resource

Rate Per Day

Junior Consultant

$750

Intern

$250

Legal Consultant

$1,500

Product Expert

$3,500

Senior Consultant

$1,500

Vice President

$3,500


The tasks above are listed in sequential order. The exceptions are market research 1 and 2, which can start simultaneously.

Part 1:
Develop the budget for this project by allocating cost over actual work time and the calendar time line. Draw a graph for the time line of the project and the money spent on the project. Assume that the payments to all resources are made on a daily basis.

Part 2:
For the consulting assignment, assume that the total project budget is spent equally on a daily basis and the work done each day contributes equally toward the project completion. You are now at the end of Day 25 of the project, the company has already spent $48,000, and the project has delivered 5% more than planned at the end of Day 25.

  • What is your assessment of the schedule performance index (SPI) and cost performance index (CPI) of the project? What actions or corrective actions would you want to take, keeping in mind the project performance so far?
  • How much more money must be spent to complete the project, and what would be the total cost of the project when it is completed, as per the details given?

Reference no: EM13232657

Questions Cloud

What is the cause of disputes and the contractual means : What is the cause of disputes and the contractual means used for resolving them?
Examine arbitration as a quasi judicial process : Examine arbitration as a quasi judicial process in which parties agree to submit unresolved disputes to a neutral third party for binding settlement. Explain the labor- contractual negotiations in detail.
How do you write a program that compares your checking : How do you write a program named Balance.java that compares your checking account balance with your savings account balance (two doubles)
Explain what is the capacity of the buffer : a buffer is created by mixing 26 mL of 3.3M sodium formate and 16 mL of 3 M formic acid. What is the capacity of the buffer if 0.2 M NaOH is added?
Develop the budget for project by allocating cost over : Develop the budget for project by allocating cost over actual work time and the calendar time line. Draw a graph for the time line of the project and the money spent on the project.
Define the result of doubling the initial concentration of x : The reaction x = Y is first -order overall and first-order with respect to the reactant x. The result of doubling the initial concentration of X will be to
Explain how many moles of strong base : consider a .7 L of a buffer composed of 0.4 M HClO and 0.5 NaClO? How many moles of strong base could this buffer withstand?
Are business mergers good or bad for the economy : (a) What is market concentration and how can you know whether a market is concentrated or not (b) What are the causes of market concentration (c) Are business mergers good or bad for the economy Explain why
How fiscal policy would affect aggregate demand : Can you explain how FISCAL POLICY (making changes to government spending and taxes) would affect Aggregate Demand (AD) How do these two mechanisms of expansionary policy differ

Reviews

Write a Review

Operation Management Questions & Answers

  Which communication medium would you use

Assume that you are about to ask your supervisor for a raise. Which communication medium or channel would you use?

  Determine the most effective way that project metrics

Determine the most effective way that project metrics and portfolio management can facilitate Information management / Information Technology

  Calculate total cost curves

Kelly Trucking, Inc., is planning a new warehouse to serve the western United States. Denver, Santa Fe, and Salt Lake City are under consideration.

  Calculate the mad

Calculate the MAD, the MAPE, the MSE and the tracking signal for Forecast 1

  Discuss how supply and demand four degrees of competition

Discuss how supply and demand would be affected under each of the four degrees of competition

  Defend a hot babe used to sell cars on a tv commercial

which is immoral. Is this valid? Defend a hot babe used to sell cars on a TV commercial. Defend requiring women to cover their bodies.

  Assess wal-marts attempt to restore its public image

Why do you think that Wal-Mart had so many events that caused its image to be tarnished?

  Elucidate how could vincent weafer use technical

Elucidate how could Vincent Weafer use technical, human also conceptual skills to maintain an environment that encourages innovation also professionalism among the virus hunters.

  Cut costs and expect the quality of healthcare

Let me ask you this. At what point in time can we continue to cut costs and expect the quality of healthcare in the United States to remain as good as it is

  Explain the best strategic planning and implementation

Explain the BEST strategic planning and implementation/execution you have observed. Discuss fully. (2) Explain the WORST strategic planning and implementation?

  Explain disadvantages and advantages of using primary data

What are the disadvantages and advantages of using primary data? What can a market researcher do to lower the threats of privacy?

  Johnson industries received a contract to develop

Johnson Industries received a contract to develop and produce four high intensity long distance receiver/transmitters for cellular telephones. The first took 2000 labor hours

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd