Reference no: EM131106873
Unit VI Project
This assignment consists of four parts.
Please label each part of the assignment Part 1, Part 2, Part 3, and Part 4 in the document, and insert a page break after each part. Please submit as one document.Note: This assignment requires the use of MS Project or similar software. If you do not have MS Project or similar software, you may look for free or trial versions on the Internet.
Part 1:Develop an in-depth schedule for your initial project based on the Work Breakdown Structure you completed in Unit III. Please refer to the Integrated Project in Chapter 10 of the textbook on page 318 for more information. (40 points total)Be sure to include:
1.An activity precedence diagram
2.An activity duration table
3.A network diagram and Gantt charts
Part 2:Please complete Case Study 10.2, "Project Scheduling at Blanque Check Construction" on pages 315 and 316 in the textbook and respond to the questions for discussion. Please make sure that each question is answered thoroughly using a minimum of 200 words for each case study question.
Part 3:Develop the network activity chart and identify the critical path for a project based on the information provided in the Gantt Chart Activity document. To access the Gantt chart activity document, click here.
1.Draw the activity network as a Gantt chart.
2.What is the expected duration of the project?
MBA 6961,Project Management4
Part 4:Consider the project with the information provided in the Project Activity Network document. To access the Project Activity document, click here or on the link above.
1.Construct the project activity network using AON methodology and label each node.
2.Identify the critical path and other paths through the network.
How can a teacher become more sensitive to the students
: Is it possible for a teacher to ensure all of the ethnic and cultural needs of the different students in the classroom are met? Explain. How can a teacher become more sensitive to the students and their needs?
|
Sketch this exponential probability distribution
: 1. The time between arrivals of vehicles at a particular intersection follows an exponential probability distribution with a mean of 12 seconds.
|
Determine the range for the rate of return
: Determine the range for the rate of return for each of the two cameras. Determine the expected value of return for each camera. Purchase of which camera is riskier?Why?
|
Find a partner
: To relieve some programming burden, project 5 is a group project that two students can form a group to do and submit one report. In your submitted report, please specify who is your partner. Of course, you can do this project alone if you want to or ..
|
Develop an in-depth schedule for your initial project
: This assignment consists of four parts. Please label each part of the assignment Part 1, Part 2, Part 3, and Part 4 in the document, and insert a page break after each part. Please submit as one document.Note:
|
Describing how the website relates and supports
: Write a 500 - word summary describing how the website relates and supports the 21st Century security challenges that GAO has identified for Homeland Security.
|
Regression and inferential statistics
: An airline has an advertisement that states: "...our passengers always receive their bags within 20 minutes after the plane arrives at the gate." Discuss the hypothesis that they might have used and write another one that could show this to be inc..
|
Determine the range of the rates of return
: a. Determine the range of the rates of return for each of the two projects.b. Which project is less risky? Why?
|
Explain the operation of the approximate dynamic programming
: Correspondingly Table P12.16 presents a summary of the approximate Q-learning algorithm. Explain the operation of the approximate dynamic programming scheme of Fig. P12.20 to justify the summary presented in Table P12.16.
|