QUESTION 1:

  1. Tallahassee Company is considering an investment in a high-quality blueprint printerwith the following cash flows:

YEAR

INVESTMENT/CEDIS

CASH INFLOW/CEDIS

1

(38000)

2000

2

(6000)

4000

3

 

8000

4

 

9000

5

 

12000

6

 

10000

7

 

8000

8

 

6000

9

 

5000

Required:

i) Determine the payback period of the investment.

ii) Would the payback period be affected if the cash inflow in year 8 was18,000Cedis?       

  1. Given the expected net cash flow of projects X and Y in the table below, answer the questions that follow:

YEAR

PROJECT X

PROJECT Y

0

(10000)

(10000)

1

6500

3500

2

3000

3500

3

3000

3500

4

1000

3500

Required:

      i. Calculate for each, the payback period, net present value (NPV),and profitability index (PI). Use 10% discount rate.

      ii. Should both projects be accepted if they are interdependent?

      iii.  Which project should be accepted if they are mutually exclusive?

QUESTION 2:

Given the table below, calculate the EXPECTED VALUE OF PERFECT INFORMATION (EVPI) and EXPECTED OPPORTUNITY LOSS (EOL) using maximization approach. What is the relation between EVPI and EOL?

NB.: di=decision alternative, Si=states of nature, and probabilities are probabilities of state of nature.


s1

s2

s3

d1

6

5

3

d2

1

4

7

d3

3

8

9

Probability

0.4

0.1

0.5

QUESTION 3:

What is the difference between operational and technical feasibility? At the project planning phase, detailed plans are made to help complete the project successfully. Name 8 of them and explain. Name three main ways of IT project deployment. What does project close entails?

QUESTION 4:

a. What is a project? State 3 attributes of a project.

b. When is a project said to be successful?

c. What is the project management life cycle?

d. In determining project feasibility at the initiation stage or phase, list 3 out of the many factors to consider.

e. List 4 causes of project failure at the initiation stage?

f. Name 6 members of the project team that are assembled at the planning stage.

QUESTION 5:

A project consists of eight activities whose durations are as follows:

Activity

A

B

C

D

E

F

G

H

Duration

2

3

5

6

1

3

1

7

The precedence relations are as follows:

B must follow A

C must follow B

D must follow A, B and C

E must follow D

F must follow C

G must follow E and F

H must follow E and G 

QUESTIONS

a. Draw a project network

b. Develop the activity schedule for the project

c. Identify the critical path

d. What is the expected completion time for the project?

Reference no: EM13671065

Questions Cloud

What sense is the marketplace cruelly capricious : What sense is the marketplace cruelly capricious - One of the important things.is to counter the notion that big corporations are faceless machines
An analysis of the implications for nurses : Provide an overview of the Meaningful Use program and an analysis of the implications for nurses, nursing, national health policy, patient outcomes, and population health associated with the collection and use of Meaningful Use core criteria.
Describe normal health patterns of the client : Describe any observed or potential cultural, geographic, religious, ethnic, or spiritual considerations of this client and describe two normal health patterns of the client as well as two abnormal health patterns that you observe, and provide exampl..
Analyse data from a recent observational study of ageing : What analyses you performed - your description of the results should be sufficiently clear that the reader could reproduce your results
Develop the activity schedule for the project : Draw a project network, develop the activity schedule for the project and identify the critical path
Which outcomes are pareto efficient : Which outcomes are Pareto efficient
What are the factors that underlie a nation decision : What are the factors that underlie a nation's decision to allow its currency to be determined by free market forces or to be fixed against some standard of value?
The supply function for x units of a particular commodity : A manufacturer determines that the supply function for x units of a particular commodity is S(x)=In (x+2) and the corresponding demand function is D(x)=10+In(x-1).Find the demand price when the level of production is x=10units
Define the number of baskets of apples : Define the number of baskets of apples and bananas produced as QA

Reviews

Write a Review

Project Management Questions & Answers

  Excess spending in project management

In reviewing the budget report of a project you notice that spending on the project is running about ten percent over plan

  Contingency planning and risk identification - how does

contingency planning and risk identification - how does risk identification help with project contingency planning?

  Project sponsorship and leadershipa project manager needs

project sponsorship and leadershipa project manager needs to understand how to escalate issues and decisions at the

  Risk on information technology project

Find an example of a company that took a big risk on an information technology project and succeeded.

  Discuss the various methods for selecting projects which

project integration management please respond to the followingdiscuss the various methods for selecting projects. which

  Explain the six methods for estimating task duration

Explain the six methods for estimating task duration and show how each method affects the accuracy of task duration estimates.

  Calculating project-s annual project free cash flow

Assuming the firm faces a 30% tax rate, calculate the project's annual project free cash flow (FCF) for each of the next five years.

  Some believe that a project management office pmo is

some believe that a project management office pmo is nothing more than yet another level of management with the

  Explain the disruptive force and organizations response

Examine a change you experienced that was initiated by a disruptive force and explain the disruptive force and the organization's response to meet the challenge.

  Calculate the slack associated in the given casegiven this

calculate the slack associated in the given casegiven this information about an activity es 10 ef 15 ls 26 and lf

  Using the cut-and-try method for aggregate operations

Using the cut-and-try method for aggregate operations planning we can determine the production requirement in units of product. If the beginning inventory is 100 units

  What is the required cycle time in minutes per unit

what is the required cycle time in minutes per unit if the daily production time is 480 minutes and the required daily output is 50 units?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd