Assume that you have been selected to serve as the project manager for a management consulting project for a client based in the United States. You have developed the WBS and listed the activities for the assignment, which involve large-scale market research in a new market. You are responsible for project costs and are keen on developing realistic cost estimates and project budget. You have estimated the following effort:
WBS
Tasks
Duration
Resource Type
Effort in Days
1.1
Final proposal and contract documentation
4 Days
Junior Consultant
4
Legal Consultant
1
Vice President
1.2
Assignment kickoff workshop
2 Days
2
Senior Consultant
2.1
Designing market research
5 Days
Product Expert
5
2.2
Pilot run of market research
10 Days
3
Intern
10
2.3
Final market research design and signoff
2.4
Market research 1
32 Days
20
2 Interns*
28
2.5
Market research 2
2.6
Data collation and analysis
0.5
3.1
Final report preparation
3 Days
3.2
Presentation to client
1 Day
*Please note the use of 2 resources in this case. The rates per day for the resources are as follows:
Resource
Rate Per Day
$750
$250
$1,500
$3,500
The tasks above are listed in sequential order. The exceptions are market research 1 and 2, which can start simultaneously.
Part 1: Develop the budget for this project by allocating cost over actual work time and the calendar time line. Draw a graph for the time line of the project and the money spent on the project. Assume that the payments to all resources are made on a daily basis.
Part 2: For the consulting assignment, assume that the total project budget is spent equally on a daily basis and the work done each day contributes equally toward the project completion. You are now at the end of Day 25 of the project, the company has already spent $48,000, and the project has delivered 5% more than planned at the end of Day 25.
Assume that you are about to ask your supervisor for a raise. Which communication medium or channel would you use?
Determine the most effective way that project metrics and portfolio management can facilitate Information management / Information Technology
Kelly Trucking, Inc., is planning a new warehouse to serve the western United States. Denver, Santa Fe, and Salt Lake City are under consideration.
Calculate the MAD, the MAPE, the MSE and the tracking signal for Forecast 1
Discuss how supply and demand would be affected under each of the four degrees of competition
which is immoral. Is this valid? Defend a hot babe used to sell cars on a TV commercial. Defend requiring women to cover their bodies.
Why do you think that Wal-Mart had so many events that caused its image to be tarnished?
Elucidate how could Vincent Weafer use technical, human also conceptual skills to maintain an environment that encourages innovation also professionalism among the virus hunters.
Let me ask you this. At what point in time can we continue to cut costs and expect the quality of healthcare in the United States to remain as good as it is
Explain the BEST strategic planning and implementation/execution you have observed. Discuss fully. (2) Explain the WORST strategic planning and implementation?
What are the disadvantages and advantages of using primary data? What can a market researcher do to lower the threats of privacy?
Johnson Industries received a contract to develop and produce four high intensity long distance receiver/transmitters for cellular telephones. The first took 2000 labor hours
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd